THE HIGH COURT
[2019] IEHC 799
[2008/11026 P.]
BETWEEN
J. GANNON, NIKKI GANNON & J.J. GANNONS LIMITED
PLAINTIFFS
AND
AIDAN BROWNE, LEO WILSON & LEO WILSON ASSOCIATES LIMITED (IN VOLUNTARY
LIQUIDATION)
DEFENDANTS
JUDGMENT of Ms. Justice O’Regan delivered on the 21st day of November, 2019
Issues
1. This matter has come before the court on foot of a notice of motion of the first named
defendant dated the 14th of January, 2019, wherein the first named defendant is seeking
an order pursuant to O.122, r.11 of the Rules of the Superior Courts and/or the inherent
jurisdiction of the court to dismiss the plaintiffs’ claim as against the first named
defendant for want of prosecution, or in the alternative an order pursuant to the court’s
inherent jurisdiction dismissing the plaintiffs’ claim on the basis of an inordinate and
inexcusable delay on the part of the plaintiffs and in the interest of justice by reason of
the lapse of time and/or delay. In the further alternative directions of the court are
sought.
2. The first named defendant’s application is grounded upon his affidavit of the 14th of
February, 2019, and is resisted on the part of the plaintiffs by virtue of an affidavit of the
plaintiffs’ solicitor, Pat Moran, bearing date the 20th of March, 2019.
Background
3. The first and second named Plaintiffs entered into a fee agreement with the first named
defendant on or about the 3rd of May, 2002, in connection with the refurbishment of an
existing premises at Main Street, Ballinrobe, Co. Mayo. The first named defendant is an
architect by profession. Ultimately a contractor was secured for the works and
construction commenced in January, 2004. A certificate of practical completion issued on
the 30th of May, 2005.
4. By plenary summons of the 18th of December, 2007, the first and second named plaintiff
sued the relevant contractor in respect of works carried out wherein injunctive relief
together with damages were sought. By the 22nd of July, 2008, the High Court had
placed a stay on the proceedings of the first and second named plaintiff against the
contractor, with the relevant matter being referred to arbitration. By that date also the
arbitrator had been appointed. There is no further update before the court in respect of
such proceedings.
5. The within proceedings were issued by plenary summons on the 22nd of December, 2008,
against the first named defendant together with the engineer employed by the first and
second named plaintiffs and the allied engineering company of the engineer.
6. There is some dispute between the parties as to when the statement of claim of the 23rd
of September, 2011, was first served on the first named defendant. However, ultimately
Page 2 ⇓
it was served on or about the 15th of June, 2012, following the entry of an appearance
on behalf of the first named defendant on the 6th of February, 2009. The necessary
notice of intention to proceed by the plaintiffs is dated the 8th of November, 2012, and is
addressed to the first and third named defendants only.
7. The first named defendant raised a notice of particulars bearing date the 22nd of
November, 2012. Following such service, a notice of intention to proceed as against the
first named defendant only, dated the 14th of February, 2019, was served. The within
notice of motion followed on the 14th of February, 2019, and since then replies to
particulars and updated particulars of loss both bearing dates the 7th of March, 2019,
have been served.
8. The plaintiffs have had available to them two engineering reports respectively dated the
24th of January, 2007, and the 14th of September, 2012. In addition, and more recently,
the plaintiffs have secured a financial report of DHKN bearing date the 25th of January,
2019.
9. On the 18th of October, 2013, a liquidator was appointed to the third named plaintiff and
by subsequent order of the High Court (the application was brought by notice of motion of
the 31st of March, 2017), the liquidator was afforded liberty to proceed with the action on
the 24th of April, 2017.
10. On the 31st of August, 2010, the third named defendant was dissolved, and on the 13th
of July, 2016, the relevant contractor was dissolved.
11. It is common case that the hearing of the within action is unlikely to take place prior to
the 15th anniversary of the certificate of practical conclusion.
