High Court of Ireland Decisions
You are here:
BAILII >>
Databases >>
High Court of Ireland Decisions >>
M28 Steering Group v An Bord Pleanala [2019] IEHC 929 (20 December 2019)
URL: http://www.bailii.org/ie/cases/IEHC/2019/2019IEHC929.html
Cite as:
[2019] IEHC 929
[
New search]
[
Printable PDF version]
[
Help]
Page 1 ⇓
THE HIGH COURT
[2019] IEHC 929
[2018 No. 708 JR]
BETWEEN
M28 STEERING GROUP
APPLICANT
AND
AN BORD PLEANÁLA
RESPONDENT
AND
CORK COUNTY COUNCIL
NOTICE PARTY
JUDGMENT of Mr. Justice MacGrath delivered on the 20th day of December, 2019.
Introduction
1. The applicant is an unincorporated environmental Non-Governmental Organisation
(“N.G.O.”) and has its office at Rochestown, County Cork.
2. The notice party, Cork County Council (“the Council”) on behalf of the Roads Authority,
proposes to upgrade 12.5 kilometres of the existing N28 national road. Part of this road
development is along the line of the existing N28, but a substantial part of it is offline.
The scheme is entitled “The Cork County Council M28 Cork Ringaskiddy Project Motorway
Scheme, Protected Road Scheme and Service Area Scheme, 2017”. The scheme was
made by the Roads Authority under s. 47 of the Roads Act, 1993 (as amended which
includes part XAB of the Planning and Development Acts, 2000-2016 and hereinafter
referred to as “the Act”) and it requires the approval of An Bord Pleanála (hereinafter “the
Board”) under s. 49. Before approving the scheme, a public inquiry must be held and
objections and observations considered. By virtue of the provisions of s. 51 of the Act, the
consent of the Board must be obtained prior to the carrying out of the scheme. The
submission of an Environmental Impact Statement (“EIS”) is mandatory by virtue of the
provisions of s. 50. The Notice Party sought the consent of the respondent for the
proposed development. An EIS was prepared and submitted, together with a Natura
Impact Statement (“NIS”) which was contained in the EIS and was prepared for the
purposes of Article 6 of the Habitats Directive.
3. The application for the consent was made on 15th May, 2017. The application pursuant to
s. 49 was made on the 2nd June, 2017 and included particulars of compulsory purchase
requirements, restrictions of access/egress and rights of way to be extinguished. A
mapping error was discovered by the notice party in relation to the proposed
extinguishment of certain rights of way and a corrected map/plan was submitted,
following re-advertisement, on 6th July, 2017.
4. Part of the land being acquired includes a portion of the existing Raffeen Quarry
(hereinafter “the quarry”). The quarry enjoys the benefit of a planning permission granted
in 2008. It is proposed that material from the quarry will be used in the construction of
the road. This is controversial as it is contended by the applicant that it will not be
possible to extract materials at the required rate without the terms of the quarry planning
permission being contravened, that the extraction of the materials at the rate required
Page 2 ⇓
has not been the subject of an Appropriate Assessment (“AA”) and that the environmental
impacts of the road and an operational quarry with such levels of extraction require to be
considered and assessed as one project, an exercise which has not been carried out. The
timing of the application for consent is also controversial, having been made on the eve of
the coming into effect of a new 2014 EU Directive, which altered the requirements for
such application for consent.
5. The Board appointed an inspector, Ms. Mary Kennelly, to report on the proposed
development. Objections were raised by a number of parties, including the applicant. An
oral hearing was convened. This took place in November and December, 2017. The Board
also appointed a traffic consultant who reported on the 1st May, 2018. The inspector
considered the proposed development and recommended that consent be given subject to
several conditions. She concluded that subject to the mitigation measures proposed on
the conditions attached to the permission, the effects of the proposed road development
on the environment would be acceptable.
6. By order dated 29th June, 2018, the Board granted approval and in doing so adopted the
recommendations of the inspector, including the proposed conditions. The decision of the
Board is challenged in these proceedings.
The Pleadings
7. The applicant, inter alia, seeks the following orders:
(1) An order of certiorari quashing the decision of the respondent dated 29th June,
2018;
(2) A declaration that the Board erred in national and EU law in failing to assess the
environmental impacts of the proposal as a whole, or cumulatively (or in
combination with) other projects. In particular, it is alleged that the respondent
failed to properly or at all consider the full effects of the development in terms of
the extraction of materials from the quarry required to give effect to the
development.
(3) A declaration that the Board erred in law in failing to apply Directive 2014/52/EU
(“the 2014 Directive”) which amended Directive 2011/92/EU (“the 2011 Directive”).
In the alternative a declaration that the Board erred in law in accepting the
application made in respect of s. 51 of the Act on the 15th May, 2017. The
application was premature, incomplete and did not meet the requirements of
National and European law. As such, the application was invalid and ought to have
been rejected by the Board.
(4) In the further alternative, if the application was validly made pursuant to the 2011
Directive, the Board failed to carry out an adequate EIA as required by Article 3
and/or Article 8 of that Directive, on the assessment of the effects of certain public
and private projects on the environment (“The Consolidated Environmental Impact
Page 3 ⇓
Assessment (EIA Directive)”) and/or s. 171A of the Planning and Development Act
2000, as amended.
(5) A declaration that the Board erred in law and acted contrary to fair procedures and
natural and constitutional justice and acted in breach of EU law and the Aarhus
Convention in failing to make available a copy of the planning file pursuant to a
request made on the 27th July, 2018 which request was not complied with until the
16th July, 2018. This ground was not particularly advanced at hearing.
8. After the Board had made its decision, the applicant sought a copy of the quarry planning
file and this was supplied. An application to amend the pleadings was sought and granted
by Barniville J. on 19th September, 2018. In amended statement of grounds the
applicant also claims a declaration that the Board failed to properly carry out an AA in
respect of the proposed development. This particularly concerns the alleged failure of the
respondent to conduct an assessment of the effects of the extraction of materials for the
proposed roadworks from the quarry, either as part of the project or in combination
therewith.
The Decision of the Board
9. The Board in its decision expressly stated that it had regard to those matters to which, by
virtue of the Planning and Development Acts and Regulations made thereunder, it was
required to have regard. These included the submissions and observations received in
accordance with statutory provisions. In particular, it states that it had regard to the
range of proposed mitigation measures set out in the EIS, the NIS and the schedule of
commitments.
10. The Board agreed with the screening assessment and conclusion in the inspector's report
that the Cork Harbour Special Protection Area (“SPA”) and the Great Island Channel
Special Area of Conservation (“SAC”) are European sites for which there is a likelihood of
significant effects. The Board stated that it had considered the NIS and the submissions.
It confirmed that it carried out an appropriate assessment of the implications of the
proposed road development for European sites; and that the information before it was
adequate to permit the carry out of that assessment. In completing the assessment, the
Board stated that it had considered, in particular, the likely direct and indirect impacts
arising from the proposed road development, both individually or in combination with
other plans or projects, the mitigation measures which are included as part of the current
proposal and the conservation objectives of the European sites. It accepted and adopted
the appropriate assessment carried out by the inspector of the potential effects of the
proposed road development on European sites, having regard to the sites’ conservation
objectives. It was satisfied that the proposed road development would not adversely
affect the integrity of those sites in view of their conservation objectives.
11. With regard to the environmental impact assessment (hereinafter “EIA”), the Board
confirmed that it completed an EIA under the provisions of the 2011 Directive taking into
account:
Page 4 ⇓
i. nature, scale, location and extent of the proposed road development;
ii. the EIS and associated documentation submitted with the planning application;
iii. the submissions;
iv. the responses from the applicant;
v. the mitigation measures proposed; and
vi. the traffic and transport consultation report.
12. The Board was satisfied that the information was adequate to identify and describe the
direct and indirect effects of the proposed development. It considered that the EIA of the
proposed road development, by itself or in combination with other development in the
vicinity, and concluded that, subject to the mitigation measures proposed, and the
conditions set out in its decision, the effects of the proposed development on the
environment would be acceptable. In doing so it adopted the inspector’s report. With
regard to the proper planning and sustainable development in the area, it concluded
that:-
“the proposed development would not have significant negative effects on the
community in the vicinity, would not give rise to a risk of pollution, would not give
rise to unacceptable visual or landscape impacts, would not have a detrimental
impact on archaeological and architectural heritage, would not seriously injure the
amenities of the area or of property in the vicinity and would be acceptable in terms
of traffic safety and convenience.”
It decided that a number of conditions, including that the proposals, mitigation measures
and commitments set out in the EIS and as clarified in the schedule of commitments
submitted by the local authority to the oral hearing on 1st December, 2017, must be
implemented as part of the development. In passing it is to be observed that one of the
conditions required omission of a proposed mitigation measure concerning the erection of
an artificial nest box for the peregrine falcon. The flora and fauna of the area, including
the quarry, had been much discussed at the hearing. This was because it was proposed to
be located in an area which could give rise to conflict with the bird species for the Cork
Harbour SPA. A number of other conditions not relevant to the current challenge were
also imposed.
The issues
13. Counsel for the applicant, Mr. Collins B.L., submits that this case concerns two issues. Ms.
Butler S.C., who represents the respondent, suggests that on closer analysis there are in
fact five areas of challenge.
14. The two issues which the applicant states arise for consideration are:
i. The validity of the application for approval made under the Act and specifically
whether a valid application was made on or before the 16th May, 2017 or as would
Page 5 ⇓
have the effect of taking the matter outside the ambit of the provisions of the 2014
Directive which came into operation on that date. It replaced and amended the
earlier 2011 Directive. The affidavit contends that the application ought to be
governed by the 2014 Directive and not the 2011 Directive.
ii. The Board failed to take into account all of the effects (direct and indirect) of the
proposed development, especially the effect of the extraction of millions of tons of
material from the quarry, which the applicant describes as being disused and
ecologically significant. Further, it is submitted, that there was a failure by the
Board to assess the effects of the development of the quarry to supply the material
required to construct the road, either as part of the project itself or as part of the
cumulative or in combination effects thereof. It is argued that the Board and the
notice party seek to rely on a grant of permission which was obtained by the
owners of the quarry, but without reference to its terms or without evidence that
those terms were considered in the approval process. It is contended that the
quarry does not enjoy a planning permission to operate at the level required to
service the road development and will involve a twelve-fold increase in operations.
It is claimed that this is not authorised, has never been assessed for environmental
impact nor has an appropriate AA been conducted. This contention centres on the
interpretation of the quarry permission. Thus, the planning permission in respect of
the quarry is described by the applicant as being of key significance and the failure
of the Board to concern itself with the terms and extent of that permission is
alleged not to be in accordance with its obligations. Particular emphasis is placed on
the proper interpretation of this permission in the light of the plans, specifications
and information provided at the time of the application for that permission. It is
submitted that there is no evidence that the quarry file was considered at any stage
of the process. It is contended that this is a fundamentally incorrect approach to
the approval and the EIA process and the Board must be satisfied that the
development can be lawfully carried out in accordance with the plans and
particulars lodged. The quarry permission authorises a continuation of the original
pre-1963 established user and while extraction on a campaign basis was envisaged,
it does not permit of the extraction of the quarry in a two-year period as, it is
claimed, will now occur. It is further claimed that a conflict arises between the two
permissions and the fullest assessment has been carried out in accordance with the
requirements of Commission v. Ireland (C-50/09). An EIA of the quarry extraction
is required. It is also claimed that as the road is to be constructed across the quarry
the previous restoration conditions attached to that permission are unworkable.
15. The respondent submits that there are five issues:-
i. Whether the quarry should have been part of the road project;
ii. The assertion that the Board did not carry out a cumulative EIA of the road and the
quarry;
iii. The alleged lack of AA in respect of the quarry works;
Page 6 ⇓
iv. Ecological complaints about a failure to assess the quarry; and
v. Which iteration of the Directive should have been applied to the project?
16. The respondent and notice party maintain that the applicant does not have locus standi to
raise the issue of the quarry permission, the assessment of the quarry in 2012 or that the
project should be regarded as one which involves the road and the quarry, such points
not having previously been raised at the Board’s inquiry or otherwise. It is contended that
the applicant’s challenge in this regard amounts to a collateral attack on the quarry
permission, in circumstances where the party who has the benefit of the permission is not
before the court and was not a party to the application; and is based on an assumption
that the terms of that permission will be breached by the third party.
17. On the other hand the applicant maintains that it is not seeking to challenge the quarry
permission or the 2012 review which had been conducted in respect of the quarry under
s. 261A of the Planning Acts, but it points to the shortcomings of the review observing
that, because the screening of the quarry in 2012 took into account the conditions which
were imposed and attached in the determination in concluding that an appropriate
assessment was not required, this was inadequate in the light of the jurisprudence of the
European Court of Justice, and in particular the decision in Commission v. Ireland.
Further, the applicant maintains that the review looked back, rather than forward, and
never considered extraction at what it contends are such increased levels.
18. I address below the contents of the EIS and AA in so far as they are relevant. In the light
of the contentions regarding the quarry, something ought to be said of the planning
permission attaching to it and also the review which took place, as these were a particular
focus of this challenge. First, the relevant evidence on affidavit ought to be considered.
