1. On
21 March 1987 the plaintiff/appellant and the defendant/respondent (to whom I
shall refer respectively as Neville and Guardian) entered into a written
agreement the essence of which was that Guardian gave Neville a licence to
enter on a plot of land, owned by Guardian, known as ‘The Gables’
situate in Stillorgan, Co. Dublin, for the purpose of building houses on it.
The agreement (to which I will hereinafter refer as ‘the licence
agreement’) was subject to planning permission being obtained for the
erection of not less than 44 houses on the plot (to which I shall refer as the
‘licence plot’) and it contained the normal provision that on
Guardian executing assignments of houses to purchasers Neville would pay
specified site fines. On the signing of the licence agreement Neville paid a
deposit of
£87,550.
2. The
access to the licence plot was to be over a road opening on to the Stillorgan
Road. This access road is the cause of the litigation between the parties.
3. Between
the licence plot and the Stillorgan Road there was firstly, another plot,
situate in the borough of Dun Laoghaire, and also owned by Guardian, and
secondly, a small strip of land about 150 sq. metres in area and owned by
Dublin County Council. The access road had to pass over this strip of land in
order to join the Stillorgan Road.
4. Prior
to entering into the licence agreement Guardian had already applied to Dublin
County Council for planning permission for the erection of 49 houses on the
licence plot. This application was refused by Dublin County Council but on
appeal An Bord Pleanála on 5
May
1988 granted planning permission for the erection of not more than 46 houses on
the licence plot. In the permission, the board stated that it was satisfied
that Guardian could provide adequate access from Stillorgan Road to the licence
plot.
5. It
had been anticipated by Guardian as far back as 1981 that the access road could
also serve the rear lands of what was then the South County Hotel and is now
Parkes Hotel and the hotel in December 1983 obtained a planning permission for
a car park at the rear of the hotel with an exit on to the access road. The
position of this exit interfered with the planning permission for the
development of the licence plot but the county council insisted that it should
not be changed without the consent of the hotel as they feared that, if it
were, they might have to pay additional compensation to the hotel, and they
were not prepared to sell to Guardian the 150 sq. metre strip which it needed
for the construction of the access road unless the position of the exit was
left unchanged. As a result the implementation of the licence agreement was
held up.
6. On
23 August 1988 Neville’s solicitors wrote to Guardian’s solicitors
complaining of the delay and stating that unless the project commenced within
seven days their client would institute proceedings for specific performance
and damages. Guardian’s solicitors responded by stating that their client
would in the circumstances accept the notice of rescission of the licence
agreement which Neville had served on 29 July 1987, approximately one year
previously. This allegation that the licence agreement was at an end because it
was rescinded by Neville was not pursued.
7. The
present proceedings were then instituted by Neville on 7 October 1988 seeking
specific performance and damages, and in the alternative damages for fraudulent
misrepresentation together with certain declarations, rectification of the
licence agreement and further and other relief. Guardian in its defence entered
a series of defences both dealing with the claim for specific performance and
the additional alternative claims, and pleaded,
inter
alia,
that
the performance of the contract had been frustrated.
8. The
learned trial judge in the course of his judgment dismissed Neville’s
claim for alternative remedies on various grounds and dismissed its claim for
specific performance on the express finding that the defence that the
performance of the contract had been frustrated had been successfully made out.
9. Neville
served a notice of appeal against the order of the learned trial judge in which
it challenged not only the learned trial judge’s decision that the
performance of the contract had been rendered impossible by frustration but
also a number of his other decisions in particular those dismissing
Neville’s alternative claims.
10. Guardian
served a notice of cross-appeal confined to so much of the order of the learned
trial judge as awarded to it, Guardian, against Neville only half of the costs
incurred in the action.
11. At
the hearing of this appeal, counsel on behalf of Neville withdrew all grounds
of appeal other than those directed either to the findings of fact or of law
supporting the learned trial judge’s conclusion that the performance of
the contract had been rendered impossible by frustration.
12. This
therefore became the sole issue for determination on the hearing of this
appeal, the cross-appeal by Guardian in regard to costs necessarily falling to
be debated at a later stage depending upon the result of the appeal made by
Neville.
