High Court of Ireland Decisions
You are here:
BAILII >>
Databases >>
High Court of Ireland Decisions >>
Ardagh Wind Farm Ltd v An Bord Pleanala [2019] IEHC 795 (22 November 2019)
URL: http://www.bailii.org/ie/cases/IEHC/2019/2019_IEHC_795.html
Cite as:
[2019] IEHC 795
[
New search]
[
Printable PDF version]
[
Help]
Page 1 ⇓
THE HIGH COURT
JUDICIAL REVIEW
[2019] 518 JR
2014 No. 518 J.R.
IN THE MATTER OF SECTION 50 AND 50A OF THE PLANNING AND DEVELOPMENT ACT
2000
BETWEEN
ARDRAGH WIND FARM LIMITED
APPLICANT
AND
AN BORD PLEANÁLA
RESPONDENT
JUDGMENT of Mr Justice Garrett Simons delivered on 22 November 2019
INTRODUCTION
1. These judicial review proceedings seek to challenge a decision by An Bord Pleanála to
refuse planning permission for a proposed wind farm. The proceedings are taken at the
instance of the applicant for planning permission, Ardragh Wind Farm Ltd. (“the
Developer”). The Developer had applied for planning permission for a development
project consisting of the erection of five wind turbines and associated works at Ardragh at
the western end of the Mealagh Valley in Cork (“the proposed development”). The
proposed development would have had a total potential output of approximately 11.5
megawatts. As such, the proposed development exceeded the relevant threshold
prescribed for wind farm projects under Schedule 5 of the Planning and Development
Regulations 2001, and, consequently, was subject to environmental impact assessment
(“EIA”) under Part X of the Planning and Development Act 2000 (“the PDA 2000”). Part X
of the PDA 2000 gives effect to the Environmental Impact Assessment Directive
(2011/92/EU) (“the EIA Directive”).
2. The principal ground of challenge advanced on behalf of the Developer is that An Bord
Pleanála failed to carry out the requisite EIA. In the alternative, it is contended that if An
Bord Pleanála did carry out an EIA, then the Board failed to give reasons for its decision
and/or failed to properly record its assessment.
3. Before turning to consider the substance of the challenge, it should be observed that
these proceedings have a number of unusual features. First, the decision under challenge
is a decision to refuse development consent. Most challenges are taken against decisions
to grant planning permission. The benefit to litigant who seeks to challenge a decision to
grant planning permission is obvious, if the proceedings are successful then the
development project cannot be carried out. It is far less obvious what benefit might be
gained from a challenge to a refusal of planning permission.
4. Secondly, there has been inordinate delay in the prosecution of these proceedings. An
Bord Pleanála’s decision was made on 8 July 2014, and these proceedings were initiated
on 1 September 2014, i.e. within the eight-week time-limit prescribed under Section 50 of
the PDA 2000. Thereafter, the proceedings were becalmed for a number of years. An
application to have a hearing date fixed for the proceedings was not made until the end of
February 2019, that is, some four and a half years after the proceedings had first been
Page 2 ⇓
instituted. On 26 February 2019, the parties applied, on consent, to have the matter
listed for hearing in November 2019. The parties estimated that the hearing would take
four days. A four-day hearing slot commencing on 5 November 2019 was duly allocated.
In the event, however, the hearing only took a single day.
5. I will return to consider the implications of this inordinate delay towards the end of this
judgment as part of the discussion of the discretionary nature of judicial review.
6. Thirdly, the legal context has changed since the proceedings were initiated more than five
years ago. The Supreme Court delivered a landmark judgment on 17 July 2018 which
clarified the legal requirements in respect of the carrying out of an EIA, Connelly v. An
Court judgment is that the arguments which the Developer seeks to rely upon are no
longer tenable.
LEGISLATIVE REGIME AS OF JULY 2014
7. An Bord Pleanála’s decision was made on 8 July 2014. It is necessary, therefore, to
consider the legislative regime as it stood at that date. (The PDA 2000 has been
amended more recently to give effect to the revised EIA Directive (Directive 2014/52/EU).
It is agreed that the Board’s decision fell to be determined by reference to the previous
version of the Directive).
8. The Developer’s challenge is predicated largely on the effect of amendments introduced in
October 2012. These amendments were necessary as a consequence of the judgment of
the Court of Justice in Case C-50/09, Commission v. Ireland. The Court of Justice (“the
CJEU”) held that Article 3 is a fundamental provision of the EIA Directive, and that
transposition of Articles 4 to 11 alone cannot be regarded as automatically transposing
Article 3. The obligations created by Article 3 were summarised as follows in the
judgment.
“36. Article 3 of Directive 85/337 makes the competent environmental authority
responsible for carrying out an environmental impact assessment which must
include a description of a project’s direct and indirect effects on the factors set out
in the first three indents of that article and the interaction between those factors
(judgment of 16 March 2006 in Case C‑332/04 Commission v Spain, paragraph
33). As stated in Article 2(1) of the directive, that assessment is to be carried out
before the consent applied for to proceed with a project is given.
37 . In order to satisfy the obligation imposed on it by Article 3, the competent
environmental authority may not confine itself to identifying and describing a
project’s direct and indirect effects on certain factors, but must also assess them in
an appropriate manner, in the light of each individual case.
38. That assessment obligation is distinct from the obligations laid down in Articles 4 to
7, 10 and 11 of Directive 85/337, which are, essentially, obligations to collect and
exchange information, consult, publicise and guarantee the possibility of challenge
Page 3 ⇓
before the courts. They are procedural provisions which do not concern the
implementation of the substantial obligation laid down in Article 3 of that directive.”
