1. The
Case Stated herein by Mrs Justice McGuinness on the 30th day of October 1997
for the opinion of this Court raises an important and novel question as to the
extent to which development - and more particularly
“works”
-
commenced before the 1st day of October 1964
(“the
appointed day”)
is
excluded from the scope of the Local Government (Planning and Development) Act
1963 by virtue of the provisions of s.24 of that Act.
2. The
circumstances in which the particular question arises are set out in detail in
the case stated but may be summarised as follows. By an agreement in writing
dated the 16th September 1952
Richard
Looby granted a licence to Agricultural Limestone Limited
to
dig. Process, remove and carry away limestone”
from
that part of the lands of Kilgrainey in the County of Waterford containing
approximately eight acres and delineated on the map annexed thereto. It appears
that Agricultural Limestone Limited commenced quarrying shortly after the date
of that agreement but was taken over by the Respondents herein, John A
3. Wood
Limited, in or about 1969. The eight acres comprised in the 1952
Agreement
may be conveniently described as
“the
original Looby lands
“.
By an indenture of lease dated the 5th day of September 1972 made between the
said Richard Looby of the one part and the Respondents of the other part the
said Richard Looby demised to the Respondents a further part of the lands of
Kilgrainey comprising some thirty-six acres for a term of forty years from the
1st day of January 1970 subject to the various royalty charges thereby
reserved. The lands comprised in the 1972 lease may be described as
“the
additional Looby lands”
.
In 1986 the Respondents purchased from a Mr Doyle further lands in the town
land of Kilgrainey. The conveyance by Mr Doyle is not annexed to the case
stated and does not appear to have been exhibited in the High Court
proceedings. However, Counsel on behalf of the Respondent explained that the
lands included in the 1986 conveyance comprised some ninety-six acres of which
only approximately forty acres contained limestone suitable for quarrying. It
may be relevant to note that it was further explained that the additional fifty
acres approximately were acquired from Mr Doyle because he was unwilling to
dispose of the limestone-bearing land separate from the remainder of his take.
4. It
is common case that on the appointed day the Respondents were quarrying the
original Looby lands and extracting limestone therefrom. Again, it was common
case that after the acquisition of the additional Looby lands the Respondents
extracted limestone therefrom without any apparent objection from the planning
authority. It was only when the Respondents commenced quarrying operations on
the Doyle lands in 1995 that proceedings were threatened and ultimately brought
by the Waterford County Council as the planning authority for the county of
Waterford. The proceedings were brought under s.27 of the Local Government
(Planning and Development) Act 1976 and on the 16th November 1995 the learned
Judge of the Circuit Court refused to grant an injunction restraining the
Respondents
5. The
physical features and more particularly the boundaries of the Looby lands and
the Doyle lands are material partly because disputes in relation thereto may
have brought the matter to the attention of the planning authority and partly
because these boundaries may be of relevance in answering the question posed by
the learned trial Judge.
6. It
appears that the entire of the Looby lands and that part of the Doyle lands
containing recoverable deposits of limestone are all situate within the town
land of Kilgrainey, County Waterford and that the combined land holding is
bounded on the north by the White Church Road and on the south by the Canty
Road. The Looby lands and the Doyle lands are separated by a boithrín
which connects the White Church Road to the Canty Road. Local residents
contended that there was a public right of way over this boithrín.
Whether such a right existed was never finally determined because a sensible
agreement appears to have been reached with the local residents involved under
which the route was to be maintained subject to the right of the Respondents to
close it off from time to time in the interests of safety. That there was and
is a modest route, fairly described as a boithrín, separating the Looby
lands from the Doyle lands is an objective fact. Finally in relation to
material facts, it is important to note that the seam of limestone which had
been identified in the original Looby lands in fact extended for a distance of
some six miles.
7. The
Respondents submitted - no doubt correctly - that the issue in the present case
did not involve any question as to what constituted
“exempted
developments”
within
the meaning or for the purposes of section 4 of the 1963 Act. The issue in this
case concerned the proper interpretation of s.24 of that Act which, so far as
material, provides as follows:
8. ““Development”
in this Act means, save where the context otherwise requires, the carrying out
of any works on, in, or under land or the making of any material change in the
use of any structures or other land.”
10. Counsel
on behalf of the Respondents contended, first, that quarrying of the seam of
limestone having commenced before and continuing at the appointed day there was
no obligation to obtain planning permission for the continuation of those works
even if they were to continue for many years and over a very substantial area.
Alternatively, the Respondents contended, they are entitled to continue works
which were
“a
natural and logical extension of the development which existed before the
appointed day”
.