The Evidence
19. The statement of grounds was verified by affidavit sworn on the 27th August, 2018 by
Mr. Gerard Harrington, a businessman and a member of the committee of the M28
Steering group. The essential matters outlined in the statement of grounds and as
described above were attested to. The grounds were subsequently amended and in a
further affidavit sworn on 19th September, 2018, in support of the application to amend,
he explains that at the time of the making of the application for leave to seek judicial
review before the court on the 27th August, 2018, the applicant had not received a full
copy of the Board’s file. While the file in relation to the quarry had been sought from the
Council, it had not at that stage been received. These documents were not available on
line and the full file was delivered to the applicant’s solicitors on the 17th September,
2018. It is explained that while the applicant had originally pleaded, in draft proceedings,
the failure of the Board to carry out an AA in respect of the application, on the advice of
counsel this ground was deleted in advance of filing the statement of grounds as the
circumstances surrounding the assessments of the quarry were unknown. When the
matter returned to court, counsel explained that there was a likelihood that once the full
circumstances were known an application for an amendment would be required.
Page 7 ⇓
20. Mr. Harrington avers that on consideration of the quarry planning file and the materials
received relating to it, it became apparent that no AA had been conducted in the course of
the planning process. It was evident from the file that the site was proximate to, and
linked with the Cork Harbour SPA, a European site. Included in the file were details of a
screening for assessment which took place in 2012. Mr. Harrington avers that it is
apparent from the report that the site was screened out on the basis that Monkstown
Creek had not been designated at the time of the application for permission. It was also
screened out on the basis that compliance with conditions attached to the permission that
the levels of operation, and in particular blasting would be such as would not be likely to
have significant effects on the SPA. While screening a development out on this basis is
wrong as a matter of law, the level of quarry operation now contemplated as part of the
road scheme involving its complete exhaustion in three rather than 30 years, has never
been permitted, described or assessed either as part of the road scheme or the quarry
permission. The quarry permission granted did not permit this development or any such
intensification of user. He asserts that no consideration was given by the Board, in its
assessment of the development proposal, to the quarry permission and that the road
development is not compatible with such permission. Central to the applicant’s argument
is that the quarry permission permits a gradual 30 year extraction of the material above
the water table and not the extraction of the same quantity of material over three years.
He states that the quarry permission and conditions attached thereto were designed to
regulate a development to be carried out at a much lower intensity over a greater
timespan. A restoration plan was provided as a condition to the quarry permission and the
laying of the road itself across the site will effectively mean that such restoration will not
be possible.
21. Fundamentally, Mr. Harrington makes the case that as the development of the quarry in
this manner is a new development, it forms part of the overall road project and is
required to be described and assessed as part of that project as a matter of national and
EU law. At minimum, he believes that the development of the quarry required to be
assessed as part of the cumulative effects on the project. What is now envisaged is a very
different development to that for which permission has been granted. He maintains that
consideration of environmental matters against a baseline of a permitted and operating
quarry is an incorrect approach in circumstances where the quarry is in fact disused. The
proper baseline is that which currently pertains, i.e. a non- operating quarry, which will
resume operation as a result of the scheme. This is a direct effect of the scheme and all
such effects need to be assessed on both macro and micro levels. This has not been
assessed. There is no description of the type or quantities of the materials to be used in
the road development, no description of their sources other than an assertion that the
quarry would supply the materials for the development and there is no assessment of
such extraction.
22. While Mr. Harrington was initially critical of the failure of the Board to provide sufficient
information for the purpose of consideration of Judicial Review proceedings, on the
opening of this application Mr. Collins B.L., while maintaining such criticism, accepts that
it is not of practical significance because the proceedings were in time.
Page 8 ⇓
23. Dr. Goodyear, an Ecologist, in an affidavit sworn by her in support of the application on
29th January, 2019, avers that she participated in the planning application and attended
and gave evidence to the oral hearing. She raised a number of issues concerning the
potential impacts on the fauna and flora of the quarry, including and in particular two
species, being the peregrine falcon and the pennyroyal plant, which is protected under
the Flora Protection Order 2015. It is considered an endangered plant species. She also
raises the issue of the hydraulic link between the quarry and the nearby SAC and
contends that the extraction at the proposed level has not been properly assessed as part
of the road scheme. She avers that the development of the quarry at a massively
increased extraction rate required to supply the road is a new development and requires a
new application for permission or to have been assessed as part of the road approval
scheme. Therefore it is either part of the project or a direct effect of it. In either event, it
requires to be assessed in its own right and/or cumulatively in combination with the
scheme. She also points out that it is not now possible to carry out the quarry restoration
plan. Thus, ecological restoration of the quarry remains unaddressed. It is also unclear as
to who is responsible for the quarry restoration.
24. Mr. Kevin Hanley, is also a member of the applicant steering group and resides
immediately adjacent to the quarry. In his affidavit sworn on the 17th January, 2019 he
echoes many of the concerns expressed by Mr. Harrington. He avers that the quarry has
been inactive for over 20 years and as matters exist, he enjoys a quiet and peaceful
existence. The quarry has become a wildlife habitat and has returned to nature. He
expresses concern at the effect on his quality of life and that of his family in the event of
a return to quarrying. His is one of 15 families living in the immediate vicinity of the
quarry. There is a Montessori school within 100m of its northern boundary. The impact of
the quarry in terms of dust and noise are directly linked to the intensity of the operations
and he believes that on a simple analysis, blasting will require to be 12 times more
frequent than the permission allows. He refers to an incident of a flying rock when the
quarry was operational. Although no one was injured, structural damage was caused to
his home and he fears that this will happen again. He is concerned that the complete
extraction of the quarry in a three year period will be intolerable and expresses his belief
that the 36 year period was calculated on the basis of the length of time it will take to
extract the full amount of material from the quarry; and that the time limit was set based
on the expected rates, being those undertaken historically. He expresses further concern
about an unrestricted quarry activity in terms of hours of operation and truck movements.
25. An affidavit in support of the application was also sworn by Mr. Pat O’Donnell, Chartered
Engineer, on 19th February, 2019 in which he addresses the procedures under s. 261 of
the Planning and Development Acts, as amended, to which the quarry was subject. These
provisions and procedures were enacted for the purposes of regularising the quarry
industry. Quarries that had the benefit of pre-1963 user were required to be registered.
The court shall address this in greater detail below. He outlines the nature of the
application for permission made by the owner of the quarry. The registration document
signifies that the quarry was a pre-1963 quarry with an extraction area of 26 ha and level
of operation expressed to be 10,000 truck movements per year; which equates to 30/40
Page 9 ⇓
truck movements per day, or 15/20 loaded trucks leaving the site per day. This amounts
to approximately 100,000 tons of excavated material per annum. He believes that there
was no application for permission of an increase over the threshold of 100,000 tons per
annum. This conclusion is supported by the EIS which accompanied the application for
permission. The environmental impacts are calculated, described and assessed on the
basis of existing operations. In his opinion, there is no evidence that an AA had been
conducted as part of the s. 261 process and no NIS was submitted with the application.
This was not surprising given the application was made in 2006 and the State had not
then properly implemented the Habitats Directive. Nevertheless, mitigation was proposed
on the basis of a quarry extracting at the level of 100,000 tons a year and employing
three or four people. This is a small-scale operation. The environmental impacts of the
quarry operations are directly linked with the intensity of operation. Most of the legal
authorities on the subject of quarrying concern an increase in the intensity of operations.
In this case, intensity of operation will be critical given the quarry’s proximity to
environmentally sensitive receptors. Mr. O’Donnell highlights a response by the quarry
developer to queries raised by Cork County Council when permission was being
processed. In one of those responses, the developer clarified that:-
“the future operation of the quarry is proposed to be on a ‘campaign basis’, subject
to market demand. The predicted timeframe for the proposed works phasing has
been based on current output of volumes and is consistent with the traffic
generation figures that have been registered with Cork County Council at section
261 Registration stage.” (emphasis supplied)
26. Mr. O’Donnell avers that there is no doubt but that the quarry was intended to continue
operating at its then extraction rates and although the rate may rise and fall with
demand, the maximum level was defined in the lifetime of the permission and was set
accordingly. The imposed conditions were predicated on such level of operation. Thus, for
example, condition number 1 mandates that the development be carried out in
accordance with the plans and particulars lodged, including the EIS, RFI and CFI. An
appeal was lodged by the developer but only against certain conditions. The Board did not
conduct a full EIA of the proposed development. In essence, he maintains that any
assessment that was carried out was on the basis of 100,000 tons permitted. On appeal
the Board made some minor changes concerning the deletion of traffic conditions but no
particular reason was advanced for this. He asserts that it must be presumed that given
that the levels of traffic were already set out in the plans and particulars, it was felt
unnecessary to impose the secondary hard daily limit. The condition in respect of the
blasting limitation remains. Mr. O’Donnell avers to his opinion, that having regard to the
terms of the permission and the approval for the road, the proposed extraction of
material cannot occur under the terms of the existing planning permission. In his view,
extraction of material required at the rates necessary will involve in excess of a tenfold
increase in extraction which he describes as a massive intensification of the development
of the quarry. There are clear constraints on the operational hours of the quarry. He
believes that if the material is extracted mechanically as proposed, the noise levels, dust
levels and operating hours will increase exponentially and none of these effects have been
Page 10 ⇓
permitted or assessed. It was open to the quarry owners to submit an application for
permission to permit extraction of the entire quarry over a two to three-year period but
this was not done. An AA was not carried out when the s. 261 procedure was being
conducted and he believes that the author of that review, Ms. Casey, was influenced in
her conclusion by reason of the conditions which were imposed on the planning
permission, which regulate a much lower extraction than is now envisaged.
27. A replying affidavit was sworn on behalf of the respondent by Mr. Chris Clarke, Secretary,
An Bord Pleanála. He outlines the chronology of events and exhibits and refers to various
documents which accompanied the application on 15th May, 2017, including the EIS and
the NIS. The scheme/CPO application for approval was made on 2nd June, 2017. On the
22nd June, 2017, the Board received a letter from the notice party, stating that there was
an error in a deposit map drawing which had been submitted with the scheme application.
On 26th June, 2017, the Board wrote to the notice party requesting further information in
the form of a revised deposit map drawing. The Board required publication of a new
notice of the scheme/CPO application and extended the period for public consultation by
six weeks. On 6th July, 2017, the notice party submitted the revised map drawing and
associated details and on 12th July, 2017 confirmed publication of new notices. Numerous
submissions were received including those from the applicant on 16th August, 2017. An
oral hearing was convened and held between the 7th and 10th November, 14th and 17th
November and 28th November to 1st December, 2017. The Board inspector prepared a
report dated 31st May, 2018. The Board considered the applications at meetings on 6th,
13th and 28th June, 2018, and its direction of 29th June, 2018 records the determination
of the Board to grant approval in accordance with the terms outlined therein. On 27th
July, 2018, the applicant’s solicitors requested a copy of the Board’s file and Mr. Clarke
avers that two discs located on the Board’s file were forwarded to the applicant’s solicitors
in the mistaken belief that they had in fact contained the complete file.
28. By letters dated 3rd and 11th September, 2018, the applicant’s solicitors wrote to the
Board acknowledging receipt of the discs but requesting a hard copy of the file. That
request was refused by the Board on 14th September, 2018. This was because the Board
was handling a large volume of similar requests at the time and because it had
understood that the applicant had already been furnished with an electronic copy of the
complete file. By further email of the 17th September, 2018, the applicant’s solicitors
indicated that while the discs contained application documentation, the EIS, the NIS, and
the submissions made to the Board at the oral hearing, they did not contain internal
Board documentation, notes or memoranda. A complete copy of the Board file was
provided to the applicant’s solicitor by 20th September, 2018.
29. Mr. Bob O’Shea, is an engineer in the National Roads Office of Cork County Council, the
notice party. In his affidavit sworn on the 22nd November, 2018 he verifies the contents
of the notice party’s statement of opposition and outlines the chronology of events. The
motorway scheme was submitted for approval to the Board pursuant to s. 49 of the Act.
Such schemes deal with matters such as compulsory purchase requirements, restrictions
of access/egress to the carriageway and the extinguishment of public and private rights of
Page 11 ⇓
ways. No EIS or NIS is required or was submitted in respect of that application. Following
the submission of the schemes to the Board, it became apparent to the notice party that
there was a mapping error in one of the drawings which had not identified the public and
private rights of way proposed to be extinguished. Mr. O’Shea states that it was for this
reason that a new map was submitted. This was the sole error of the application. A
revised deposit map drawing was prepared, published, made available for inspection in an
extended time period and notices were erected in prominent positions at the public rights
of way proposed to be extinguished. The revised deposit map drawing was furnished to
the Board by letter of 5th July, 2017. On 11th July, 2017, a letter was sent by the notice
party to the Board confirming republication in newspapers and other public notices.
30. With regard to the road development application, Mr. O’Shea avers that this was
accompanied by an EIS and NIS and was received by the Board on 15th May, 2017. It is
therefore contended that it falls to be considered by reference to the requirements of the
2011 Directive. He believes that this position is not altered by reason of the submission of
the motorway scheme application on 2nd June, or as a result of re-publication due to the
mapping error. It is his belief, and the position of the notice party, that the EIS complied
with the requirements for the 2011 Directive including Article 5(2) and Annex IV thereof.