9. Case C-50/09 concerned the planning legislation as it stood prior to the Planning and
Development (Amendment) Act 2010. The CJEU held that the pre-2010 Act version of
the planning legislation did not properly transpose Article 3 of the pre-2014 version of the
EIA Directive.
10. In response to the judgment in Case C-50/09, a series of amendments were made to Part
X of the PDA 2000. These amendments were introduced by inter alia the European Union
(Environmental Impact Assessment) (Planning and Development Act, 2000) Regulations
2012 (S.I. No. 419 of 2012) (“the 2012 Regulations”).
11. The Developer places emphasis on the amended definition of “environmental impact
assessment” under Section 171A(1) of the PDA 2000, which read as follows.
“‘environmental impact assessment’ means an assessment, which includes an
examination, analysis and evaluation,* carried out by a planning authority or the
Board, as the case may be, in accordance with this Part and regulations made
thereunder, that shall identify, describe and assess in an appropriate manner, in
light of each individual case and in accordance with Articles 4 to 11 of the
Environmental Impact Assessment Directive, the direct and indirect effects of a
proposed development on the following:
(a) human beings, flora and fauna,
(b) soil, water, air, climate and the landscape,
(c) material assets and the cultural heritage, and
(d) the interaction between the factors mentioned in paragraphs (a), (b) and
(c).”
* Words in italics added by the 2012 Regulations.
12. Counsel on behalf of the Developer, Mr Michael O’Donnell, BL, submits that this section
imposes an express obligation on An Bord Pleanála itself to carry out an EIA. The
examination, analysis and evaluation must be evident from the Board’s decision.
13. Counsel on behalf of An Bord Pleanála, Ms Nuala Butler, SC, has drawn attention to other
aspects of the amendments introduced under the 2012 Regulations. In particular,
counsel opened the following provisions which address, first, the Board’s obligation to
consider the adequacy of the environmental impact statement submitted with the
planning application, and, secondly, the nature of the information to be made publicly
available following the making of a decision to grant or to refuse planning permission.
“(1D) The planning authority or the Board, as the case may be, shall consider whether an
environmental impact statement submitted under this section identifies and
describes adequately the direct and indirect effects on the environment of the
proposed development and, where it considers that the environmental impact
Page 4 ⇓
statement does not identify or adequately describe such effects, the planning
authority or the Board shall require the applicant for consent to furnish, within a
specified period, such further information as the planning authority or the Board
considers necessary to remedy such defect.
(1E) In addition to any requirement arising under subsection (1D), the planning
authority or the Board, as the case may be, shall require an applicant for consent to
furnish, within a specified period, any further information that the planning
authority or the Board considers necessary to enable it to carry out an
environmental impact assessment under this section.
(1F) Where information required by the planning authority or the Board under
subsection (1D) or subsection (1E) is not furnished by the applicant for consent
within the period specified, or any further period as may be specified by the
planning authority or the Board, the application for consent for the proposed
development shall be deemed to be withdrawn.
(1G) In carrying out an environmental impact assessment under this section the
planning authority or the Board, as the case may be, shall consider—
(a) the environmental impact statement;
(b) any further information furnished to the planning authority or the Board
pursuant to subsections (1D) or (1E);
(c) any submissions or observations validly made in relation to the
environmental effects of the proposed development;
(d) the views, if any, provided by any other Member State under section 174 or
Regulations made under that section.
(1H) In carrying out an environmental impact assessment under this section the
planning authority or the Board, as the case may be, may have regard to and adopt
in whole or in part any reports prepared by its officials or by consultants, experts or
other advisers.
(1I) Where the planning authority or the Board, as the case may be, decides to grant
consent for the proposed development, it may attach such conditions to the grant
as it considers necessary, to avoid, reduce and, if possible, offset the major adverse
effects on the environment (if any) of the proposed development.
(1J) When the planning authority or the Board, as the case may be, has decided
whether to grant or to refuse consent for the proposed development, it shall inform
the applicant for consent and the public of the decision and shall make the following
information available to the applicant for consent and the public:
(a) the content of the decision and any conditions attached thereto;
(b) an evaluation of the direct and indirect effects of the proposed development
on the matters set out in section 171A;
(c) having examined any submission or observation validly made,
Page 5 ⇓
(i) the main reasons and considerations on which the decision is based,
and
(ii) the main reasons and considerations for the attachment of any
conditions, including reasons and considerations arising from or related
to submissions or observations made by a member of the public;
(d) where relevant, a description of the main measures to avoid, reduce and, if
possible, offset the major adverse effects;
(e) any report referred to in subsection (1H);
(f) information for the public on the procedures available to review the
substantive and procedural legality of the decision, and
(g) the views, if any, furnished by other Member States of the European Union
pursuant to section 174.”
14. As appears, these legislative provisions chart a series of procedural steps which An Bord
Pleanála must follow. Relevantly, these include an obligation to consider the adequacy of
an environmental impact statement submitted with the planning application, and, if
necessary, to request the applicant to submit such further information as the Board
considers necessary to remedy any defect. The provisions then set out the relevant
considerations to which regard must be had. Finally, the provisions set out the
information which must be made available following the making of a decision to grant or
refuse planning permission.