13. In
order to determine if the performance of the licence agreement was frustrated
it is necessary first to see what was Guardian’s obligation under the
agreement since essentially it is the performance of its obligation that is
alleged to have been frustrated and in order to do this
it
is
necessary to construe the agreement.
14. The
principal question that arises in construing the agreement is whether under its
terms there was an obligation on Guardian to give Neville access to the licence
plot or, in other words, whether Guardian had undertaken as part of the
agreement that it would give Neville access to the plot over the access road
which was to be constructed from the Stillorgan Road.
15. On
behalf of Guardian it was submitted that it had not undertaken to do this. It
was contended that the licence agreement was silent on this point; that in the
licence agreement Guardian did not offer title to the small strip owned by the
county council, and that Neville knew that Guardian did not have title to it.
In regard to this latter point, particular reliance was placed on a letter of
13 March 1987 written by Guardian’s solicitor to Neville’s
solicitor, before the execution of the licence agreement, in which reference
was made to a map which showed that the 150 sq. metre strip between
Guardian’s property and the Stillorgan Road was in the ownership of the
county council.
16. I
have no hesitation in rejecting Guardian’s contentions on this issue. It
seems to me to be quite clear that while Guardian did not at the time own the
small strip over which the access road had to go, it nonetheless agreed to give
access to Neville over it, no doubt being satisfied that it would be able to
acquire title from the county council to enable it to do this, since it had in
March 1984 agreed terms with the county council for the acquisition of the
strip in question.
18. In
clause (1) of the agreement ‘development’ is defined as meaning
‘the land delineated in red on the plan annexed hereto together with the
benefit of the right of way coloured yellow and green. The tenure to the said
lands is as described in the second schedule hereto.’ What was coloured
yellow and green on the plan was both the access road and the entire of the
road throughout the proposed housing estate on the licence plot. Under clause 6
of the agreement, and clause 1 of the addendum to the agreement, both the
access road and the entire of the road throughout the licence plot was to be
constructed by Guardian.
20. The
licensor hereby grants to the licensee licence and authority during the licence
period to enter upon the development for the purpose of erecting buildings and
carrying out works as hereinafter mentioned.
21. In
my opinion the clear meaning of this is that Guardian would give Neville access
to the licence plot during the licence period which was for the period of 18
months commencing 14 days after the granting of planning permission, and since
access could only be obtained by getting title to the 150 sq. metre strip from
the county council, it meant that it necessarily undertook an obligation to do
this. When pressed on this point in the course of the hearing, Mr. Salafia SC,
on behalf of Guardian, initially submitted that this clause should be construed
as meaning that what Guardian was doing was agreeing to give access ‘in
so far as it lay within its power’ but later he reverted to saying that
he had to submit that it meant that Guardian did not undertake to give access.
I am satisfied that this is not correct and accordingly that the question of
whether or not the performance of the licence agreement was frustrated must be
looked at in the light of this basic obligation resting on Guardian. Apart from
paying the deposit of £87,550
,
which
it did, Neville’s principal obligation under the licence agreement was to
‘erect and complete fit for immediate occupation upon each of the sites a
dwelling-house and all necessary works thereto appertaining in accordance with
plans and specifications drawn by the licensor’ s architect and approved
by the local authority before the operative date.’ (See clause 4(2)).
Clearly Neville had no obligation to comply with this clause until given access
to the licence plot by Guardian. So the essential question is whether the
learned trial judge was correct in holding that the performance by Guardian of
its obligation to give access to the site was frustrated and the licence
agreement thereby brought to an end.
22. I
now turn to that issue. Detailed written and oral submissions were made on
behalf of both Neville and Guardian concerning the legal principles applicable
to the question of the frustration of contracts and to the question of the
application of those principles to the facts which were largely not in
controversy arising from the oral and documentary evidence adduced in the case.
23. It
is necessary first, therefore, to determine what are the principles which
should be applied in relation to the doctrine of the frustration of contracts.
24. I
am satisfied that this issue in effect falls into two separate sub-questions.
The first being the necessity to define the circumstances in which frustration
takes place and the second being to determine the basis on which, if those
circumstances do occur, the court has power to declare that the contract is at
an end.