Fundamentally, he maintains that the requirement to assess the development of the
quarry as part of the cumulative effects of the project was in fact undertaken and that
both the EIS and NIS address this. The potential for significant effects on the natural
environment were addressed in the EIS. Thus, Mr. O’Shea states that it is acknowledged
that the quarrying operations may affect plant species protected under the Flora
Protection Order and breeding bird activities upon areas of quarry cliff face, principally
through indirect disturbance, which previously supported the breeding peregrine falcon.
The EIS also acknowledges that quarrying activities may result in increased release of
dust and particulate matter which can reduce photosynthetic potential for plants
associated with in situ and adjacent semi-natural habitats. The potential for cumulative
effects on sensitive eco systems from dust and particulate matter during the construction
and operational phases of the road and quarrying activities are also identified.
31. Mr. O’Shea avers that the whole project in this case is the proposal to construct the road,
part of which is through the quarry, on lands acquired under the approved motorway
scheme. The impact of the road development on the quarry was fully considered as part
of the EIA and AA undertaken by the Board. These assessments took into account the
existence of the quarry planning permission following the submission of an EIS by the
quarry operator and the carrying out of an EIA by the notice party and the Board. The
quarry planning permission exists independently of the road development application. He
also contends that neither of the screening determination undertaken under s. 261A(2)
nor the quarry permission were challenged by the applicant or any other party. The
notice party signalled an intention to use materials extracted from the quarry in the
construction of the road and this is referred to in the EIS, Volume 2, s. 17.4.2.1. It was
identified in the EIS that the construction of the road will require approximately 2.2
million cubic metres (m3) of fill material. It is anticipated that approximately 1.15 million
m3 of useable material will be excavated from the cuttings for the project and that,
Page 12 ⇓
therefore, there will be a deficit of material required to construct the project, including the
project requirements for higher quality rock material, in the order of 1.05 million m3. It is
anticipated that, where possible, the majority of the material will be obtained from the
quarry under its current planning permission. The notice party maintains that this has the
advantage of maximising the sustainable reuse of materials available close to the site,
minimise carbon footprint, noise and air emissions associated with transport and adheres
to the principle outlined in the Southern Region Waste Management Plan, 2015 – 2021.
32. Mr. O’Shea maintains that full consideration was given to the direct and indirect
cumulative affects associated with quarrying activities. He also maintains that the
applicant is incorrect in its assertion that the quarry permission does not permit
extraction of material over a three year period and that extraction may occur on an
accelerated basis does not amount to an intensification of user. The EIS dealt extensively
with the flora and fauna of the quarry in its current condition and was considered
extensively at the hearing. He avers that the conditions attached to the quarry permission
will have to be adhered to and that it is significant in the context of the 2012 screening
report for AA, that the Council was of the view that the quarry permission contained
significant safeguards governing extraction activities, including those in relation to the
potential for impacts on designated site areas for the purposes of the Habitats Directive.
Thus, when the quarry permission was granted, following an appeal to the Board, the
permission was restricted to extraction above the water table and measures were put in
place in respect of surface water, hydrocarbon interceptors and the requirement to
develop and implement environmental and storm water management systems.
33. Chapter 12 of the EIS contains a detailed ecological assessment of the quarry both for the
section of the quarry within the CPO line and road footprint and those areas located north
of the CPO line, being the entire boundary of the quarry. The EIS addresses the habitats
and species found within the quarry. The flora and fauna in the quarry have been
assessed in the EIS and the NIS. A detailed survey of the quarry, including a botanical
survey and assessment of the wetlands in the quarry was completed by Dr. Cillian Roden.
Pennyroyal was discovered in the quarry and translocation was proposed. An area of land
was identified for this purpose and was included in the CPO. However, following
publication of the EIS and during the course of the oral hearing further discussions with
the National Parks and Wildlife Services (“NPWS”) it was concluded that the pennyroyal in
the quarry was in fact of the non-native variant. Mr. O’Shea alludes to this as an example
of the detail into which the local authority went to address habitat and ecological issues.
Further, throughout the EIA process, open dialogue took place with the NPWS and various
specialist botanists/ecologists. The quarry was identified as an ecological receptor and
the EIS evaluated it as a habitat complex which is considered to be of county importance
ecologically. Habitats and species found within the quarry are described in s. 12.5.2 of the
EIS. Table 12.18, identifies the quarry as an ecological receptor within the study area and
the EIS addresses the ecological receptors located in the quarry, which are considered to
be of county importance. Therefore, he avers that the quarry is not of national or
European importance and there will be no direct or indirect impact on any Natura 2000
Page 13 ⇓
site as detailed in the NIS. He avers that there are no species within the quarry that are
of European importance.
34. Mr. O’Shea also highlights the conditions attached to the consent to the road
development. These include certain conditions to mitigate the environmental effects of
the development. He disputes Mr. Harrington’s averment that the quarry will only reopen
as part, or as a result, of the proposed project and states that no evidence of this has
been produced by Mr. Harrington. He also states that Mr Harrington’s averments do not
take into account the existence of the current quarry permission which permits extraction
activities up to 2038, an activity which can be undertaken whether or not the road
development project proceeds.
35. With regard to the allegation that there will be a tenfold intensification of the
development, Mr. O’Shea believes that this is incorrect and takes no account of the fact
the quarry operations by their very nature depend on an available market for material
extracted. He re-iterates that any extraction of materials to be used in connection with
the road development must be in accordance with the terms of the quarry permission and
the conditions attached thereto. It is disputed that the quarry permission does not permit
extraction of the material over a three year period or that if extraction occurs on an
accelerated basis it will amount to intensification so as to require a new planning
application. He states that if there was any substance to the contention that extraction
was to be gradual over the entire 30 year period, given that ten years has now elapsed a
maximum of two-thirds of the originally permitted limit would now be permissible. In his
address to the court, Mr. Collins B.L. states that Mr. O’Shea is correct in this regard.
36. Mr. O’Shea also refers to the 2012 review. The primary impacts which could be caused to
the Cork Harbour SPA by activities at the quarry relate to water quality and in particular
the potential for contaminated runoff to affect habitats upon which species are dependent
for feeding and in respect of which the SPA is designated. No potential for impacts on the
Cork Harbour SPA were identified in the EIS prepared in connection with the 2008 quarry
permission and he believes that this was a reasonable conclusion. The screening report
noted the various safeguards contained in the 2008 permission, which govern extraction
activities. In addition, he avers that stricter mitigation is proposed in respect of sensitive
areas, including the quarry, and that such measures are detailed throughout the EIS. At
Table 18.4 in the EIS it is recorded that the literature suggests that the most sensitive
species appear to be affected by dust deposition at levels above 1,000 mg/m2/day.
Therefore, once dust deposition rates are maintained within the standard guideline for
human nuisance being 350 mg/m2/day the impact of construction dust on sensitive
ecosystems is considered negligible. The mitigation measures in respect of dust are
outlined in chapter 13. Mr. O’Shea also avers that the in-combination affects were
considered in the NIS which indicated that quarrying operations would not contribute to a
cumulative or in-combination impacts to the Cork Harbour SPA.
37. Mr. O’Shea takes issues with the suggestion that the correct baseline which pertains to
the quarry is one based on a quarry which is not operating but will resume operation as a
Page 14 ⇓
result of the scheme. The quarry permission permits the resumption of quarrying
operations with or without the scheme. The EIS and NIS address the baseline as of 2016,
when the quarry was not operating. Thus, the baseline data was representative of
conditions which prevailed at that time. He also takes issues with Mr. Harrington’s
averment that there was no assessment of the extraction. The earthworks quantities and
material balances are described in volume two of the EIS in chapters 3, 11 and 17,
specifically at ss. 3.13.51 and 17.4.2. Chapter 11 of the EIS, Volume 2, examines the
soil’s geology and hydrogeology along the proposed road scheme including the quarry.
38. Mr. O’Shea also objects strongly to the raising of issues relating to the AA in these
proceedings as they were not raised by the applicant before the Board. The information
was known or capable of being known to the applicant when it framed its objection and at
the time of the oral hearing. He believes that the seeking and obtaining of the planning
file for the quarry after the Board’s determination is no answer to the applicant’s failure to
raise all relevant issues before the Board during its consideration of the road development
application. Nevertheless, he avers that the NIS addressed impacts arising from the
quarry and concluded that the quarrying operations will not contribute to cumulative or in
combination impacts to Cork Harbour SPA. In particular, s. 5.5 of the NIS, entitled
“Conclusion of Impact Assessment”, addresses the potential of in combination effects. All
possible sources of effects from the proposed road project, in combination with all other
sources in the existing environment, and any other likely effects to arise from the
proposed plans or projects were identified. While it is correct to say that the Monkstown
Estuary was not part of the Cork Harbour SPA at the time of the quarry planning
application, Mr. O’Shea avers that the applicant does not provide any evidence as to how
this would alter the findings of the 2012 screening exercise, or indeed the conclusions
contained in the NIS which were submitted as part of the road development application.
39. In a further affidavit sworn on 15th February, 2019, Mr O’Shea states the road
development was assessed in the light of the existing conditions of the quarry permission,
including blasting restrictions of four times per month and the obligation to cease
extraction once the groundwater level reached.
The Quarry Permission and the 2012 Review
40. The quarry is owned by John A. Wood and Co. Ltd., which is not a party to the application
or to these proceedings. It enjoys the benefit of a permission under planning reference
number 06/10037 (hereinafter “the quarry permission”). Before this the quarry had the
benefit of a pre-1963 use, a use which was accepted by Cork County Council when the
quarry was registered under s. 261 of the Planning and Development Act 2000, as
amended (hereinafter “the Planning Acts”). The operators were directed to submit a
planning application with an EIS. Planning permission was granted subject to a number of
conditions. The conditions were appealed to An Bord Pleanála which modified them.
41. The planning application was submitted on the 29th August, 2006, and the nature and
extent of the proposed development was described therein as:-
Page 15 ⇓
“Application for continuation of quarrying activities including the processing of
aggregates, landscaping, restoration and associated works at the existing
registered quarry lands at Raffeen Quarry in accordance with Section 261 of the
Planning and Development Act 2000.”
At para. 11 of the form, details were sought of any application in respect of a material
change of use or retention of a material change of use, to which the answer “N/A” was
given. At question 12, the applicant was requested to state any special reason for the
selection of this particular site, to which was answered “Limestone quarry in existence
prior to 1963. The quarry has been registered under Section 261 of Planning and
Development Act 2000.” The application was accompanied by an EIS. At question 29, an
estimation of the number of employees and of traffic likely to be generated evoked a
reply “(a) Directly 4 (including one part-time) and (b) 10,000 truck movements per
annum when quarry is in operation on a continuous basis.” The applicant places particular
emphasis on these queries and replies as being fundamental to the proper manner in
which the quarry permission ought to be interpreted. Emphasis was also placed on the
EIS which accompanied this application and the reference to the extraction of materials
on a campaign basis, based on local market demand and the fact that up to that time
production of the quarry was intermittent. The EIS also referred to matters including
excavation by excavator only refers to the equipment that might be used such as a
loading shovel, mobile crusher and mobile screener.
42. The initial application envisaged that extraction would be completed over five phases to a
finished floor level of approximately -20 0D. The operational times of the quarry were
specified as between 7a.m. and 8p.m. and not on Sundays. It specified the number of
employees. The applicant maintains that such level of employment and activity is
inconsistent with and will be unable to accommodate the amount of excavation that will
now be required. It is also stated that it is evident from the EIS, under the heading
potential impacts that the baseline was its then current level of operations.
43. At para. 4.4 of the EIS it is acknowledged that the continued use of the quarry will have
negative effects on the local population, that it will operate under strict guidelines and
that current mitigation measures and those proposed in the EIS would ensure that the
quarry was operated in such a way as to limit the impact on the surrounding
environment. It was also noted that the Glounatouig stream flow through the northern
part of the site and into the estuary at Monkstown Creek approximately 900 m
downstream of the quarry site. A number of potential impacts were identified and it was
stated there would be no direct impacts on any designated sites but that indirect impacts
which may potentially occur and cause further deterioration in water quality of the
Glounatouig stream. It was noted that there had been no direct discharges to the stream
when the quarry was in operation and that assessment of the stream had indicated that
the watercourse was moderately polluted in the vicinity of the site. Nevertheless, it was
stated in the EIS that the continued use of the quarry should not result in a significant
impact on the water environment.
Page 16 ⇓
44. A notice requiring further information was raised by the local authority. The developer
was requested to advise whether the future operations of the quarry was proposed to be
on a campaign basis or ultimately to be a full-time operation. Detailed
verification/clarification was sought of (i) the proposed future operation of the site and (ii)
the anticipated life of the quarry. The expected duration of each of the five phases was
required to be outlined. In response, the predicted timeframe for the first proposed
working phase was stated to be 0-36 years. The developer advised that the future
operation of the quarry was proposed to be on a campaign basis, subject to market
demand. The predicted timeframe for the proposed works phasing was based on current
output of volumes and was consistent with the traffic generation figures that were
registered with Cork County Council at s. 261 registration stage. Information concerning
dust monitoring and the results of such monitoring was also sought. A restoration plan
was addressed. Restoration was to be on a phased basis, those relating to phase 1 being
primarily of a shrub and tree planting nature. The applicant also refers to a query which
was raised concerning a requirement that the landscape/visual impact assessment should
be revised to include an assessment from the N28 road improvement scheme.