15. Counsel for An Bord Pleanála submits that it is implicit from the statutory provisions which
stipulate the information to be provided to the public at the time of the decision that the
EIA does not necessarily have to be set out in full in the decision but rather can be
provided separately, i.e. in the inspector’s report. Sub-section 172(1J)(b) identifies an
“evaluation of the direct and indirect effects of the proposed development” as part of the
information to be provided. That this is enumerated separately from the planning
decision is said to support an inference that this information can be provided in a different
document, i.e. the inspector’s report.
THE DEVELOPER’S CASE
16. The grounds of challenge were narrowed at the hearing on 5 November 2019. Counsel on
behalf of the Developer indicated that his client was not now pursuing the grounds in
relation to the interpretation of the statutory development plan. In particular, grounds
(e) (13) to (18) were withdrawn.
17. The Developer’s case is striking in its simplicity. An Bord Pleanála is a “competent
authority” for the purposes of the EIA Directive. An Bord Pleanála is under an express
obligation to carry out an EIA in accordance with Sections 171A and 172 of the PDA 2000.
This assessment must include an “examination, analysis and evaluation” of the direct and
indirect effects of a proposed development on the environment. It is submitted that the
carrying out of the requisite “examination, analysis and evaluation” must be evident from
the Board’s decision itself.
Page 6 ⇓
18. An Bord Pleanála’s decision of 8 July 2014 does not, it is submitted, fulfil these statutory
obligations. There is no reference in the curial or operative part of the Board’s decision to
its having carried out an EIA in respect of the proposed wind farm. Even if one considers
the earlier Board Direction, there is, again, no reference to the carrying out of an EIA.
19. It is not sufficient, on the Developer’s argument, that the Board Direction states that the
Board decided to refuse permission “generally in accordance with” the inspector’s
recommendation. The court should not impute the assessment set out in the inspector’s
report to the members of An Bord Pleanála. To do so, it is said, would be to engage in
“speculation”. Rather, the only inference which could be drawn from the absence of an
express reference, in either the Decision or the Direction, to the Board itself having
carried out an EIA, is that the Board did not, in fact, carry out an EIA.
20. (A “Board Direction” is the initial document which records the determination on an appeal
as taken at a meeting of the board members. That determination is subsequently
embodied in a formal order or decision which is signed and sealed by a member of the
Board. Both the Board Direction and the Decision are then made publicly available).
21. Counsel for the Developer, very properly, concedes that the legal position would have
been different had either the Decision or Direction expressly stated that the Board had
“carried out” or “completed” an EIA, and that it had “adopted” the inspector’s assessment
as set out in his report. This concession is well made given the established case law
discussed at page 14, paragraphs 38 et seq. below. Counsel maintains the position,
however, that in the absence of such an express statement, it would be “improper” and
“impermissible” to speculate as to whether and on what basis an EIA might have been
carried out by An Bord Pleanála.
22. In order to determine whether these arguments on behalf of the Developer are correct, it
is necessary to rehearse the manner in which the appeal was processed by An Bord
Pleanála. This is done under the next heading below.
AN BORD PLEANÁLA’S PROCESSING OF THE APPEAL
23. The appeal came before An Bord Pleanála by way of two third-party appeals. The first-
instance decision of the local planning authority (Cork County Council) had been to grant
planning permission.
24. As is normal practice, an employee of the board (“the inspector”) had been assigned the
role of reporting upon the appeal and preparing a recommendation. The board members
are required to consider the report and recommendation. (Section 146 of the PDA 2000).
25. In the event, the inspector prepared two reports. The first report is dated 13 July 2012
(“the first report”). In this report, the inspector made, in effect, two alternative
recommendations. This arose in circumstances where the inspector had identified what
he considered to be a “number of deficiencies” in the environmental impact statement
(“EIS”) submitted on behalf of the Developer. The inspector also identified other areas
where he considered further information would be required in order to adequately assess
Page 7 ⇓
the impacts of the proposed development. The inspector recommended that the Board
could either (i) make a decision to refuse planning permission, by reference to what the
inspector considered to be the significant negative impacts which the proposed
development would have on the landscape and visual amenities of the area, or (ii) issue a
request for further information. The inspector indicated a preference for the first option,
and provided a draft form of wording for a decision to refuse planning permission. The
inspector went on, however, to set out in detail the nature of the further information to be
sought in the event of the Board deciding not to refuse planning permission at that stage.
(See pages 45 and 46 of the inspector’s first report).
26. The Board made a decision at a meeting on 13 December 2012 to serve a request for
further information. Relevantly, the following information was sought in respect of the
cumulative landscape and visual impacts of the proposed development.
“The submitted EIS and supporting documentation fails to adequately assess the
cumulative landscape and visual impacts of the proposed development with other
permitted and proposed wind energy developments, particularly those within the
Mealagh Valley, at Barrboy to the east and seven turbines in respect of which
planning permission has been granted at Derreenacrinnig West to the southeast of
the site. A revised Landscape and Visual Impact Assessment should therefore be
submitted taking into consideration these cumulative impacts.”
27. The response to the request for further information on behalf of the Developer was
received by the Board on 14 October 2013. Crucially, this response was circulated to
parties to the appeal and submissions were received from the third-party appellants.
28. The inspector then prepared a supplementary report dated 12 May 2014 (“the second
report”). The second report sets out a revised environmental impact assessment of the
impact of the proposed development, having regard to the response to the request for
further information and the submissions received from the third party appellants. The
inspector explained (at page 11 of the second report) that he continued to have concerns
in respect of the landscape and visual impacts of the proposed development.