25. The
circumstances in which frustration takes place were defined as follows by Lord
Simon in his speech in
National
Carriers Ltd v. Panalpina (Northern) Ltd
[1981] AC 675 at p. 700F:-
26. Frustration
of a contract takes place when there supervenes an event (without default of
either party and for which the contract makes no sufficient provision) which so
significantly changes the nature (not merely the expense or onerousness) of the
outstanding contractual rights and/or obligations from what the parties could
reasonably have contemplated at the time of its execution that it would be
unjust to hold them to the literal sense of its stipulations in the new
circumstances; in such case the law declares both parties to be discharged from
further performance.
27. In
the same case Lord Roskill in his speech analysed the circumstances in which
frustration occurs in terms which I am satisfied are virtually identical in
their effect where at p. 7 17D he stated as follows:-
28. There
must have been by reason of some supervening event some such fundamental change
of circumstances as to enable the court to say; ‘this was not the bargain
which these parties made and their bargain must be treated as at an end’
– a view which Lord Radcliffe himself tersely summarised in a quotation
of five words from the
Aeneid:
non haec infoedera veni.
29. I
am satisfied that these two quotations from the decision of the House of Lords
represent a correct statement of the principles of law applicable to
frustration in our law and I am prepared to adopt them as being a correct
statement of principle.
30. With
regard to the basis on which in the circumstances in which frustration occurs
the court has power to declare that the contract is at an end I find again in
the case of
National
Carriers Ltd v. Panalpina (Northern) Ltd
and
this time in the speech of Lord Wilberforce, what I am satisfied is a correct
statement of the principles on this issue where at p. 693-694G he states as
follows:-
31. Various
theories have been expressed as to its justification in law [i.e. the doctrine
of frustration]: as a device by which the rules as to absolute contracts are
reconciled with a special exception which justice demands, as an implied term,
as a matter of construction of the contract, as related to removal of the
foundation of the contract, as a total failure of consideration. It is not
necessary to attempt selection of any one of these as the true basis: my own
view would be that they shade into one another and that a choice between them
is a choice of what is most appropriate to the particular contract under
consideration. One could see, in relation to the present contract, that it
could provisionally be said to be appropriate to refer to an implied term, in
view of the grant of the right of way, or to removal of the foundation of the
contract – viz, use as a warehouse. In any event, the doctrine can now be
stated generally as part of the law of contract; as all judicially evolved
doctrines it is, and ought to be, flexible and capable of new applications.
32. What
has to be determined is whether there were in the present case circumstances
such as those outlined in the speeches of Lord Simon and Lord Roskill in the
case of
National
Carriers Ltd v. Panalpina (Northern) Ltd.
Did
an event supervene which so significantly changed the nature of the outstanding
obligations of Guardian from what the parties could reasonably have
contemplated at the time the licence agreement was entered into? Or was there
by some supervening event some such fundamental change of circumstances that
the court could say, ‘this is not the bargain that these parties made and
their bargain must be treated as at an end’? In my opinion the answer to
both these questions is no.
33. As
far back as 1984 Guardian had reached agreement with the county council for the
acquisition of the 150 sq. metre strip. The terms of the agreement are set out
in a letter of 12 March 1984 from Dublin County Council to Guardian. One of the
terms in the agreement was as follows:-
35. Condition
(b) was complied with on 16 September 1986 when Guardian, on appeal to the
planning board obtained planning permission from Dun Laoghaire Borough for the
erection of two three-storey office developments. One of the conditions to
which this planning permission was subject was as follows:-
36. On
25 August 1987 Guardian’s solicitor wrote to the county council with a
view to having the terms set out in the county council’s letter of 12
March 1984 put into effect. After some further correspondence and discussions
between Guardian’s solicitor and the county council, the county council
wrote on 4 December 1987 saying that they were not prepared to proceed in
accordance with the terms set out in their letter of 12 March 1984 as Guardian
‘did not construct the road referred to at item 3’, i.e. the access
road.