45. Planning permission was granted by the local authority on 28th August, 2007, subject to
74 separate conditions. Significantly, condition number 43 provided that no quarry
activity should take place below the water table. Thus, permission was authorised for the
continuation of quarrying only for phase 1 of the proposed extraction plan. The condition
provided that at the end of phase 1, i.e. when extraction reaches 16m OD or when the
water table is encountered, whichever is the sooner, quarrying activities must cease and
the site be reinstated, unless planning permission is obtained to continue operations. A
condition was imposed regarding the operating hours of the quarry. Conditions were
imposed in relation to noise levels, frequency of blasting (not to exceed four per month)
and it was also provided that site landscaping and restoration should be in accordance
with the plans submitted. Condition number 73 provided that a maximum vehicle
movement of 34 vehicles per day should not be exceeded.
46. A number of the conditions attached to the permission were appealed to the Board and
certain modifications were made. One such condition related to the frequency of blasting
of no more than four times a month on the ground that the condition had the potential to
restrict the operations greatly and that there did not appear to be an engineering or
environmental reason for this. Messrs John A Wood and Co stated that they regarded this
as an example of a new restriction for which they should be entitled to compensation
pursuant to s. 261(8)(b) of the Act, if the condition was upheld. An appeal was also made
against condition number 43 and it was stated that if the condition was upheld it would
force the closure of the quarry. The developer protested that the local authority, in
framing this condition, had effectively sought to render unauthorised approximately 76%
of the authorised reserves of the site. Again, this suggested that compensation would
arise in the event of this condition being maintained.
47. The Board appointed an inspector who visited the site on 2nd April, 2008. A report was
prepared on 10th April, 2008. With regard to condition number 43, the inspector reported
Page 17 ⇓
that the timespan for phase 1 was estimated as 1-36 years based on what she described
as a very low extraction volume of 100,000 tons/year on a campaign basis. She noted
that if the rate increased to 300,000 tons/year then phase 1 timespan would decrease to
approximately 10-12 years on a full-time basis. She thought that the completion of phase
1 would involve the clearing of the entire section of phase 1 prior to commencing phase 2,
which was unrealistic and impractical. Nevertheless, she did not recommend any change
to condition number 43. With regard to condition number 73, again no change was
recommended. Condition number 24 regarding blasting operations was maintained in the
final permission, the inspector having conducted an analysis of the number of dwelling
houses in the vicinity and other potential receptors.
48. While the Board removed condition number 43, certain additional conditions were
imposed including that the permission was for a period of 30 years from the date of the
order and that no quarrying should occur below the groundwater level of 16 m OD. In its
decision, the Board stated that it considered that the information set out in the EIS
including the pumping tests was insufficient to assess the future impact of pumping in a
large area which has an aquifer of extreme vulnerability with karstic features. Without
that information the Board was not satisfied that the quarrying operation would not
constitute an unacceptable risk to ground and surface water resources. Any development
below that level should be subject to a future planning application. Condition number 73
was also removed but without any particular comment.
49. The appellant observes that the Board did not carry out a fresh assessment, rather dealt
with particular conditions. The Board imposed a condition, condition number 21,
stipulating that noise levels may be exceeded to allow temporary but exceptionally noisy
phases in the extraction process or for a short-term construction activity which is required
to bring long-term environmental benefits following written consent by the planning
authority.
50. Mitigation measures were identified as was a restoration plan. Landscaping was
addressed as part of the restoration works, on an as you go basis.
51. In July, 2012, Ms. Sharon Casey conducted a review under s. 261A of the Planning Acts to
determine whether an AA was required and, if so, whether this had been completed as
part of the planning process. In her review she noted that two Natura sites are located
within 15km of the quarry; the Sovereign Island SPA and the Great Island Channel SAC.
The potential for the quarry to give rise to environmental impacts on the qualifying
features of the Sovereign Island SPA was ruled out on the basis of the scale of the quarry
and its distance from the SPA. The potential for quarry activities to give rise to impacts of
the Great Island Channel SPA was ruled out having regard to the distance, and its
location down channel, from the SAC.
52. It was noted that the quarry is located some 900m west of the Cork Harbour SPA,
another Natura 2000 site. The northern boundary of the quarry was described as being
adjacent to the Glounatouig Stream which discharges into the Monkstown Creek, a part of
the Cork Harbour SPA. Protection under the Natural Habitats Regulations, 1997 applied to
Page 18 ⇓
the Cork Harbour SPA, which had been designated for the occurrence of nationally and
internationally important species on 21st November, 1994 pursuant to S.I. 349 of 1994.
At the time of designation in 1994, the Monkstown Creek did not form part of the SPA.
Amendments were made to the boundary of the SPA. Notification was given on the 27th
August, 2008 of intention to designate the site under the Habitats Regulations, and
Monkstown Creek was included within the SPA from that time. The decision of An Bord
Pleanála on the quarry permission was given on the 16th July, 2008, prior to the
extension of the boundary of the SPA. Therefore, as Ms. Casey noted, activities which
were permitted after the designation of the Cork Harbour SPA required to be screened to
determine whether they could be likely to give rise to impacts on the Cork Harbour SPA.
Ms. Casey recorded that these included the phased extraction by drilling and blasting of
limestone, crushing and screening of material on site and storage of aggregates on site to
a finished floor level of approximately -20 OD and landscaping and restoration of the site.
She observed that activities in the site had not given rise to any direct loss of habitat
within the SPA and considered that the potential for blasting at the site to have caused
disturbance to the SPA was low. She stated:-
“The primary impacts which could be caused to the SPA by activity at this quarry
relate to water quality, and in particular the potential for contaminated run off from
the quarry to affect habitats upon which species for which the SPA is designated are
dependant for feeding.”
53. A review was conducted of the EIS, information submitted, the report of the inspector
appointed by the Board and the permission conditions as amended. Ms. Casey observed
that no potential for impacts were identified on the Cork Harbour SPA in the EIS. She
considered this to be a reasonable conclusion having regard to the fact that the
downstream estuary was not part of the SPA at the time the planning application was
made, and the distance of the quarry from other parts of the SPA. She also observed the
following:
(i) that the permission restricted extraction to above the water table;
(ii) the requirement that soiled surface water be directed to settlement tanks prior to
discharge to the adjacent stream;
(iii) the requirement to install and monitor a hydrocarbon interceptor;
(iv) the bunding of fuel tanks;
(v) the requirement to develop and implement an environmental and stormwater
management system for the site; and
(vi) that hydrocarbon interceptors with silt storage had to be constructed upstream of
storm water outfalls.
54. Ms. Casey concluded:-
Page 19 ⇓
“Having regard to the conditions which were imposed, and the boundary of the SPA
as it exited at the time that authorisation was granted for this development, I
consider the potential for this quarry to have given rise to impacts on this site to be
low…
… I consider that there was no requirement for development as permitted at this
quarry under 06/100037, with conditions amended by PL 04.225610 to have been
subject to Appropriate Assessment.”
Submissions
55. The applicant contends that the application for approval pursuant to s. 51 of the Act
which was submitted on the eve of the coming into force of the 2014 Directive was
premature, incomplete, and did not properly describe the proposed development. It did
not meet the requirements of either the 2011 or 2014 Directives and is invalid.
56. Under the terms of the 2014 Directive, and in particular Article 3(2) thereof, applications
in respect of which the information referred to in Article 5(1) of 2011 Directive was
received before the 16th May, 2018 continue to be considered under that Directive.
Applications in which such information was received after the 15th May, 2018 fall to be
considered under the 2014 Directive. In the instant application it is submitted that the
information listed in Article 5(1) was received after the 15th May, 2017. Article 5(1)
specifies the making available by the developer of the information specified in Annex IV of
the Directive, which in turn requires that the developer make available a description of
the project including in particular (but not limited to) a description of the characteristics
of the whole project and the land-use requirements thereof during construction and
operation. It is submitted that as the full land-use and land take description was not
provided until the 22nd June, 2017 the required information was not provided before the
transition date.
57. Mr. Collins B.L., on behalf of the applicant, contends that the CPO lines were submitted
after the relevant date, particularly the information required under Article 3(2) of the
Directive, which refers to the material in Article 5(1) of the 2011 Directive. Having regard
to the fact that the quarry was omitted, an estimate of the type, quantity, expected
residues, emissions, water and soil pollution, noise vibration, resulting from the proposed
project were not submitted. The failure to characterise or describe at all the quarry
development permeates all of the assessments. That the land use requirements only
become apparent when the lands are identified, the CPO compiled and submitted for
approval. The sequencing of the development should be to identify the lands in the first
instance and to then conduct an EIS. Thus, the applicant maintains that the Council has
reversed the sequencing solely for the purposes of circumventing or avoiding the deadline
of the 15th May, 2017.
58. There is no description of the effects of the development on the environment through the
extraction of such materials, nor is there any consideration of the use of natural
resources. All of this information is required under Annex IV, however, it was not
provided before the 15th May, 2018, and still has not been provided.
Page 20 ⇓
59. The application for scheme approval pursuant to s. 49 of the Act was not received until
the 2nd June, 2017, was incomplete, and was supplemented by plans and particulars
received on the 22nd June, 2017. It is submitted that this information was received after
the 15th May, 2017, the date the 2014 Directive came into force. Re-advertisement of the
application was required. This publication occurred after the 15th May, 2017.
60. Counsel places particular emphasis on what is described as the inevitable increased
activity on site including blasting, crushing, screening, traffic movements etc. all of which,
it is feared, will have additional significant impacts on the environment and that such
increased activity has neither been assessed nor is it in accordance with the permission
granted. In the quarry EIS it was stated that, in relation to noise that “predicted that
operations at Raffeen quarry will continue at approximately the existing extraction rate
depending on market demand locally. There will be no increase in the amount of
extraction equipment/plant on site.”
61. The notice party maintains that the motorway/CPO scheme did not constitute an
application for development consent so as to engage the provisions of the EIA Directive.
Following its submission, the notice party became aware of a mapping error in one of the
drawings submitted as part of the application regarding identification of public and private
rights of way. The drawing failed to indicate the public and private rights of way to be
extinguished. This error was brought to the attention of the Board on the 22nd June,
2017. The submissions of the Board and the notice party are similar on this point. It is
submitted that confirmation of the CPO is not in any sense a consent to carry out
development on lands and therefore is not an application for development consent within
the meaning of Article 2 of the 2011 Directive. Further, the correspondence received by
the Board on the 22nd June, 2017 was provided solely in respect of a single mapping
error and did not amount to further information.
The Board did not invoke the provisions of s. 51(4) of the Act of 1993 requiring the
furnishing of additional information. But, even if it had, this would not have had the effect
of triggering the requirements of the 2014 Directive.
62. The notice party contends that in accordance with the provisions of O. 84, r. 20(3) of the
Rules of the Superior Courts, an applicant is required to precisely state the grounds of
challenge and it is submitted that insofar as this aspect of the challenge is concerned,
there is no precision and that the application is vague.
63. In so far as any further information may have been sought or supplied after the
transposition date, the respondent contends that pursuant to Article 5(2) of the Directive
further information may be sought even after a scoping opinion has been provided, and
this does not remove the application from consideration pursuant to the provisions of the
2011 Directive.
64. The central thrust of the response of the respondents and notice party is that the
Directive is concerned with land use, rather than land take, which is the principal focus of
the CPO. In any event, the application had been initiated before the 2014 Directive
Page 21 ⇓
became operational and therefore the 2011 Directive therefore applies. There was in fact
no request for further information made by the Board.
65. The applicant also contends that the road and the quarry should be, and should have
been, assessed as part of a single project. Counsel refers to the definition of project in
Article 1(2)(a) of the Directive which includes the execution of construction works or of
other installations or schemes and other interventions in the natural surroundings and
landscape, including those involving the extraction of mineral resources and say that all of
the activities that have been carried out fall within that definition. The obligation arises
from Commission v. Ireland (Case C-50/09), linked to the precautionary principle, that
the assessment must be as high as possible in environmental protection. In this regard,
the road goes across the quarry. The quarry is of significant ecological importance. The
impact of the development are not properly assessed. The assessment is narrow, confined
to the area underneath the road in certain locations and is oblivious to the large-scale
extraction works that are going to be carried out in the quarry. Mitigation measures in
relation to issues such as the peregrine falcon appear to presume that the quarry will
remain in its current condition. Far from a complete assessment, there is an absence of
an assessment. On the Board’s own admission, it does not look beyond the planning
permission which the quarry has. It operates on the basis that the quarry may operate in
accordance with its permission completely independently of the road and there will be no
changed impact on the quarry permission as a result. Instead of contemplating the
interactions that will occur in the site as required by European law, fictitious scenarios
which can never occur have been in contemplation. This includes that the road is going to
be idle in its construction at certain times every year. The manner of the construction,
through the winning of materials from the quarry, requires to be assessed. Further,
alternatively, the quarry planning permission will not be capable of being complied with in
terms of restoration. Mr. Collins B.L. suggests that the notice party takes a different view
as to what the quarry permission means because if the arguments before the court made
by the respondent are successful, the notice party will still not be able to give effect to
the development because they rely on a pre-existing permission as authorising the
necessary extraction works. They will have to persuade the owners of the quarry to make
a new application. No appropriate assessment was conducted. The test is whether the
Board is satisfied that there will not be a significant effect on the integrity of the site.