12. In the affidavit of Mr. Moran two excuses are proffered in respect of the delay in
progressing the claim namely: -
(a) at paragraphs 4 and 5 of his affidavit he states that the request for particulars of
the 22nd of November, 2012, necessitated involving professional financial
investigation and an engineering professional which information is now to hand;
and
(b) at paragraphs 17 and 18 it is asserted that a further issue was the appointment of
a liquidator to the third named plaintiff company which occurred on the 2nd of
December, 2013. It was not until the High Court granted the liquidator authority to
proceed on the 24th of April, 2017, that this difficulty was overcome.
13. The first named defendant asserts the following prejudice: -
(1) the proceedings involve allegations affecting his professional standing;
Page 3 ⇓
(2) by reason of the dissolution of the contracting party and the engineer’s limited
company, the first named defendant has been hampered in bringing a notice of
indemnity and/or contribution or joining the contractor as a third party; and
(3) part of the claim levied as against the first named defendant is that he failed to
adequately supervise the relevant building contractor and oral evidence would be
pivotal in this regard.
14. The 1st named defendant argues that in the event of the court being satisfied that there
is inordinate and inexcusable delay, the balance of justice favours the striking out of the
proceedings by reason of: -
(1) the first named defendant was not responsible for any delay and did not acquiesce
nor engage in conduct to indicate that no difficulty arose with respect of the delay
(the first named defendant does acknowledge that the raising of particulars might
possibly be considered some form of acquiescence and accordingly the main focus
of the first named defendant’s argument is from the raising of particulars to the
notice of intention to proceed in January, 2019), nor did the first named defendant
encourage any avoidable expense;
(2) the statement of claim is pleaded generally and fails to distinguish between the
liability of each of the three parties involved. In addition, similar proceedings were
instituted as against the contractor;
(3) the issues of prejudice against the first named defendant cited above;
(4) the fire to the hotel in 2010 and the failure to carry out any repairs since that time
(as per reply to particulars of the 7th of March, 2019), together with the potential
unavailability of any documents because of the dissolution of a number of parties
results in a real possibility of an unfair trial; and
(5) the courts have indicated that a delay culture must be ended and Article 6.1 of the
European Convention on Human Rights requires proceedings to be concluded within
a reasonable timeframe. In addition, Article 34.1 of the Constitution requires the
courts to administer justice, and delay is an adverse consequence on the proper
and efficient administration of this justice.
15. The plaintiffs argue: -
(1) the plaintiffs have a constitutional right of access to the courts and this would be
lost if the case was dismissed;
(2) all the excuses for the delay have been furnished;
(3) there is no affidavit evidence saying the first named defendant has a good defence;
and
Page 4 ⇓
(4) the hotel is still in situ and can be examined.
16. In addition to the foregoing the plaintiffs have argued, although no evidence is
forthcoming in respect of such arguments, that: -
(a) the plaintiffs had no control over the liquidator;
(b) the defendants, other than the first named defendant, do not have resources for
which the first named defendant might recover; and
(c) the plaintiffs have difficult financial circumstances and there is a complex ownership
situation with regard to the hotel.
Jurisprudence
17. Both parties acknowledge that the starting point of any jurisprudence is the Supreme
Court decision in Primor plc v. Stokes Kennedy Crowley [1996] 2 IR 459, where it was
held that it is necessary to establish inordinate and inexcusable delay on the part of the
respondent party and thereafter an assessment has to be made as to where the balance
of justice lies in regard to the seven headings identified in that matter.
18. The first named defendant also refers to Gilroy v. Flynn [2004] IESC 98 Supreme Court,
where Mr. Justice Hardiman stated that the courts have become even more conscious of
the unfairness and increased possibility of injustice which attaches to allowing an action
which depends on witness testimony to proceed a considerable time after the cause of
action accrued.
19. In McMullen v. Ireland no.42297/98 [2004] ECHR, it was indicated that Article 6.1 of the
European Convention on Human Rights required the resolution of proceedings within a
reasonable time and as to what was reasonable would involve, depends on the
circumstances of the case, the conduct of the plaintiffs and what was at stake.