“4.2 Landscape and Visual Impacts:
The concerns expressed in my previous report in relation to the landscape
and visual impacts of the proposed development related primarily to the
cumulative impacts on the character of the Mealagh Valley. In this regard,
the revised visual impact assessment notes that the proposal will be visible in
conjunction with the permitted developments of Goulacullin (Barrboy) and
Derreenacrinnig, “at widely disparate viewing angles within complex terrain”.
It is stated that the “steep and meandering nature of the Mealagh River
Valley aids the visual absorption of the modest scale wind farms that are
located on the ridges above the valley.”
The submission is not accompanied by additional imagery. It is clear from
documentation submitted with the planning application and at further
Page 8 ⇓
information stages, that the development will be visible in conjunction with
other existing and permitted wind energy developments along almost the
entire southern side of the Mealagh Valley. While I note the analysis
submitted, I consider that the cumulative impact with other permitted
development within the area would be significant adverse rather than
medium as suggested. I do not consider that the succession or sequential
nature of such views, as opposed to a combined view, significantly mitigates
the landscape character impacts of the development. The concentration of
three wind energy developments around this valley, notwithstanding their
modest scale, would significantly alter and erode its character. In this
regard, I remain of the opinion that the permission for the development
should be refused for the reason previously recommended.”
29. The inspector then set out his overall conclusion and recommendation as follows (at
pages 12 and 13 of the second report).
“5.0 CONCLUSION AND RECOMMENDATION:
I consider, based on the information submitted with the planning application
and associated further information responses, and the information
subsequently submitted to the Board in October 2013, that there is sufficient
information before the Board on which to make a determination in this
instance.
I have previously raised concerns with regard to the overall landscape and
visual impacts of the proposed development, particularly on the character of
the Mealagh Valley, when taken in conjunction with other permitted
developments in the area. I do not consider that the submissions received
have addressed there concerns and remain of the opinion that permission
should be refused on these grounds, as follows:
1. The Cork County Development Plan 2009 sets out policies and
objectives in relation to wind energy development and identifies areas
in broad strategic terms for the location and siting of such
development, identifying “Strategic Search Areas” and “Strategically
Unsuitable Areas”. The overall strategic approach as set out in the said
Development Plan is considered to be reasonable. The proposed
development, which is not located within a “Strategic Search Area”, is
located immediately adjacent to areas designated as “Strategically
Unsuitable Areas”, considered generally to be unsuitable for wind
energy projects and where such projects would normally be
discouraged The proposed development, which would itself be visible
over a wide area, would in conjunction with permitted and proposed
development in the area, give rise to an undue concentration of wind
energy development with significant negative impacts on the landscape
character and visual amenities of the area, and in particular the
Page 9 ⇓
Mealagh Valley, and it’s amenity, tourism and recreational potential.
The proposed development would therefore be contrary to the proper
planning and sustainable development of the area.”
30. The Board, at a meeting held on 30 June 2014, made a decision to refuse planning
permission. The decision is recorded in a Board Direction dated 2 July 2014 as follows.
“The submissions on this file and the Inspector’s report were considered at a
further Board meeting held on 30th, June 2014.
The Board, by majority of 2 1, decided to refuse permission generally in
accordance with the Inspector’s recommendation, for the reasons and
considerations as set out below.
REASONS AND CONSIDERATIONS
The Cork County Development Plan 2009 sets out policies and objectives in
relation to wind energy development and identifies areas in broad strategic
terms for the location and siting of such development, identifying “Strategic
Search Areas” and “Strategically Unsuitable Areas”. The overall strategic
approach as set out in the said Development Plan is considered to be
reasonable. The proposed development, which is not located within a
“Strategic Search Area”, is located immediately adjacent to areas designated
as “Strategically Unsuitable Areas”, considered generally to be unsuitable for
wind energy projects and where such projects would normally be
discouraged.
The proposed development, which would itself be visible over a wide area,
would in conjunction with permitted and proposed development in the area,
give rise to an undue concentration of wind energy development with
significant negative impacts on the landscape character and visual amenities
of the area, and in particular the Mealagh Valley, and it’s amenity, tourism
and recreational potential. The proposed development would, therefore,
seriously injure the visual amenities of the area and be contrary to the proper
planning and sustainable development of the area.”
31. A formal order of the board was then prepared; and this order was signed and sealed on
8 July 2014 (“the Decision”).
DETAILED DISCUSSION
32. The single issue which falls for adjudication in these judicial review proceedings could
hardly be narrower. It is whether the absence of an express reference, in either the
Decision or Board Direction, to the carrying out of an environmental impact assessment
renders the decision to refuse planning permission invalid. It is common case that the
inspector carried out an EIA which, had it been expressly adopted by An Bord Pleanála,
would meet the requirements under national law and under the EIA Directive.
33. The Developer makes no criticism of the EIA which had been carried out by the inspector
and recorded in his two reports. Nor has there been any suggestion that the procedural
Page 10 ⇓
requirements under Part X of the PDA 2000 were not complied with. This is scarcely
surprising: the Developer could have no grounds for criticising the procedure adopted in
circumstances where the Board had given the Developer an opportunity—by way of the
request for further information—to address its concerns in respect of the impact of the
proposed development on the landscape and visual amenity of the area.
34. The Developer has not sought to challenge the finding that the cumulative effect of the
proposed development with other wind energy development projects would have
“significant negative impacts” on the landscape character and visual amenities of the
area.