Permissions granted under the old regime have questions attached to them. The s. 261A
procedures is also questionable.
66. It is contended by the respondent that the applicant does not seek to impugn the earlier
decision. While it criticises the 2012 assessment, it doesn’t challenge it. Section 261A
concerns past works. The s. 261A scoping exercise is informative but is just a screening
exercise. It does not grant anything to the quarry. The s. 261A determination is not
concerned with the validity of the permission, rather with whether as a matter of law an
appropriate assessment ought to have been carried out.
67. The respondent argues that there is no obligation on the Board to be certain that the
development can be carried out in accordance with the plans and particulars lodged
Page 22 ⇓
before approval can be granted. The fact that planning permission cannot be implemented
does not necessarily invalidate the permission. Planning permissions are frequently
granted on the basis of the intentions of a developer, such as for example to obtain
consents of third parties. If the third-party consent is not forthcoming, that does not
mean that the planning permission is invalid. While the Board does not accept the
applicant’s interpretation of the planning permission attaching to the quarry, it is
submitted that even if that interpretation is correct, it will not have the effect of
invalidating the road approval.
68. The respondent also maintains that it was entitled to act on the basis of the validity of the
quarry planning permission and it cannot be assumed that the quarry operator will breach
the permission and thereby act illegally. Counsel also submits that on a proper
interpretation of the planning permission, while there are undoubtedly conditions attached
to the permission, none of them impose the restriction contended for by the applicant
being 100,000 tonnes per annum. Further, insofar as the timespan is concerned, it is
submitted that a proper analysis of the inspector’s report shows that it speaks of phase 1
being between 1 and 36 years. Insofar as the restorative works are concerned, that
condition effectively speaks to the full excavation of the quarry in all of the five originally
planned phases. While the respondent accepts that an intensification of use may
constitute a material change of use, it is not accepted that there must necessarily be a
breach of planning permission which is interpreted by the applicant as imposing absolute
limits which it does not in fact impose.
69. It is also submitted that the quarry and the road are legally separate projects, operated
or proposed to be operated by separate developers. There is not one single developer,
one single site for a phased development as may occur in the case of suggested project
splitting. That there may be a linkage between two projects does not mean that they
become one project which must be assessed as one. This is not a case of project splitting.
The obligation is to look at the interaction between projects in the context of the
cumulative assessment, rather than making all such projects part of the single project.
With linear developments such as a roadway, linkages with other developments are likely.
In this case, the EIS identified a range of projects for the purposes of the cumulative
assessment.
70. It is never been the position of the Board that because the quarry had a previous planning
permission that the Board did not have to concern itself with the quarry. The Board had
before it the nature of the established quarry use, the terms of its planning permission
and the information submitted for the quarry planning permission. It was therefore in a
position to assess the effects of quarrying cumulatively with the road effects. Nothing
which the Board has done in approving the road scheme or project served to vary the rate
at which the quarry owner was permitted to quarry. The Board acknowledged that the
quarry would be affected by the road development and the potential for cumulative
effects was addressed in the EIS and also in the Board’s assessment. This was assessed
under various headings. Proposed mitigation measures were addressed. Dust and noise
were assessed. The quarry was assessed as becoming a source of noise if it is used to
Page 23 ⇓
provide material for the road. Potential impacts of quarrying during construction are
addressed. Terrestrial ecology was addressed as were issues concerning flora and fauna
and the ecology within the quarry is considered in detail in chapter 12. The EIS addressed
the question of the potential for indirect cumulative impacts to sensitive receptors, in the
event that aggregate materials are extracted from the quarry to facilitate the road.
71. Regarding flora and fauna, it is submitted that the applicant fails to acknowledge that the
quarry permission itself acknowledges the potential presence of the peregrine falcon and
allows for the imposition of restrictions if quarrying activities disturb its breeding. The
underlying expert evidence is that while the road presented a problem for various
reasons, the active quarrying itself is not necessarily counter indicative to peregrine
nesting. Not only is the quarry not a designated site, but the falcon is not a qualifying
interest for any of the adjacent designated sites. Human effects are dealt with topic by
topic as they arise, particularly in chapter 18 of the EIS.
72. The notice party argues that an AA was in fact carried out in respect of the road project,
following a stage 1 screening process, and that in completing the assessment the Board
considered the likely direct and indirect impacts arising from the proposed road
development both individually and in combination with other plans or projects. It is
further submitted that the in-combination effects were considered in the NIS which
indicated that the quarrying operations would not contribute to cumulative or in
combination impacts to the Cork Harbour SPA. This is not challenged. The notice party
has never denied that the Glounatouig stream is hydrologically linked to the Cork Harbour
SPA, it has advanced very definite conclusions that the quarrying operations will not
impact on that site. It is submitted that the applicant advances no contrary evidence but
makes a bald assertion that extraction will have significant impacts on the environment.
Reliance is placed on the decision of Barrett J. in Friends of the Irish Environment v.
Fingal County Council [2017] IEHC 695, in this regard. The applicant goes no further than
to raise the fact of the hydrological link between the Raffeen Quarry and the Cork SPA but
advances no evidence of any likely effects on the SPA or on any qualifying interests.
73. The notice party also strongly argues that none of the issues in respect of the AA, which
are pleaded in the amended statement of grounds, were ever raised by the applicant at
the oral hearing. The quarry operations were the subject of screening for AA in 2012 and
it was concluded that there were no likely significant effects on the Cork Harbour SPA
from the operation of the quarry. The applicant is engaged in an impermissible collateral
attack on the quarry permission and/or on the 2012 screening assessment.
74. Counsel for the notice party relies on the decision of Finlay Geoghegan J. in Friends of
the Curragh Environment Limited v. An Bord Pleanala [2006] IEHC 390 in which it is
submitted the court categorically interpreted the Directive as requiring an EIA to be
carried out only in respect of the development which was the subject matter of the
application. There is a marked distinction between that case and this, because there it
was all one project and here there are two discrete projects. Thus, even if the court is
Page 24 ⇓
persuaded that there is in reality a larger project present here, then the decision in
Curragh provides a complete answer.
75. The notice party also submits that the Board had before it adequate material to justify its
conclusions on the EIA for the proposed road development, including those concerning
cumulative impacts and that it is not appropriate for the court to be asked to substitute
its own view for those of the Board, an expert body.
The Role of the Court
76. This is an application for judicial review and it is important to recall the role of this court
on such application. In so far as alleged inadequacies in the EIS and AA are concerned,
the notice party argues that it is a matter for the first respondent to consider the
adequacy of the information included in an EIS. This may, however, be subject to a
review in accordance with the principles set out in O’Keeffe v. An Bord Pleanála [1993] 1
I.R. 39. In People Over Wind v. An Bord Pleanála [2015] IEHC 271, Haughton J. stated at
para. 98:-
“It has been consistently held in the courts that it is for the deciding authority to
determine whether the EIS and the information contained therein satisfies the
requirements of the Regulations and is adequate.”
He re-emphasised that the standard of review applicable to the Board’s decision in that
regard was that set out in O’Keeffe at para. 101:-
“The Court can not interfere with the decision of an administrative decision-making
authority merely on the grounds that (a) it is satisfied that on the facts as found it
would have raised different inferences and conclusions, or (b) it is satisfied that the
case against the decision made by the authority was much stronger than the case
for it.”
77. In order to show that the Board has acted irrationally, it is necessary for the applicant to
establish that the Board “had before it no relevant material which would support its
decision”. Thus, the court’s jurisdiction to intervene is not unlimited.
Failure to particularise the grounds of challenge
78. With regard to the objection of the notice party that the applicant has failed to properly
particularise its grounds of challenge as required by O. 84, r. 20(3) of the Rules of the
Superior Courts. At para. 6 of the statement of grounds it is pleaded that the application
for approval pursuant to s. 51 was premature, incomplete and did not properly describe
the proposed development. It is further pleaded at para. 7 that the respondent continued
to consider the application which was incomplete and notwithstanding that the scheme
approval sought under s. 49 of the Act was not received until 2nd June, 2017. It is
pleaded that in turn even this application was incomplete and was supplemented by
further plans and particulars on 22nd June, 2017. This information was received after
15th May, 2017 and re-publication and re-advertising occurred after that date.
Page 25 ⇓
79. Having considered the pleadings and the submissions of the parties, I am satisfied that
the claim made by the applicant with regard to the question of the Directive applicable,
has been sufficiently particularised as not to fall foul of the provisions of O. 84.
The approach of the Court to the determination of the issues
80. To some extent the arguments of the applicant on the adequacy of the EIS and AA
overlap with the contention that a completed application was not submitted prior to the
15th May, 2017. Nevertheless, it seems to me that as a first step it is appropriate to
consider the issue of which iteration of the Directive is applicable (“the Directive issue”).
If the applicant is correct in its contention that the 2014 Directive applies, then it is clear
that the provisions of that Directive have not been adhered to and a fresh application will
have to be made. The 2011 Directive required the submission of an EIS, whereas the
2014 Directive envisages a procedure whereby an EIA report be submitted. Save to the
extent considered below, a determination on this issue in favour of the applicant would
render it unnecessary to proceed to consider issues relating to the adequacy of the
assessment which was carried out, and in particular with reference to issues concerning
the “quarry”. On the other hand, if the 2011 Directive is applicable then those issue will
require consideration as will the issue of the locus standi of the applicant to make certain
arguments regarding the project and the quarry.
The Directive Issue
81. The inspector addressed this issue in her report. She noted that while the 2014 Directive
came into force on 15th May, 2014, with a requirement to be transposed into national
legislation by 16th May, 2017, this had not been done. The Department of Housing,
Planning, Community and Local Government issued a circular dealing with transitional
arrangements and which stated that where an application for planning permission or
other development consent with an EIS had been submitted before 16th May, 2017, the
relevant provisions of the 2011 Directive must be applied.
82. The inspector noted that the observations and objections raised by the applicant’s legal
advisers at the oral hearing were that the Act of 1993 required that the scheme approval
under s. 49 be sought together with the road development proposal consent; that they
both should travel in tandem and that there was no basis in law for the practice of
“putting the s. 51 cart before the s. 49 horse.” It was argued that the scheme approval is
a pre-requisite to showing that the Authority will have the legal right to carry out the
development. Therefore the two applications should be considered, assessed and decided
upon as a unitary project. This would mean that the application ought to be governed by
the law in force when the latest of the papers relating to the s. 49 matter were lodged.
Her conclusion on this issue is outlined at p. 61 of the report:-
“I note that s. 49 of the Roads Act 1993 (as amended) requires the submission by
the roads authority of the scheme made by it under section 47…; S. 50 requires the
preparation of an EIS and specifies the contents of the EIS; and s.51 requires the
road authority to apply for approval and to submit the EIS to the Board, and states
that the proposed development shall not be carried out unless it has been
approved. S.51(7) (b) requires that where an application under s. 51 and a scheme
Page 26 ⇓
for approval under s.49 relate wholly or partly to the same road development, a
decision must be made on the two applications at the same time. However, I can
find no reference to any provisions in the Roads Act, 1993 (as amended) to a
requirement for the sequencing of the lodgement of the applications. As the
application for the proposed road development was submitted to the Board,
together with an EIS for the proposed development, on 15 May 2017, it is
considered that the relevant provisions of Directive 2011/92/EU apply, as set out in
Circular PL 1/2017.” (emphasis supplied)
83. Ms. Kennelly also dealt with the submission made by the applicant that even if the s. 51
application was properly before the Board, it could not benefit from the transitional
arrangements because the EIS submitted on 15th May, 2017 as it did not meet the
mandatory requirements of Article 5(1), (3) and Annex IV of the 2011 Directive. It also
had been argued that nothing could be added to the EIS after that date for the purposes
of the audit by the Board. As the scheme plans were not before the Board for 2nd June,
2017 and because of other inadequacies in the EIS, it had been submitted that the
information required by Article 5 had not been provided before 16th May, 2017 and
therefore the 2014 Directive applied. Having considered the Departmental guidelines on
EIA’s issued in 2013, she commented that the EIS is part of the EIA process, which must
be carried out by the Competent Authority and which includes consideration of
submissions by the public, prescribed bodies and the applicant. On this, she observed at
p. 63:-
“It is considered that the submission of the EIS is the starting point and that the
information gathered in written submissions and at the oral hearing form part of
the EIA process which will ultimately inform the Board decision. It is considered,
therefore, that the relevant provisions applicable to the proposed development
before the Board are contained in EU 2011 Directive/92/EU, as the application for
the proposed development, together with an EIS, was submitted before 16th May
2017, and as such it falls within ‘Applications on hand on or before 15th May 2017.”
84. Although a legal matter, she was therefore satisfied that the application was submitted
prior to the 16th May 2017, the date for transposition of the 2014 Directive and therefore
the 2011 Directive applied.
85. Article 3 of the 2014 Directive provides as follows:-
“1. Projects in respect of which the determination referred to in Article 4(2) of Directive
2011/92/EU was initiated before 16 May 2017 shall be subject to the obligations
referred to in Article 4 of Directive 2011/92/EU prior to its amendment by this
Directive.