37. Further
meetings and correspondence then took place between Guardian and its solicitor
on the one hand and the county council on the other with a view to coming to a
new agreement. A problem had emerged in regard to the position of the exit from
the Parkes Hotel car park on to the access road. In a planning permission XA
1181 which the hotel had obtained from the county council on 5
December
1983, the exit was shown in the middle of the car park. Its position there
interfered with the planning permission in respect of the licence plot and
Guardian wished to have it moved closer to the Stillorgan Road. Parkes Hotel
was not agreeable to this and the county council were not prepared to permit
any change in the position without the hotel’s consent in case it could
result in their having to pay additional compensation to the hotel. Under an
interim award by an arbitrator the county council had paid compensation to the
hotel for the compulsory acquisition of the car park formerly in front of the
hotel which had been acquired for the widening of the road.
38. New
terms which are set out in a letter from the county council dated 8 September
1988 were then agreed upon. They provided for the acquisition of the 150 sq.
metre strip by Guardian in consideration of the payment of £37,500. In
addition Guardian had to ‘construct, at its own expense, a new junction
and access road leading from the carriageway of the Stillorgan Road to the
development site via the proposed car park entrance as per planning permission
Reg. Ref. XA1181’.
40. These
terms were accepted by Guardian in a letter of 13 September 1988 and on 26
October 1988 Mr. Loftus the law agent for the county council wrote
Guardian’s solicitor stating that he was preparing a draft contract. In
the meantime these proceedings had been commenced by Neville by a plenary
summons which was served on 11 October 1988, and Guardian did not go ahead with
the agreement. If it had done so, it would have been in a position to construct
the access road and so comply with its obligation to give Neville access to the
licence plot.
41. Before
completing this narrative of the relevant facts, there is one further letter I
should refer to as it pinpoints the cause of the problem in regard to the
access road. It is a letter of 26 July 1988 from Guardian’s solicitor,
Mr. Owens, to Mr. Loftus and is as follows:-
45. I
refer to our telephone conversation today and to the agreement reached between
our respective clients in 1984 in respect of the above. As you are aware, your
client pointed out that the one outstanding matter in the 1984 agreement was
the location of the access to Parkes Hotel which we discussed with both
yourself and Mr. Fallon at our last meeting in your office. I now set out
hereunder the wording to get over this difficulty which we agreed this morning:-
46. The
owners of Parkes Hotel acknowledge that the access as proposed in paragraph 1
above will not give rise to a claim by it against the county council as a
result of the change in its location from that proposed in planning permission
reference XA1181 already obtained.
47. We
will now endeavour to get its agreement to the inclusion of such a paragraph as
the above in an agreement with our client. Failing reaching such an agreement
with it, our client may have to revert back to the old access as proposed by
Parkes Hotel in planning permission reference XA1 181 as a result of the views
you expressed at our last meeting in your office.
48. As
agreed on the telephone such an agreement (if reached) will be signed on behalf
of Parkes Hotel by its manager and on behalf of Guardian Builders Ltd by its
principal.
51. When
one looks at these facts it is in my opinion impossible to say that the
performance of this contract was frustrated. No event supervened which
significantly changed the nature of Guardian’s obligation to provide
access to the licence plot which involved constructing the access road. When
Guardian entered into the licence agreement, it had the informal agreement of
10 March 1984 with the county council which, if implemented, would have enabled
it to construct the road. And in fact, under the terms of the agreement, it had
an obligation to do so since it was a condition of the agreement that it would
construct the road within twelve months of obtaining planning permission for
its office development from the Dun Laoghaire Borough, and this had been
obtained on 16 September 1986. And when this agreement went off, the county
council showed its willingness to enter into a new agreement in September 1988.
Furthermore, it is quite clear from the evidence of the county council’s
witnesses that the county council wanted this access road built. The only
unexpected problem that Guardian had was the county council insisting that the
position of the exit from the Parkes Hotel car park to the access road should
not be altered, but this could not by any means be termed a supervening event
which significantly changed the nature of Guardian’s obligation under the
licence agreement. It made it more onerous, but that was all.
52. I
am satisfied, therefore, that the defence of frustration fails, and that having
been the only defence which was raised against Neville’s claim for
specific performance, I would allow this appeal and direct specific performance
of the licence agreement. And the court will hear counsel on the question of
damages, if any.