35. Rather, the Developer’s entire case turns on the highly formalistic argument that a
planning decision must, at a bare minimum, expressly state that An Bord Pleanála
“carried out” or “completed” an environmental impact assessment. Nothing less will do.
If the board is relying upon its inspector’s report as evidencing the EIA, then the decision
must state that the board “adopted” the inspector’s report.
36. Arguments along these lines have been rejected by the High Court in a series of cases
dating from 2015. In each of these cases, the applicant for judicial review had sought to
seize upon the literal wording of Section 172(1H) of the PDA 2000 to make an argument
that An Bord Pleanála was required to state expressly that it had “adopted” its inspector’s
report. The sub-section reads as follows.
“(1H) In carrying out an environmental impact assessment under this section the
planning authority or the Board, as the case may be, may have regard to and adopt
in whole or in part any reports prepared by its officials or by consultants, experts or
other advisers.”
37. It will be recalled that Section 172(1H) had been introduced in October 2012 under the
2012 Regulations (S.I. No. 419 of 2012). At the time the within proceedings were
instituted on 1 September 2014, the argument that an inspector’s report had to be
formally “adopted” was still a novel one, and had not yet been the subject of a reserved
judgment of the High Court. Unfortunately for the Developer, however, one consequence
of the leisurely pace at which these proceedings have been pursued is that, by the time
the case eventually came on for hearing on 5 November 2019, the argument had no life
left in it.
38. The relevant case law includes the following: Buckley v. An Bord Pleanála [2015] IEHC
572; Ahearne v. An Bord Pleanála [2015] IEHC 606; Dunnes Stores v. An Bord Pleanála
(Square Tallaght) [2016] IEHC 226; and, most recently, Redrock Developments Ltd. v. An
Bord Pleanála, unreported, High Court, Faherty J., 21 October 2019. In each of these
cases, a formula of words which fell short of An Bord Pleanála formally “adopting” the
inspector’s report was held to be sufficient.
39. The approach taken in these judgments can be illustrated by the following passages from
Buckley v. An Bord Pleanála.
Page 11 ⇓
“117. On the facts of the present case, it is clear that the inspector carried out an
Environmental Impact Assessment. Indeed the Applicant accepts that were this
‘adopted’ by the Board then its argument would fall away. In circumstances
however, where the Board in its decision, at the very outset, stated that it decided
to grant permission ‘generally in accordance with the inspector’s recommendations
for the following reasons and considerations and subject to the following conditions’
and that it had regard to ‘the report of the inspector’ and that it adopted all 25
conditions in the Inspector’s Report, I am of the view that it is clear that the Board
did ‘adopt’ the Inspector’s Report and carry out an appropriate EIA in accordance
with its statutory obligations.
118. I would therefore conclude that the Applicants’ submission in this regard is not well
founded.”
40. The language employed by An Bord Pleanála in the decision under review in Buckley
resonates with that of the decision the subject matter of these proceedings. In each
instance, the decision was made “generally in accordance with” the inspector’s
recommendation. Moreover, again as in Buckley, it is accepted by the applicant for
judicial review that had An Bord Pleanála formally “adopted” the two inspector’s reports,
this would have represented proper compliance with the requirements of Part X of the
PDA 2000.
41. Counsel on behalf of the Developer has sought to distinguish this line of case law on the
basis that in those cases the planning decision under review had included a statement to
the effect that the Board had “completed” an environmental impact assessment.
42. With respect, this argument is incorrect in point of fact and of law. In at least one of the
judgments, Redrock Development Ltd v. An Bord Pleanála, the planning decision did not
include any such formula. See, in particular, paragraphs [120] to [124] of the judgment.
Notwithstanding this, the High Court (Faherty J.) held at [137] that An Bord Pleanála had
discharged its statutory function in conducting an EIA.
“The first thing to be noted is that the rEIS submitted with the substitute consent
application was comprehensively addressed in the Report of the Inspector.
Secondly, the Board specifically states in its Decision that it decided to refuse the
substitute consent application generally in accordance with the Inspector’s
recommendation and for the reasons and considerations set out in the Decision.
Thirdly, the Board’s Direction clearly refers to the rEIS. Fourthly, both the Board’s
Direction and Decision reference matters which were canvassed in the rEIS. By and
large, the Board’s reason for refusal of substitute consent replicates the Inspector’s
first recommended reason for refusal. The Inspectors first recommended reason
for refusal clearly followed upon his appraisal of the rEIS which accompanied the
substitute consent application. To my mind, all of those factors lead to the
undoubted conclusion that the Board conducted the requisite EIA.”
Page 12 ⇓
43. A similar commonsense analysis is to be found in each of the cases. The courts apply a
pragmatic approach to the interpretation of planning decisions. The absence of a
particular form of words such as, for example, “the board adopted the inspector’s report”
or “the board completed an environmental impact assessment” is not necessarily fatal to
the validity of a planning decision. Rather, the decision, as with any planning document,
must be read as a whole. If it is evident that the members of the Board accepted the
approach in the inspector’s report, then it is legitimate to regard the assessment set out
in the inspector’s report as representing the EIA as adopted by the Board. It is not
necessary for An Bord Pleanála to replicate the content of same in the formal decision.
44. The case law of the High Court discussed above has, to an extent, been eclipsed by the
landmark judgment of the Supreme Court in Connelly v. An Bord Pleanála [2018] IESC
duty to give reasons. I turn to consider this judgment under the next heading below.