2. Projects shall be subject to the obligations referred to in Article 3 and Articles 5 to
11 of Directive 2011/92/EU prior to its amendment by this Directive where, before
16 May 2017:
Page 27 ⇓
(a) the procedure regarding the opinion referred to in Article 5(2) of Directive
2011/92/EU was initiated; or (b) the information referred to in Article 5(1) of
Directive 2011/92/EU was provided.” (emphasis added)
86. Also of relevance is recital 39 of the 2014 Directive, regarding legal certainty:-
“In accordance with the principles of legal certainty and proportionality and in order
to ensure that the transition from the existing regime, laid down in Directive
2011/92/EU, to the new regime that will result from the amendments contained in
this Directive is as smooth as possible, it is appropriate to lay down transitional
measures. Those measures should ensure that the regulatory environment in
relation to an environmental impact assessment is not altered, with regard to a
particular developer, where any procedural steps have already been initiated under
the existing regime and a development consent or another binding decision
required in order to comply with the aims of this Directive has not yet been granted
to the project. Accordingly, the related provisions of Directive 2011/92/EU prior to
its amendment by this Directive should apply to projects for which the screening
procedure has been initiated, the scoping procedure has been initiated, (where
scoping was requested by the developer or required by the competent authority) or
the environmental impact assessment report is submitted before the time-limit for
transposition.”
87. The statutory regime envisages two applications. One arises under s. 49 in respect of the
approval of the scheme and the second under s. 51 in respect of the consent to the
carrying out of the development. By virtue of the provisions of s. 47(2), a scheme must
be in the prescribed form and specify certain matters including the land and any rights
which it is proposed to compulsorily acquire, or any rights which it is proposed to
extinguish. The scheme must also specify any planning permissions intended to be
revoked or modified. It also provides at s. 47(2)(b) that the above matters shall, where
appropriate, be described by reference to a map or maps. The section also specifies that
the lands referred to which are the subject of the acquisition shall include land and rights
in respect of land necessary for, or incidental to, the construction or maintenance of the
scheme. Therefore, it is necessary that the lands in question be specified by reference to
a map or maps.
88. By virtue of the provisions of s. 48, the Authority is obliged to take certain steps before
submitting the scheme to the Board for its approval under s. 49, including necessary
advertisements and publications and the service on every owner or occupier of any land
referred to in the scheme of s. 47 and persons who are affected by proposed revocation
or modifications of planning permissions. There is no suggestion in this case, that the
mis-description and subsequent re-correction on one map affected any particular
landowner or that he/she objected thereto on that ground. It is of note that no particular
timeframe is provided in s. 47, which is not surprising as it is an empowering section, as
to when it is necessary to apply for approval of the scheme under s. 49. Section 48
Page 28 ⇓
provides, however, that certain necessary steps must be taken before the scheme is
submitted to the Board under s. 49.
89. I can find nothing in ss. 47 to 49 which make reference to particular time limits, or the
order in which the applications for approval of the scheme and the consent to the carrying
out of the works or development, ought to be made. Section 51 prohibits the carrying out
of a proposed road development unless the Board has approved it or approved it with
modifications. Section 51(2) imposes an obligation on the Authority to apply to the Board
for approval and to submit an EIA prepared in respect of the development. It is therefore
clear that whatever about the submission of a scheme for approval, that scheme cannot
be carried out without obtaining the necessary consent from the Board and that the
application for such consent will be invalid unless it is accompanied by an EIS. However,
the Act makes provision for the timing of the decision in respect of both applications and
it is clear from the provisions of s. 51(7) that a contemporaneous decision must be made
in respect of the approval of the scheme and the approval concerning the carrying out of
the works proposed by that scheme. Section 51(7)(b) provides:-
“(b) Where an application for approval under this section relates to a proposed road
development, and
(i)
a scheme submitted to the Minister for approval under section 49…
…relate wholly or partly to the same proposed road development, the Minister shall
make a decision on such approval and on the approval of such scheme or the
making of such bridge order or the confirmation of such compulsory purchase order
at the same time.” (emphasis added)
90. That this is specifically provided for in respect of the timing of the decision, leads one to
conclude that had it been intended that the applications be made at the same time, the
Act would have so provided. This is the conclusion which, although not expressed as a
legal opinion, was arrived at by the inspector and I see little reason to differ from her
view in this regard.
91. I also believe that there is merit in counsel for the respondent’s submission that the
application under s. 49 addresses land take rather than land use, and is more concerned
with and focuses on land ownership, rights of way, extinguishment of rights etc. The
procedure under s. 49 concerns the acquisition, or extinguishment, of legal title to the
land over which the road is going to be built.
92. Section 49 of the Act does not make express reference to the requirement that an
application under that section be accompanied by an EIS or AA. It seems to me that if
that had been the intention of the Oireachtas, it would have so provided. This fortifies the
view that an application under s. 49 is concerned with land take, rather than land use. It
seems likely that it is the use to which land is to be put that attracts the requirements of
the Directive and the necessity for an EIS and, potentially, an AA.
Page 29 ⇓
93. Turning specifically to the issue in this case, the public rights of way and the private rights
of way proposed to be extinguished were identified in schedule three of the scheme. The
road development application was made on the 15th May, 2017 and was accompanied by
the EIS and NIS. The scheme /CPO application was made on the 2nd June, 2017 and
shortly thereafter it became clear that there was an error in a deposit map drawing
submitted as part of the CPO /scheme. This deposit map drawing (No. M28/MO/02) did
not properly identify all the public and private rights of way proposed to be extinguished.
However, having considered the scheme as submitted, particularly the contents of
schedule 3, parts 1 and 2, I see nothing to suggest that the rights of way were not
described appropriately in narrative form. I am satisfied, therefore, that the information
was provided in narrative form but was not fully mapped. The error in question had
nothing to do with the use to which the land is to be put, rather it was concerned with
the mapping of the rights to be extinguished, both public and private. Further, and in any
event, necessary corrections were made before the decision was taken in respect of the
applications.
94. In all the circumstances, I have come to the conclusion that the Board was correct when
it considered the application under s. 51 in the context with the requirements of the 2011
Directive. Further, in my view the transition provisions of the 2014 Directive and in
particular the principles of legal certainty enshrined in recital 39 thereof, supports the
conclusion of the Board in this regard. Thus, in the event that the EIS and the AA as
submitted are in accordance with the requirements of the 2011 Directive, the transition
provisions of the 2014 Directive apply. Such assessments as are relied on were completed
before the transposition date and it is difficult to envisage circumstances in which it could
be said that the process had not been at least initiated in accordance with the provisions
of the Directive.
95. I believe this to be consistent with decision of the ECJ in Commission v. Germany (Case
C-431/92) where the Court observed at para. 32:-
“Informal contacts and meetings between the competent authority and the
developer, even relating to the content and proposal to lodge an application for
consent for a project, cannot be treated for the purposes of applying the directive
as a definite indication of the date on which the procedure was initiated. The date
when the application for consent was formally lodged thus constitutes the sole
criterion which may be used. Such a criterion accords with the principle of legal
certainty and is designed to safeguard the effectiveness of the directive.”
96. In view of the Court’s conclusions on this issue, it is therefore necessary to address the
further points raised by the Applicant , with particular regard to the proposed rate of
extraction and that the road and the quarry ought to have been considered as one
project. Before doing so it is necessary to consider the locus standi of the applicants to
raise such grounds of challenge.
Page 30 ⇓
Locus Standi
97. The respondent and the notice party object to the applicant raising issues before this
court which were not raised before the Board. These include objections to the locus standi
of the applicant to raise the arguments concerning the assessment of the quarry and the
road as one project, that the assessment of the in-combination effects did not take into
account what the applicant maintains will be an unlawful and impermissible use of the
quarry, and that the assessment exercise conducted in respect of the quarry in 2012 was
inadequate and not in accordance with what is required by the law as it has developed
since then. As I understand the submissions of the respondent and the notice party, it is
not a question of whether the court should, in the exercise of his discretion, refuse to
grant the relief sought, rather it is whether the applicant has standing to make the case
in the first instance.
98. It is fair to summarise the respondent and notice party’s positions as being that while the
applicant might enjoy general standing to mount a challenge to the Board’s decision, it
should not be permitted to raise an issue which was not raised before the Board, as to do
so would be fundamentally unfair. If the issue had been raised, the notice party maintains
that it would have had the opportunity to deal with it. The court is being requested to
adjudicate on a challenge without the decision maker having had the opportunity to
consider the matter. Thus an issue based locus standi argument arises.
99. Mr. Connolly S.C., counsel for the notice party, submits that while the court may have a
discretion to entertain points in relation to the AA or the rate of extraction, if some reason
had been given or some excusing factor advanced as to why those points were not
addressed, no such reasons or excuse have been advanced in this case. He relies on
Casey v. An Bord Pleanala [2004] 2 I.L.R.M. 296, where Murphy J. expressed the view
that by raising a point before the Board, an applicant allows for the possibility of the
Board to consider the points and if appropriate to provide immediate relief. He submits
that the decision of the Supreme Court in Grace and Sweetman v. An Bord Pleanala
[2017] IESC 10, discussed below, does not detract from the proposition which emerges
from the earlier decisions of Lancefort v. An Bord Pleanala [1998] 2 IR 511 and Casey
that the failure advance an adequate excuse should constitute a basis for barring him or
her from challenging an administrative decision on that ground. The issue is not so much
whether such persons are affected, but that they should not now be heard on the points
that could or should have been raised in the course of the oral hearing.
100. The applicant maintains that the rules in relation to locus standi must be viewed in the
light of Grace and Sweetman, where applicants who had not participated in the process
under review were found to have locus standi to maintain a challenge to the Board’s
decision. Therefore, if such an applicant has locus standi in court proceedings, how can a
person who has previously participated not enjoy standing to make a particular point that
may not have been raised before the Board? It is submitted that the applicant’s status as
an NGO strengthens its position. But, the question arises, is the position different if a
prior participant, including an NGO, fails to raise a particular point?
Page 31 ⇓
101. Article 11 of 2011 Directive on the assessment of the effects of certain public and private
projects on the environment provides:-
“1. Member States shall ensure that, in accordance with the relevant national legal
system, members of the public concerned:
(a) having a sufficient interest, or alternatively;
(b) maintaining the impairment of a right, where administrative procedural law
of a Member State requires this as a precondition;
have access to a review procedure before a court of law or another
independent and impartial body established by law to challenge the
substantive or procedural legality of decisions, acts or omissions subject to
the public participation provisions of this Directive.
2. Member States shall determine at what stage the decisions, acts or omissions may
be challenged.
3. What constitutes a sufficient interest and impairment of a right shall be determined
by the Member States, consistently with the objective of giving the public
concerned wide access to justice. To that end, the interest of any non-
governmental organisation meeting the requirements referred to in Article 1(2)
shall be deemed sufficient for the purpose of point (a) of paragraph 1 of this Article.
Such organisations shall also be deemed to have rights capable of being impaired
for the purpose of point (b) of paragraph 1 of this Article.
4. The provisions of this Article shall not exclude the possibility of a preliminary
review procedure before an administrative authority and shall not affect the
requirement of exhaustion of administrative review procedures prior to recourse to
judicial review procedures, where such a requirement exists under national law.
Any such procedure shall be fair, equitable, timely and not prohibitively expensive.
5. In order to further the effectiveness of the provisions of this Article, Member States
shall ensure that practical information is made available to the public on access to
administrative and judicial review procedures.”
102. In Grace and Sweetman, in their joint judgment Clarke J. (as he then was) and O’Malley
J., in considering the provisions of Article 11, held that the starting point of any analysis
is to determine what national law says about standing. Noting the wording of Article 11,
the court stated that there was no reason in principle why the language of Irish
environmental judicial review standing law has to use the term “sufficient interest” for it
to be compatible with EU law. It is open to the Oireachtas to provide for any standing
rules considered appropriate provided that those rules, in whatever terms they are
defined, meet the broad access to justice requirement. For this reason, the court
observed that it was important in analysing case law on standing in environmental cases
Page 32 ⇓
to pay particular regard to whether the decision in question was given at a time during
which the substantial interest test existed. Standing rules in environmental cases were
subject to specific statutory intervention initially in the form of s. 50(4) of the Act of
2000, but that had now to be considered in the light of the provisions of s. 13 of the
Planning and Development (Strategic Infrastructure) Act 2006, which removed the
requirement imposed by s. 50(4) of the earlier legislation. The court observed at para.
6.4:-
“…Thus the earlier of those measures introduced, with effect from 2000, a
requirement of prior participation but the latter reverted the law to the previous
position that a failure to participate does not operate necessarily in all
circumstances as a barrier to standing. Indeed, some of the case law which
predated those legislative changes suggests that the traditional position was one
where a failure to participate did not necessarily, and in all circumstances, prevent
a relevant person from having standing.”
103. The court also observed that certain judicial interpretations of Lancefort might suggest a
view that prior participation or an appropriate explanation for non-participation was a
prerequisite for standing, but continued:-
“… it is arguable that Lancefort does not stand as authority for a general principle
that prior participation is in all cases a prerequisite to standing. Lancefort certainly
does suggest that it may, however, be a factor. But even if Lancefort might have
been regarded as authority for the wider proposition it must, of course, now be
read in the light of the introduction, in 2000, of an express statutory requirement
for prior participation followed by the express repeal of that provision in 2006. On
that basis it can no longer be held that Lancefort provides authority for any general
preclusion of standing in the absence of prior participation or an appropriate
explanation for the lack of it.”