This was an expression taken from views expressed by the late Eamonn Walsh when
a senior counsel and author of an authoritative book on planning law but before
his appointment to the Bench. In the views expressed by him and adopted by
counsel on behalf of the Respondents he went on to explain that what he meant
by the expression aforesaid was
“that
it could also have been reasonably anticipated that the development would
progress to this point”.
He
pointed out that one would have to disregard the apparent change of use in the
sense that land which had formerly been used for agricultural purpose was being
swallowed up by the advance of the extraction programme.
11. However,
Mr Justice Walsh in the views expressed by him did state that some limitation
must be imposed on the extent to which works that had started might be
continued. He suggested that the deposit being worked must be the same deposit;
that there could be no leapfrogging over major roads, rivers or other
developments so as to reach what was essentially a new seam. He thought that
one could cross a minor road but that a major baffler would present a
12. Mr
Gallagher SC on behalf of the Applicant/Appellant likewise contended for either
an extreme interpretation of s.24
or
a more moderate one. He submitted that quarrying operations in existence on the
appointed day could not be continued at all thereafter without the developer
obtaining planning permission. That argument was based on the fact that every
quarrying operation - certainly every lateral extension of a quarry - would
appear to involve a material change of use of the surface area from - in the
present case - farming to excavation works.
13. Indeed,
Mr Gallagher’s argument found support in the typically colourful phrase
of Lord Denning in
Thomas
David . v. Penybont RDC
[1972] 3 All ER 1092 when he said of quarrying that:
14. It
seems to me that the extreme views contended for by either party must be
rejected. Not for the nature of the views in themselves but for the fact that
they do not represent a proper interpretation of s.24
of
the 1963 Act as construed within the general framework of that legislation.
Section 24 of the 1963 Act having expressly excluded works from the need to
obtain permission - which term expressly includes
“any
act or operation of ...... excavation......”
-
necessarily permits the continuation of such works even where they involve a
material change in the user of adjoining ground. If s.24 had not contained a
provision so as to exclude existing uses and works from the new planning code
serious and perhaps unconstitutional
15. On
the other hand it is, in my view, equally clear that the right to continue
works commenced before the appointed day does not give to the developer an
unrestricted right to engage in activities of the nature commenced before the
relevant date. The exclusion from the operation of s.24 could not be invoked so
as to confer on the particular developer a licence to carry on generally the
trade or occupation in which he was engaged. The section merely permits the
continuation to completion of the particular works commenced before the
appointed day at an identified location. In my view the answer to the question
posed by the learned Judge of the High Court requires the examination of all of
the established facts to ascertain what was or might reasonably have been
anticipated at the relevant date as having been involved in the works then
taking place. It is clear that in some cases particular factors may be of
decisive importance whereas in others those factors may be of little or no
consequence. It has been argued, for example, that the fact that the property
rights of the Respondents were confined to the original Looby lands at the
appointed date is not a decisive factor. Whilst that may be so, I doubt that
the converse would be correct. If the Respondents had acquired the ownership of
the eighty acres for the purpose of extracting limestone before the relevant
date and had commenced work on part of those lands I would have thought that
the acquisition of the lands would have been of decisive importance in
determining what might have been reasonably anticipated as the consequences of
continuing the works commenced before the operative date. In the context of
building works, presumably, plans
16. No
question was posed by the learned trial Judge in relation to quarrying works
which were or have been carried on on the additional Looby lands and it may be
that those works have been completed so that no question of an injunction
arises but I feel that it would be appropriate to say that the logic of my
reasoning would have had equal application to those lands so that if the
question had arisen I would have felt bound to say that planning permission
would likewise have been required for planning operations on these lands.
17. Again,
I note that the learned trial Judge has rightly reserved to herself the
question whether or not an injunction should be granted in relation to the
works started on the Doyle lands in 1995 and I accordingly express no view on
that matter.
18. Finally,
I should add that it is clear - perhaps with the benefit of hindsight - that
the proceedings herein should not have been instituted under s.27 of the 1976
Act. As Mr Justice Gannon pointed out in
Dublin
County Council .v. Kirby
[1985] IRLM 325, that section was:
19. The
views so expressed by Gannon J were confirmed by Mr Justice Keane in
Dublin
Corporation . v. McGowan
[1993] 1 IR 405 and applied by this Court in
Mahon
. v. Butler
[1998] 1 ILRM 284. This observation is not intended as any criticism of the
Applicant/Appellant or its legal advisors. Indeed they did explore the
possibility of invoking other remedies. I merely draw attention to the fact
that it is now clear that the matters in issue between the parties involved
novel questions of law and complex questions of fact which could not be dealt
with readily in summary proceedings. Indeed Mrs Justice McGuinness recognised
that special difficulties arose in the case and sought to overcome them by
facilitating the parties in furnishing additional evidence before her. These
difficulties should be borne in mind where similar applications are contemplated.