CONNELLY V. AN BORD PLEANÁLA
45. The unanimous judgment of the Supreme Court in Connelly v. An Bord Pleanála
Justice identified two purposes which a duty to state reasons serves, as follows. First, to
enable a person affected by the decision to understand why a particular decision was
reached. Secondly, to enable a person to ascertain whether or not they have grounds
upon which to appeal the decision (where an appeal lies) or to seek judicial review.
46. Having identified the purpose of the duty to give reasons, the court was then able to
formulate the legal requirements against which the adequacy of reasons may be tested.
First, any person affected by a decision is entitled to know in general terms why the
decision was made. This requirement derives from the obligation to be fair to individuals
affected by binding decisions, and also contributes to transparency. Second, a person is
entitled to have enough information to consider whether they can or should seek to avail
of any appeal or to apply for judicial review of a decision. The reasons provided must
also be such as to allow a court hearing an appeal or reviewing a decision to engage
properly in such an appeal or review.
47. The aspect of the judgment in Connelly of most immediate relevance to the present case
is, of course, the discussion of what surrounding documentation can be relied upon in
identifying the reasons for an administrative decision. The Supreme Court indicated that,
in principle, the reasons for a decision may be derived in a variety of ways, either from a
range of documents or from the context of the decision, or in some other fashion. This is
subject always to the requirement that the reasons must actually be ascertainable and
capable of being determined.
48. As with the present case, the proceedings in Connelly also involved a challenge to a
decision of An Bord Pleanála to grant planning permission in respect of an EIA project.
The Supreme Court accepted, in principle, that in assessing the adequacy of reasons, it
was appropriate to have regard not only to An Bord Pleanála’s formal decision, but also
the report prepared in respect of the planning appeal by an inspector employed by An
Page 13 ⇓
Bord Pleanála. The inspector’s report is made available to the public at the same time as
the Board’s decision is notified. The Supreme Court further accepted that it might also be
appropriate to have regard to the documentation accompanying the planning appeal,
including documentation submitted by the applicant for planning permission, i.e. the
proposed developer.
49. The judgment indicates that it would be preferable in all cases if An Bord Pleanála made
expressly clear whether it accepts all of the findings of its inspector or, if not so doing,
where and in what respect it differs. Failure to do so is not, however, necessarily fatal if
in the circumstances it is possible to reach a significantly clear inference as to what the
board thought in that regard.
“9.6 In that context it does seem to me to be worth saying that it would be preferable in
all cases if the Board made expressly clear whether it accepts all of the findings of
an inspector or, if not so doing, where and in what respect it differs. It may be
possible, in certain circumstances, to reach a significantly clear inference as to what
the Board thought in that regard but it would be better if the matter were put
beyond inference and were expressly stated.
9.7 Where the Board differs from its inspector then there is clearly an obligation for the
Board to set out the reasons for coming to that conclusion in sufficient detail to
enable a person to know why the Board differed from the inspector and also to
assess whether there was any basis for suggesting that the Board's decision is
thereby not sustainable. But where, as here, a further process intervenes between
an inspector’s report and the final decision of the Board then it is obvious that that
further process was designed to ascertain whether the concerns set out in the
inspector’s report and accepted by the Board could be met by further information.
In essence, the general reasons issue in this case comes down to one of assessing
whether the Board has given adequate reasons for being satisfied that the initial
concerns expressed in the inspector's report, and which would appear to have
found favour with the Board at least on a prima facie basis, had been adequately
dealt with by the additional information, including the NIS supplied.
9.8 It seems to me, therefore, that the reasons for the Board’s development consent
decision in this case can, at a minimum, be found in the inspector’s report and the
documents either expressly or by necessary implication referred to in it, the s.132
notice and the further information and NIS subsequently supplied, as well as the
final decision of the Board to grant permission including the conditions attached to
that decision and the reasons given for the inclusion of the conditions concerned.
9.9 Any interested party will have had access to all of that documentation. If the
reasons for the Board’s decision can be reasonably ascertained from that
documentation, then, at least so far as national law is concerned, the requirement
to give reasons will be met because any interested party (including a person who
has standing but who was not involved in the planning process before the Board)
will be able to assess whether adequate reasons have been given or whether there
Page 14 ⇓
might be grounds for challenging the decision of the Board. Insofar as the High
Court judgment suggests that the reasons for the Board’s decision cannot be
sufficiently identified, I would reverse the judgment.”
50. The Supreme Court addressed the specific requirements in relation to the reasons for an
environmental impact assessment at page 481/482 of the report.
“11.4 It follows that, while the general principle remains the same, there is an additional
requirement in a case to which the EIA regime applies to the effect that the
decision must be sufficiently clear to enable any interested party to consider
whether they may have grounds to challenge the decision on the basis that it might
be contended that an adequate EIA had not been conducted.
11.5 In that context, it is important to note that the EIA regime does not require any
particular result to the relevant process but rather is concerned with the process
itself. It requires a particular assessment to be carried out and, by necessary
inference, that a sustainable permission only be granted where that assessment is
favourable to the grant of the permission concerned. It follows that, amongst the
reasons which need to be given, there must be included the basis on which the
assessment required under the EIA regime leads to the conclusion that a
permission can be granted. That in turn requires that the decision, or other
relevant and connected materials available to any interested party, must
demonstrate that an EIA was carried out and that the decision maker properly had
regard to the results of the EIA in coming to its conclusion.