104. In the opinion of the Supreme Court, a reasonably liberal approach ought to be taken to
the sort of interest which must be potentially affected in order to confer standing in
environmental cases. Thus, persons can have an interest by virtue of proximity to the
proposed development. The court also considered the extent of the effect of the project
on the individual in question, the nature and general importance of the site sought to be
protected and that:-
“… developments which have the potential to have a material and significant effect
on the environment generally or raise questions of particular national or
international importance (such as the national monument involved in Mulcreevy)
may confer standing on a much wider range of persons.”
105. The court continued at 6.11:-
“On the current state of the jurisprudence in Ireland and without, for the moment,
having regard to the requirements of European law it seems that standing in
Page 33 ⇓
environmental cases involves a broad assessment of whether the legitimate and
established amenity or other interests of the challenger can be said to be subject to
potential interference or prejudice having regard to the scale and nature of the
proposed development and the proximity or contact of the challenger to or with the
area potentially impacted by the development in question…”
Later, in considering the European dimension, the court was satisfied that as national
standing rules must be consistent with broad access to justice, it follows that in
interpreting national standing rules, the court of a member state is required to ensure
that those rules meet the “wide access to justice” standard. Given that Irish standing
rules were expressed in broad terms capable of appropriate interpretation, it did not seem
to the court that any question of disapplication arose. Nevertheless, it remains necessary
for the court in interpreting the “sufficient interest” requirement for standing contained in
national law, to ensure that the interpretation conforms with the requirements of Article
11. The court continued:-
“…Second, it is potentially of some relevance to note the provisions of European law
concerning the standing of environmental non-governmental organisations (NGOs)
and the measures adopted in Ireland to ensure compliance with those provisions.”
106. The distinction between NGOs and individuals was called in aid by both parties in Grace
and Sweetman to support their respective positions. Thus, it was argued that the very
fact that environmental NGO’s have an almost unlimited access to environmental litigation
removed the necessity for invoking a Cahill v. Sutton [1980] I.R. 269 type exception in
environmental cases.
107. The principles relating to standing have evolved through national and European
legislation; and as they have been judicially interpreted. This much is clear from Grace
and Sweetman. There are, however, differences in the factual circumstances of this
challenge and those which pertained in Grace and Sweetman. The court was not there
concerned with an NGO which, it seems to me, if anything strengthens the applicant’s
position in this case. The court was not required to directly concern itself with
circumstances in which a party participated in the process before the Board but had not
made a particular point which it now seeks to raise on a judicial review application. Ms.
Grace was not a prior participant. Counsel for the applicant questions how a person who
has not participated in a planning inquiry can be in a better position vis a vis standing,
than someone who has not advanced a particular claim before the Board but has
otherwise participated.
108. Supporting dicta in favour of the respondent and notice party’s contention, however, is to
be found in the decision of Barrett J. in An Taisce v. An Bord Pleanala and Others
[2018] IEHC 640. When considering an application for leave to appeal, he observed:-
“POINT 4. ‘Was An Taisce precluded from challenging the Board's decision to accept
the adequacy of the rEIS if it had not made any comment on the issue in the course
of the planning process?’ Under Irish law, one cannot typically raise in a judicial
Page 34 ⇓
review application a matter not previously put to the relevant decision-maker. The
European Union law doctrines of equivalence/effectiveness do not vary this position
here. Case C-263/08 Djurgården-Lilla is not authority for free-wheeling competence
on the part of judicial review applicants to raise points not raised before the
decision-maker. Case C-664/15 Project Natur- (see paras.[88]-[89]) expressly
anticipates timing requirements as regards making objections. If there was an Irish
rule that rendered European Union law less effective than national law that would
cause difficulty; nothing of the like presents.”
109. Although it seems to me that the court is in a position to address the standing issue by
reference to national law as discussed in Grace and Sweetman, nevertheless, in the light
of the arguments made before the court, it is also instructive to consider the position
under European law.
110. In Djurgarden-Lilla Vartens Miljoskyddsforening v. Stockholms Kommun Genom Dess
Marknamnd (Case C-263/08) issues arose as to the scope of the right of appeal provided
by the Aarhus Convention and whether the conditions laid down by Swedish law were too
restrictive. A question which the court was required to address was whether Member
States, in implementing Article 6(4) and 10a of Directive 85/337, may provide that small,
locally established environmental protection associations have a right to participate in the
decision making procedures referred to in Article 2(2) of the Directive 85/337, but no
right of access to a review procedure to challenge the decision adopted at the end of that
procedure. There, national legislation dictated that only an association with at least 2,000
members may bring an appeal against the decision of adopted on an environmental
matter.
111. The Court of Justice reiterated that the national rules must ensure:-
“‘wide access to justice’ and, second, render effective the provisions of Directive
85/337 on judicial remedies. Accordingly, those national rules must not be liable to
nullify Community provisions which provide that parties who have a sufficient
interest to challenge a project and those whose rights it impairs, which include
environmental protection associations, are to be entitled to bring actions before the
competent courts.”
The court observed that while it is conceivable that the condition that an environmental
protection association must have a minimum number of members may be relevant in
order to ensure that it does in fact exist and that it is active, the number of members
required could not be fixed by national law at such a level that it runs counter to the
objectives of the Directive and in particular the objective of facilitating judicial review of
projects which fall within its scope. Although the Directive 85/337 provided that members
of the public concerned who had a sufficient interest in challenging projects or who had
rights which may be impaired by such projects, are to have the right to challenge the
decision which authorises it, the Directive in no way permits access to review procedures
to be limited on the ground that the persons concerned had already been able to express
their views in the participatory phase of the decision making procedure established by
Page 35 ⇓
Article 6(4) of the Directive. Thus, national rules which offered extensive opportunities to
participate at an early stage in the procedure in drawing up the decision relating to the
project, do not justify the fact that judicial remedies against the decision adopted at the
end of that procedure are available only under very restrictive conditions.
112. The court therefore held that provisions of Article 10a of Directive 85/337 precluded a
provision of national law which reserves the right to bring an appeal against a decision on
projects which fall within the scope of the Directive, solely to environmental protection
associations which have at least 2,000 members. It seems to me that this decision is
authority for the proposition that a party which has participated in the planning process
cannot be excluded from the right to seek to review that process before the courts. Mr.
Collins B.L. places particular emphasis on the contents of para. 39 of the decision where
he stated that:-
“Accordingly, the answer to the second question is that the members of the public
concerned, within the meaning of Article 1(2) and 10a of Directive 85/337, must be
able to have access to a review procedure to challenge the decision by which a
body attached to a court of law of a member state has given a ruling on a request
for development consent, regardless of the role they might have played in the
examination of that request by taking part in the procedure before that body and
by expressing their views.” (emphasis added)
113. In Project Natua-, Arten- und Landschaftsschutz Umweltorganisation v.
Bezirkshauptmannschaft Gmünd (Case C-664/15), the ECJ considered certain provisions
of the Aarhus Convention. The court stated that effective judicial mechanisms should be
accessible to the public, including organisations, so that its legitimate interests are
protected and the law is enforced. The question which the court had to consider was
whether Articles 9(3) and (4) of the Aarhus Convention must be interpreted as precluding
a rule of national procedural law that imposes a time limit on an environmental
organisation, pursuant to which a person loses the status of party to the procedure and
therefore cannot bring an action against the decision resulting from the procedure, if it
has failed to submit objections in good time following the opening of the administrative
procedure or, at the very latest, during the oral phase of that procedure. The court
accepted that in principle, member states may, in the context of the discretion they have,
establish procedural rules setting out conditions that must be satisfied in order to be able
to pursue such review procedures, provided they also ensure compliance with the right to
an effective remedy and to a fair hearing.
114. Importantly, at para. 88 of the court’s decision, it is stated:-
“88 In principle, Article 9(3) of the Aarhus Convention does not preclude a rule
imposing a time limit, such as the one set out in Paragraph 42 of the AVG, obliging
the effective exercise, from the administrative procedure stage, of the right of a
party to the procedure to submit objections regarding compliance with the relevant
rules of environmental law, since such a rule may allow areas for dispute to be
Page 36 ⇓
identified as quickly as possible and, where possible, resolved during the
administrative procedure so that judicial proceedings are no longer necessary.
89 Thus, such a rule imposing a time limit may contribute to the objective of Article
9(3) of the Aarhus Convention, set out in the 18th recital of that Convention, of
providing effective judicial mechanisms and appears also to be in line with Article
9(4) of that Convention, which requires that the procedures referred to, inter alia,
in Article 9(3) of the convention provide ‘adequate and effective’ remedies that are
‘equitable’.”
115. The court held that the rule imposing a time limit may be justified, notwithstanding that
as a precondition for bringing judicial proceedings, it constitutes a limitation on the right
to an effective remedy before a court within the meaning of Article 47 of the Charter of
Fundamental Rights of the European Union. Such justification may arise:-
“in accordance with Article 52(1) of the Charter, to the extent that it is provided for
by law, it respects the essence of that law, it is necessary, subject to the principle
of proportionality, and it genuinely meets objectives of the public interest
recognised by the EU or the need to protect the rights and freedoms of others…”
The court concluded that Articles 9(3) and 9(4) of the Aarhus Convention, read in
conjunction with Article 47 of the Charter must be interpreted as precluding, in
circumstances pertaining in that case, the national procedure rule in question.
116. Counsel for the respondent submits it was never the intention of the Directive that
environmental decision-making should be shifted to the court. In Project Natur the court
addressed the issue of whether the provisions of the Directive prohibited national legal
requirements from excluding small environmental organisations from exercising a right of
bringing the matter before a Court. It was not being asked whether there exists a general
and unrestricted right for an NGO to come to court and make any argument that it wants.
It was being asked the more specific question as to whether the participation rights of the
public, including an NGO, can legitimately be treated by a Member State as exhausted, if
they had full access to the planning process. Article 11 expressly envisages that there will
be a right of access to a review procedure, but the case law also envisages that the right
of access to review procedure can be made subject to the laws of the Member State, but
not laws that effectively completely exclude that right.
117. In Commission v. Germany a complaint was made about a national law which restricted
standing to bring proceedings and the scope of the review by the courts to objections
made during the administrative procedure. That law placed a restriction on the pleas in
law which could be made by an applicant in a challenge to an administrative decision
falling within the scope of Article 11 of the 2011 Directive, and another Directive on
industrial emissions, to those which were previously made during the administrative
procedure. The court ruled as follows:-
Page 37 ⇓
“77 The Court has previously held that Article 11(1) of Directive 2011/92, pursuant to
which the decisions, acts or omissions covered by that Article must be subject to a
review procedure before a court of law or another independent and impartial body
established by law to challenge their substantive or procedural legality, lays down
no restriction whatsoever on the pleas which may be relied on in support of such a
review (see, to that effect, judgment in Bund für Umwelt und Naturschutz
Deutschland, Landesverband Nordrhein-Westfalen, C 115/09, EU:C:2011:289,
paragraph 37). That consideration meets the objective pursued by that provision of
ensuring broad access to justice in the area of environmental protection.
78 Paragraph 2(3) of the UmwRG and Paragraph 73(4) of the VwVfG lay down specific
conditions restricting the review by the courts which are not provided for in either
Article 11 of Directive 2011/92 or Article 25 of Directive 2010/75.
79 Such a restriction laid on the applicant as to the nature of the pleas in law which he
is permitted to raise before the court reviewing the legality of the administrative
decision which concerns him cannot be justified by considerations of compliance
with the principle of legal certainty. It is in no way established that a full review by
the courts of the merits of that decision would undermine that principle.
80 As regards the argument concerning the efficiency of administrative procedures,
although it is true that the fact of raising a plea in law for the first time in legal
proceedings may, in certain cases, hinder the smooth running of that procedure, it
is sufficient to recall that the very objective pursued by Article 11 of Directive
2011/92 and Article 25 of Directive 2010/75 is not only to ensure that the litigant
has the broadest possible access to review by the courts but also to ensure that
that review covers both the substantive and procedural legality of the contested
decision in its entirety.
81 None the less, the national legislature may lay down specific procedural rules, such
as the inadmissibility of an argument submitted abusively or in bad faith, which
constitute appropriate mechanisms for ensuring the efficiency of the legal
proceedings.”
118. In my view this reinforces the proposition that as a matter of law there is no general rule
that a prior participant who has not raised particular point before the Board is
automatically precluded from raising such points in a court of review. To adopt such a
stance might place a person who has not previously participated in a stronger position
than someone who has. On the other hand, in my view, neither do the authorities
establish an unrestricted right to raise new points. This is particularly so, as was
recognised in the Commission v. Germany, where there is evidence of bad faith or a
deliberate decision to withhold a point.