20. Mr. Justice Kearns indicated in Stephens v. Paul Flynn Limited [2005] IEHC 148, that
even partial prejudice may justify a dismissal in respect of the third leg of the Primor test.
21. In Quinn v. Faulkner t/a Faulkner’s Garage & anor [2011] IEHC 103, Mr. Justice Hogan
indicated that there was a public interest in the timely administration of justice having
regard to Article 34.1 of the Constitution and there should be no endless indulgence in
delay.
22. In Gorman v. Minister for Justice, Equality and Law Reform & ors [2015] IECA 41, Ms.
Justice Irvine held that a twelve-year delay between the relevant events and the trial of
the action could amount to a dismissal even with an absence of specific prejudice. The
ability to test the veracity of evidence would be hampered and justice would be put to the
hazard, in particular in a case which did not involve reliable documents. In that case at
para. 72 Ms. Justice Irvine found that, the fact that the defendant was reacting to a step
taken by the plaintiffs, as opposed to being proactive in seeking a dismissal was not a
valid ground of complaint as against the defendant.
Page 5 ⇓
23. In Cassidy v. The Provincialate [2015] IECA 74, Ms. Justice Irvine referred to O’Domhnaill
v. Merrick [1984] I.R. 151 Supreme Court, where it was held a case might be dismissed
in circumstances where asking a defendant to defend the case would place that defendant
under an inexcusable and unfair burden. The test would be, if there was a real or
substantial risk of an unfair trial or an unjust result.
24. In Millerick v. Minister for Finance [2016] IECA 206, Ms. Justice Irvine was satisfied that
where the delay was inordinate and inexcusable marginal prejudice may justify a
dismissal although she also stressed that the absence of proof of prejudice does not mean
there would not be a dismissal. Rather the plaintiffs must point to countervailing
circumstances to cancel the effect of the delay. The court distinguished between culpable
delay and mere inaction by the defendant which is not considered to be culpable given
that the plaintiff has a primary responsibility to advance the proceedings. Reference was
also made to Article 34.1 of the Constitution where the courts are mandated to administer
justice and delay has adverse consequences on the proper and efficient administration of
such justice.
25. In Farrell v. Arborlane Limited & ors [2016] IECA 224, Mr. Justice Sheehan was satisfied
that where there was culpable delay on the part of the plaintiffs, the defendant did not
have to establish prejudice to be able to identify a significant risk of an unfair trial.
Modest prejudice would be sufficient where the delay is inordinate and inexcusable. The
court was satisfied that a defendant should not have to wait twelve to thirteen years with
allegations affecting his professional standing. Article 6.1 of the European Convention on
Human Rights requires that there not be excessive indulgence. The court noted that
memories fade with time resulting in a difficulty with a fair trial. The court is not only
concerned with the position of the parties but with the administration of justice generally.
In that case there was no distinguishing liability identified in the statement of claim as
against the various defendants where the statement of claim ascribed equal level of
culpability to all defendants, and the court was satisfied that this was a factor that could
be taken into account in weighing the balance of justice. In that case the prejudice was
the defendant had a difficulty in securing insurance and the matter was hanging over him
for a considerable time (there was an eighteen-year gap between the occurrence of the
alleged negligence act and the prospective trial of the action) and this was sufficient to
dismiss the proceedings.
26. In Comcast International Holdings Inc. & ors v. Minister for Public Enterprise & ors;
Persona Digital Telephone Ltd & anor v. Minister for Public Enterprise & ors [2012] IESC
50, McKechnie J. stressed a need for a subjective approach in looking at the period of
delay on the basis that the same years of delay in different cases may demand different
treatment and the court should therefore react to the facts of a particular case.