11.6 Against that background it is necessary to look at the decision. It is clear that the
inspector’s report sets out the analysis of the matters which the inspector
considered necessary in the context of an EIA. But it is also clear that an additional
assessment was carried out both by the Board in considering the inspector’s report,
again by the Board in requiring additional information including an NIS and finally
by the assessment of the Board of the overall situation in the light, amongst other
things, of that additional information.
11.7 In those circumstances it does not seem to me that it can be said that there is
inadequate information to allow a party to assess whether a proper EIA has been
carried out. Any interested party can identify the issues which were addressed in
the inspector’s report, in the additional information and in the Board’s final
assessment. If there is a case to be made that material issues were not assessed
then an interested party has access to adequate information to enable them to
mount such a case. In my view it follows that the information and reasons given
are adequate to permit any interested party to mount a challenge based on a
contention that a proper EIA was not carried out. Such a party knows the matters
that were assessed and, for the reasons already analysed, knows why the result of
that assessment was as set out in the decision. So far as information and reasons
are concerned that is sufficient to meet the legal requirement. Insofar as the High
Court judgment found otherwise I would reverse the judgment.”
Page 15 ⇓
FINDINGS OF THE COURT
51. The legal test as per Connelly is that the planning decision, or other relevant and
connected materials available to any interested party, must demonstrate (i) that an EIA
was carried out, and (ii) that the decision-maker properly had regard to the results of the
EIA in coming to its conclusion.
52. Applying these principles to the facts of the present case, I am satisfied, first, that it is
appropriate to read the formal board decision in conjunction with the inspector’s report;
and, secondly, that the recording of the EIA and the reasons for the decision to refuse
planning permission by reference to the significant negative impacts of the proposed
development are to be found in these materials. I elaborate upon these points below.
53. Under Section 172(1D) of the PDA 2000 (set out earlier), An Bord Pleanála is obliged to
consider whether an environmental impact statement (“EIS”) submitted by a developer
identifies and describes adequately the direct and indirect effects on the environment of
the proposed development, i.e. the Board is obliged to appraise the adequacy of the EIS.
It will be recalled that the inspector, in his first report, had put forward an option of
making a request for further information. The purpose was to address inadequacies in
the EIS. The Board chose this option at their meeting in December 2012, and duly issued
a request pursuant to Section 132 of the PDA 2000. The request for further information
was in almost identical terms to that recommended by its inspector.
54. It is evident from this sequence of events that both the inspector and the members of An
Bord Pleanála were not only cognisant of the fact that the proposed development was
subject to mandatory EIA, but also were taking active steps in order to ensure that the
assessment was properly carried out.
55. The further information was then subject to a second report by the inspector, and the
inspector recommended that planning permission be refused because of the cumulative
impact on landscape and visual amenity.
56. The Board Direction expressly states that the Board decided to refuse permission
“generally in accordance with” the inspector’s recommendation for the reasons and
considerations set out. There then followed a formal statement of the “reasons and
considerations”. The content of this formal statement of “reasons and considerations” is
precisely the same as that recommended by the inspector in his second report.
57. There can be no doubt, therefore, but that the Board was adopting the same approach as
its inspector. Section 172(1H) of the PDA 2000 expressly envisages that the Board may
adopt the EIA carried out in an inspector’s report. The High Court case law discussed
earlier indicates that it is not necessary to use the term “adopt” in order to achieve this.
Rather, the court will take a common sense approach to the interpretation of the planning
decision.
58. The Board’s Decision to refuse planning permission is framed in language which can only
be understood as referable to the carrying out of an EIA. More specifically, planning
Page 16 ⇓
permission was refused by reference to the cumulative impact of the proposed
development and its significant adverse effect on the landscape and visual amenity. The
requirement to take into account the cumulative effect of a proposed development
project, i.e. the environmental impact of that project when considered with other existing
and proposed development projects, is a concept directly referable to the EIA Directive.
59. An informed participant—which is the relevant test as per Connelly—would have
immediately understood from reading the inspector’s two reports; the Board Direction;
and the Board Decision that the Board agreed with and accepted the inspector’s
recommendation to refuse planning permission precisely because of the significant
negative impact it would have on the environment. The requirements of the EIA Directive
were fulfilled. The Board made a decision, informed by the EIS and further information
submitted by the Developer, and following public consultation, to refuse planning
permission because the proposed development would have had a significant negative
impact.
60. Counsel on behalf of the Developer submitted that it would be improper and
impermissible to impute the inspector’s assessment to the members of An Bord Pleanála.
To do so, it was suggested, would require the court to engage in “speculation”. With
respect, this submission is untenable. The only rational and logical inference to draw
from the materials, and the history of the processing of the appeal, is that An Bord
Pleanála had been cognisant of its obligation to carry out an EIA and had done so. It
would be perverse for this court to draw the opposite conclusion and to decide, in effect,
that having taken the time and trouble of serving a request for further information and
obtaining a second inspector’s report, the members of An Bord Pleanála thereafter
entirely overlooked the requirement to carry out an EIA.
DISCRETIONARY FACTORS
61. For the reasons set out above, I have concluded that the challenge to the decision of An
Bord Pleanála cannot succeed on the merits. For the sake of completeness, I should state
that even if I had found for the Developer on the merits, I would have refused to set
aside the Board’s Decision in the exercise of the court’s discretion.
62. It is well established that judicial review is a discretionary remedy. A court, in the
exercise of its discretion, may decide to withhold relief from an otherwise entitled
applicant. The court is not, of course, at large in this regard. There must be a reasoned
basis for the exercise of discretion. The type of factors which might be considered include
inter alia the conduct of an applicant, delay, the existence of an adequate alternative
remedy or that the grant of relief would serve no useful purpose.
63. I would have refused to grant relief in this case on the basis of the last of these factors,
namely that to do so would serve no useful purpose. As observed at the outset of this
judgment, these proceedings are unusual in that they seek to challenge a decision to
refuse development consent. Such proceedings are normally only ever brought in order
to clarify an issue of principle which might affect the reconsideration of the planning
application. A recent example of proceedings with this purpose is provided by Element
Page 17 ⇓
Power Ireland Ltd v. An Bord Pleanála [2017] IEHC 550. Those proceedings presented an
issue of principle as to whether An Bord Pleanála is entitled to refuse planning permission
on the basis that it would be premature to grant permission in the absence of a national
wind energy strategy with a spatial dimension. The resolution of this issue of principle
would be of obvious benefit to the developer who had been refused planning permission.
If, as ultimately transpired, the court were to hold that An Bord Pleanála was not entitled
to refuse planning permission on this basis, then the matter could be remitted to the
Board to be reconsidered by reference to the legal position as clarified by the judgment.
64. By contrast, the within judicial review proceedings do not present any issue of principle.
The proceedings simply allege a procedural error on the part of the Board in recording an
EIA. The Developer never sought to suggest that the substance of the decision was
incorrect nor that the inspector’s assessment was erroneous. It is not at all obvious as to
what benefit even a favourable ruling would have had for the Developer. An order of this
court setting aside An Bord Pleanála’s decision as invalid would not, for example, have the
legal effect of reviving the planning authority’s first-instance decision to grant planning
permission. See McCallig v. An Bord Pleanála (No. 1) [2013] IEHC 60, [86]. Nor would
the judgment have provided guidance for future decision-making.
65. Moreover, as a direct consequence of the delay in prosecuting these proceedings, this is
not a case where it would have been appropriate for the court to have made an order,
pursuant to Order 84, rule 27(4) of the Rules of the Superior Courts, remitting the
planning appeal to An Bord Pleanála for further consideration. Rather, any order would
have been confined to one setting aside the decision to refuse planning permission
simpliciter. If the Developer wished to obtain planning permission, it would have to make
a fresh application to the local planning authority. This is something that could have been
done in any event, without recourse to the courts.
66. The reason that remittal would have been inappropriate is that it would be contrary to the
spirit of the EIA Directive, with its requirement for timely decision-making and effective
public participation, to revive a planning appeal which had been determined more than
five years ago. This is especially so where the legal provisions governing the carrying out
of EIA have been amended in the interim. The amendments made to the EIA Directive by
Directive 2014/52/EU came into effect on 16 May 2017. The transitional provisions
indicate that, in certain circumstances, consent applications which were pending before
that date fall to be determined by reference to the old legislative regime. It would have
been contrary to the spirit of those transitional provisions to have remitted the planning
application the subject-matter of these proceedings to An Bord Pleanála. To do so would
have had the effect that the Developer would have the benefit of the old rules in respect
of a consent application which, in effect, would be made some two and a half years after
the implementation date for Directive 2014/52/EU.
67. It would also be contrary to the general approach adopted under the PDA 2000. The
legislation indicates that a planning appeal should ideally be determined within a period of
eighteen weeks. The legislation also provides that a planning permission must normally
Page 18 ⇓
be implemented within five years of the date of grant. It would be entirely inconsistent
with these timeframes to revive a planning appeal which had first been made to An Bord
Pleanála on 10 April 2012.
68. Finally, relief by way of judicial review would also have been refused on the basis that the
Developer has failed to put forward even an arguable case for saying that the outcome of
the decision-making before An Bord Pleanála might have been different had the (allegedly
omitted) EIA been carried out. Whereas an applicant for judicial review is not, of course,
required to establish that a breach of procedure has affected the substantive outcome of
the decision-making (Case C 72/12, Altrip), there is nevertheless a minimum standard
which must be met. In many objector-led cases, the argument will be that had the
competent authority carried out a proper EIA, then this would have disclosed some
environmental impact which might have led to the refusal of development consent.
69. On the facts of the present case, conversely, the Developer has not sought to challenge
the finding that the proposed development would have a “significant negative” impact on
the landscape character and visual amenity. Nor is this a case where a party argues that
they were not given an opportunity to make submissions on a point. As the procedural
history outlined earlier indicates, An Bord Pleanála afforded the Developer an express
opportunity to address its concerns in relation to the impact on landscape character and
visual amenity, by way of a request for further information.
70. The height of the Developer’s case is that the Board determined the planning appeal by
reference solely to the national law test of “proper planning and sustainable
development”, and failed to assess the significant impacts of the proposed development in
accordance with the EIA Directive. Even if this analysis were correct—and I have
concluded it is not—there is simply nothing before the court which suggests that a
different outcome would have followed for the planning appeal. The Board’s finding that
the development would have a significant negative impact on landscape character and
visual amenities of the area is self-evidently one which would have informed the
conclusion of any EIA process.
CONCLUSION AND FORM OF ORDER
71. The application for judicial review is dismissed. I will hear counsel on the question of
costs, and, in particular, on whether the proceedings are subject to the special costs rules
applicable to certain types of environmental litigation under Section 50B of the PDA 2000.
Result: Application for judicial review dismissed.