27. In Cavanagh & anor v. Spring Homes Developments Limited & anor [2019] IEHC 496, Mr.
Justice Noonan accepted a degree of prejudice suffered by the defendant by reason of the
passage of time, and that had to be balanced against the loss of the plaintiffs’
constitutional right of access to the court which would not be likely set aside. The
Page 6 ⇓
plaintiffs would then be left without a remedy. In the circumstances, Mr. Justice Noonan
concluded that the balance of justice just about favours the dismissal of the motion and
the matter was to be case managed. That case concerned a straight forward issue and
was largely record based together with expert report, and oral evidence was not pivotal.
The matter involved a four-year gap where the defendant had an influence on the delay.
28. Although the plaintiffs did refer to the case of Carroll Shipping Limited v. Mathews
Mulcahy & ors [1996] IEHC 46, the court was referring to the case of documentary
evidence only, finding that in the case of inordinate or inexcusable delay this would not
necessarily prevent the holding of a fair and just trial.
29. In the instant matter both parties acknowledge the necessity for oral evidence in the
matter, not least because of the allegations of a lack of supervision.
Decision
30. I am satisfied that there was no pre-action delay as between the certificate of practical
completion on the 30th of May, 2005, and the issue of the plenary summons on the 22nd
of December, 2008 - there was a gap of some three and a half years. However,
proceedings were instituted well within the six-year limitation period.
31. There was a delay between the 22nd of December, 2008, and potentially the 23rd of
September, 2011, when the plaintiffs assert that the statement of claim was first served.
The first named defendant subsequently raised particulars from the 22nd of November,
2012, in respect of the statement of claim without complaint as to the lateness of service
of the statement of claim.
32. By the date of service of the notice for particulars the plaintiffs had available to them two
engineering reports, respectively dated the 24th of January, 2007, and the 14th of
September, 2012, the latter of which dealt with individual liability of each of the
defendants and the contractor. In those circumstances, I am satisfied that there was
information available to the plaintiffs to at least respond to the bulk of the particulars
raised even if some of same had to be left over until the securing of an updated financial
report.
33. No evidence is before the court relative to why there was a delay of in excess of three
years and three months between the appointment of a liquidator to the 3rd named
plaintiff (on the 2nd of December, 2013) and the application to the court for authority for
the liquidator to proceed with the action (on the 31st of March, 2017). It is suggested on
behalf of the plaintiffs in submissions that the plaintiffs had no control over this delay.
However, there is no evidence before the court as to any steps taken by the plaintiffs to
expedite the application which was ultimately made by notice of motion of the 31st of
March, 2017, or to explain to the first named defendant the reason why there was a delay
during this period.
34. The excuse of waiting for a financial report between the service of the notice for
particulars and the subsequent notice of intention to proceed is in my view wholly
Page 7 ⇓
inadequate. There was no real attempt in the affidavit of Mr. Mullen to justify this delay.
There was no evidence given by him as to when the financial report was sought and what
steps were taken to expedite the securing of such report during the intervening six-year
period.
35. In all of the circumstances I am satisfied that the delay, limited to the period between the
notice requiring particulars and the notice of intention to proceed is inordinate and the
excuses proffered are inadequate. Accordingly, the delay is inordinate and inexcusable.
36. Insofar as the balance of justice is concerned on the one hand the plaintiffs have a right
of access to the courts under the Constitution and a dismissal of the proceeding at this
time would clearly have a devastating effect on their hope of recovering in respect of their
losses claimed. On the other hand, the case involves allegations affecting the first named
defendant’s professional standing. The contractor who appears from report held by the
plaintiffs on the 14th of September, 2012, to bear the brunt of the responsibility for the
matters complained of by the plaintiffs, dissolved on the 13th of July, 2016, which has
added to the prejudice suffered by the first named defendant in that he can no longer
serve a third party notice on such contractor. Furthermore, this is a case in which oral
evidence as to the adequacy of the first named defendant’s supervision of the building
contractor in or about 2005, being at least fifteen years prior to any prospective trial, will
be relevant.
37. I am satisfied in the circumstances that the balance of justice favours the dismissal of the
proceedings at this time. Accordingly, the first named defendant should succeed in his
application to the court.
Result: Application succeeded. Proceedings struck out for inordinate and inexcusable delay.