119. Clarke J. acknowledged in Grace and Sweetman that standing in environmental cases
involves a broad assessment of whether the legitimate and established amenity or other
interests of the challenger can be said to be subject to potential interference or prejudice
Page 38 ⇓
having regard to the scale and nature of the proposed development and the proximity or
contact of the challenger to or with the area potentially impacted by the development in
question. Although these comments were expressed in the context of general standing, as
opposed to an objection based on the failure to raise a particular issue, I believe that they
must have relevance to the issue raised in this case. While each case must be dependent
on its facts, bearing in mind the considerations alluded to in Grace and Sweetman, it
seems appropriate in determining the locus standi of the applicants in this case, to give
consideration to the nature of the illegality or infringement alleged, the consequences of a
decision either way, any explanation that is advanced for the failure to raise the issue,
and the overall obligations imposed as a matter of European law with regard to a
particular process and to the requirement for broad access to justice.
120. The nature of the alleged illegality is significant. If the applicant is correct, then the Board
has acted ultra vires and has failed to take due account of mandatory requirements in the
consideration of matters relating to environmental concern. The explanation advanced for
failing to raise this point at the earlier hearing, is that the applicant was unaware of the
planning history of the quarry, the lack of the AA or the screening process which had been
undertaken pursuant to s. 261A, matters which it had to establish for itself. It also pleads
that it was hampered by the fact that the planning file for the quarry was not available
electronically on the council’s website, and that a copy had to be obtained from storage.
Further, the s. 261A file was also not available electronically. It is stated by the applicant
that it had originally pleaded a ground based on the AA but this had been deleted in
advance of the filing of the original statement of grounds because the circumstances
surrounding the AA were still not known. What was described by counsel as the more
nuanced, evolved ground, was of a type that an individual or an NGO not versed
intimately with the machinations of European environmental law, might not raise at a
public hearing. In any event, it is maintained that it could never be said that the issue
was not raised with a view to trapping the respondent.
121. The notice party maintains that information concerning the application which resulted in
the 2008 planning permission regarding extraction activities at the quarry was available.
Mr. O’Shea states that the information was either known or capable of being accessed or
known to the applicant when it framed its objection and at the time of the oral hearing.
To seek details of the planning file for the quarry after the Board had made its decision,
he states, is no answer to the failure to raise all relevant issues before the Board. In any
event, Mr. O’Shea avers that the NIS addressed impacts arising from the quarry and
concluded that the quarrying operations would not contribute to cumulative or in
combination impacts to Cork Harbour SPA.
122. It seems to me that it is also particularly important for the court to be mindful that where
there has been a failure to raise a particular issue that might have been more fully
considered and assessed by the deciding authority, parties to the statutory procedure will
not have had the opportunity to deal with the objection on a substantive basis. This must
be considered in light of the role of the court on an application for judicial review. This
court is not concerned with the merits of the decision and care must be exercised in the
Page 39 ⇓
consideration of such “new” matters, lest the court is unwittingly led into an assessment
of the merits of a particular point, where the body which is statutorily charged with the
function of dealing with these matters, and recognised for its expertise in so doing, has
not had the opportunity to address it.
123. One must also have some sympathy with the contention of the respondent that a
question mark must arise over the explanation advanced by the applicant that it did not
know that the development was “proximate and linked with the Cork Habour SPA.” As
the respondent points out, the NIS expressly identifies Cork Harbour SPA as a European
site with the potential to be affected and it proceeded to examine the potential connection
to the Cork Harbour SPA, including the in-combination or cumulative effects of the road
development and the operation of the quarry. Although, the applicant might thus be
open to criticism for not addressing issues relating to the quarry permission in as much
detail before the Board as it has in this court, in the particular circumstances of this case,
with the above caveats in mind and consistent with the requirement of broad access to
justice, I am satisfied that I should entertain the arguments which have been advanced
by the applicants on these points and that they have locus standi to make them. In
arriving at this conclusion, I am somewhat guided by the fact that the “new” matters are
to an extent aligned with issues which were considered and addressed by the inspector in
her report at p. 235. When listing the issues raised by observers regarding flora and
fauna, she noted that one such issue was that the EIS was inadequate in terms of
cumulative impacts. The stated reason for this concern that the EIS was inadequate was
because “there would be a phenomenal increase in the rate of extraction of stone from
the quarry from 30 years (as granted under the planning permission) to 3 years, required
for the road project”, and that this had not been assessed. Another matter which is
referred to in her report at p. 236 as being one of the issues raised by the Department of
Arts, Heritage and the Gaeltacht, concerned the “extant permission for Raffeen quarry
and conditions re restorative works following excavation.” It therefore appears that
certain of the contentious issues raised by the applicant before this court, about which
objection is taken by the respondent and notice party, on one view, might be considered
not entirely unrelated to those themes. Further, in consideration of locus standi, I also
should not lose sight of the fact the applicant disavows any attempt to collaterally
challenge the quarry permission in an impermissible manner.
124. The overall project is a significant one. The applicant is an NGO and enjoys, as a matter
of law, a general right of standing. The road project, in its entirety involves matters of
European significance and importance. While the quarry is not a European site, there is a
European site dimension to it, in view of the reclassification of the Glounatouig stream to
bring it within the Cork Harbour SPA, which is a European site. I am also satisfied that
there is no evidence that the applicant sought to deliberately withhold points from the
hearing. Also, although the applicant is an NGO, the court nevertheless takes into account
the fact that a number of its members reside in the immediate vicinity of the quarry. The
decision of the court on this issue must be viewed and confined to the particular
circumstances of this case and should not be interpreted as a “freewheeling competence
on the part of judicial review applicants to raise points not raised before the decision
Page 40 ⇓
maker”, something which was rejected by Barrett J. in An Taisce v. An Bord Pleanala and
The Directive
125. The relevant provisions of the Directive are as follows. Article 1 of the 2011 Directive
provides:-
“1. This Directive shall apply to the assessment of the environmental effects of those
public and private projects which are likely to have significant effects on the
environment.
2. For the purpose of this Directive the following definitions shall apply:
(a) ‘project’ means:
-
the execution of construction works or of other installations or
schemes,
-
other interventions in the natural surroundings and landscape including
those involving the extraction of mineral resources…”
126. Article 5 of the 2011 Directive provides:-
“1. In the case of projects which, pursuant to Article 4, are to be made subject to an
environmental impact assessment in accordance with this Article and Articles 6 to
10, Member States shall adopt the necessary measures to ensure that the
developer supplies in an appropriate form the information specified in Annex IV in
as much as:
(a) the Member States consider that the information is relevant to a given stage
of the consent procedure and to the specific characteristics of a particular
project or type of project and of the environmental features likely to be
affected;
(b) the Member States consider that a developer may reasonably be required to
compile this information having regard, inter alia, to current knowledge and
methods of assessment.
[…]
3. The information to be provided by the developer in accordance with paragraph 1
shall include at least:
(a) a description of the project comprising information on the site, design and
size of the project;
(b) a description of the measures envisaged in order to avoid, reduce and, if
possible, remedy significant adverse effects;
Page 41 ⇓
(c) the data required to identify and assess the main effects which the project is
likely to have on the environment;
(d) an outline of the main alternatives studied by the developer and an
indication of the main reasons for his choice, taking into account the
environmental effects;
(e) a non-technical summary of the information referred to in points (a) to (d).”
127. Annex IV provides:-
“INFORMATION REFERRED TO IN ARTICLE 5(1)
A description of the project, including in particular:
(a) a description of the physical characteristics of the whole project and the land-
use requirements during the construction and operational phases;
(b) a description of the main characteristics of the production processes, for
instance, the nature and quantity of the materials used;
(c) an estimate, by type and quantity, of expected residues and emissions
(water, air and soil pollution, noise, vibration, light, heat, radiation, etc.)
resulting from the operation of the proposed project.
An outline of the main alternatives studied by the developer and an indication of
the main reasons for this choice, taking into account the environmental effects.
A description of the aspects of the environment likely to be significantly affected by
the proposed project, including, in particular, population, fauna, flora, soil, water,
air, climatic factors, material assets, including the architectural and archaeological
heritage, landscape and the interrelationship between the above factors.
A description (1) of the likely significant effects of the proposed project on the
environment resulting from:
(a) the existence of the project;
(b) the use of natural resources;
(c) the emission of pollutants, the creation of nuisances and the elimination of
waste.
The description by the developer of the forecasting methods used to assess the
effects on the environment referred to in point 4.
A description of the measures envisaged to prevent, reduce and where possible
offset any significant adverse effects on the environment.
Page 42 ⇓
A non-technical summary of the information provided under headings 1 to 6.
An indication of any difficulties (technical deficiencies or lack of know-how)
encountered by the developer in compiling the required information.”
128. Article 8 of the Directive provides that “the results of consultations and the information
gathered pursuant to Articles 5,6,7 shall be taken into consideration in the development
consent procedure.”
The EIS
129. While in this judgment, I have touched upon aspects of the EIS submitted by the
authority, particularly where referred to in argument and in the affidavits, given the
nature of the applicant’s challenge to the adequacy of the Board’s assessment, it is
necessary to engage with the substance of the relevant portions of the EIS, NIS and the
inspectors report and assessment. In doing so, I should pay particular regard to the terms
of the quarry permission and the screening process concerning the quarry which have
been described above at para. 40 et seq.
130. The physical characteristics and land use requirements of the project are addressed in
chapters 3, 7 and 8. At para. 3.10 the blasting required for the road is considered. A
number of locations of potential areas of blasting are identified and it is noted that “it is
also anticipated that materials present at Raffeen quarry will be used for construction
under the existing planning permission.”
131. Paragraph 3.13 of the EIS concerns “Environmental Management during the Construction
Phase”, and in the context of resource requirements, “earthworks” are considered at para.
3.13.5.1 as follows:-
“The project will require approximately 2.2 million m³ of fill material. It is
anticipated that approximately 1.15million m³ of reusable material will be
excavated from the cuttings for the project. This means that there will be a deficit
of material required to construct the road project, including the project
requirements for higher quality rock material in the order of 1.05 million m³…
.. It is anticipated that the majority of the material deficit will be obtained from
Raffeen Quarry. The route of the proposed road passes to the southern part of the
quarry. The quarry has planning permission to resume material extraction… This
planning permission is valid for a 30 year period.
The potential for cumulative impacts associated with the construction of the road
and quarrying activity occurring simultaneously is addressed in the relevant
specialist EIS chapters and within the NIS. The benefits of using material from the
quarry from a sustainability perspective on air and climate are outlined in Chapter
13: Air and Climatic Factors.
It is anticipated that any fill material, which is sourced in the quarry, will be
transported to its destination within the Lands Made Available (LMA) as the
Page 43 ⇓
southern part of the quarry will be within the lands acquired for the schemes.
Ramps are likely to be formed at appropriate locations, within the quarry boundary,
to facilitate access for dump trucks etc., directly onto the LMA.
Haulage of material from the quarry will access the LMA and avoid using local roads
where possible….”
132. Chapter 17.4.2.1 of the EIS, under the heading “waste”, excavated material is
considered. It is repeated that there will be a deficit of material required to construct the
project and that it is anticipated that where possible the majority of this material will be
obtained from the quarry under its current planning permission. The advantages of using
the reserves in the quarry are repeated. It is further stated that it is estimated that
approximately 21,000 m³ of excavated material from the quarry will be generated in
order to create the wetland habitat area. It continues as follows:-
“At this stage, it is assumed that this material will be suitable for reuse on site as
fill material. By reusing excavation material from the proposed cuttings where
possible and sorting the remaining material from the quarry situated adjacent to
the proposed M28 Road project the impact from excavations is considered to be
slightly negative in the absence of mitigation.”
133. “Interactions and Interrelationships of Impacts” are considered in chapter 18, where an
analysis is conducted of two types of cumulative effects. The EIS was stated to have been
prepared based on headings of its technical chapters including terrestrial, ecology, air and
climate factors, noise and vibration, and landscaping and visual. The potential for in
combination effects is described in s. 18.2 and the potential for significant cumulative
effects in s. 18.3. Analysis is conducted of two types of cumulative effects. The first is the
assessment of effects on receptors or receptor groups such as local residents which may
be affected by different environmental elements generated by the proposed road project
simultaneously or concurrently. This is stated to be referable to interrelationships or in
combination effects between different environmental effects. Thus, where several effects
affect one receptor such as noise, dust, and so on, these are assessed. The second type
of assessment is that of the effects of the proposed road project together with other past,
present and reasonably foreseeable projects where there is a potential for overlap,
spatially or temporally. These are described as the cumulative effects.
134. The cumulative effects of the M28 road project and individual projects are considered at s.
18.3.1 which, in Table 18.4, outlines the potential for cumulative effects, where relevant,
of the proposed M28 road project occurring with each existing or potential project in the
study area under human environment and natural environment. The quarry is considered
and under the heading “Summary of potential for significant effects – human
environment” and the following is stated:-
“The cumulative effects on Raffeen Quarry are assessed on the basis that the
quarry has permission and therefore can extract any time between now and 2038.
It is proposed to utilise material from the quarry where feasible for the construction
Page 44 ⇓
phase of the proposed M28 road project. This has a slight positive cumulative effect
for air quality and climate, noise and traffic as a result of reduced transport
requirements on the local and regional road network and in turn air and noise
emissions during the construction phase of the road and the operation phase of the
quarry. There is however a heightened risk of wind – blown dust from materials
handling and noise from the construction phase of the proposed road project and of
the quarrying activity occurring simultaneously impacting on properties in the
immediate vicinity of the quarry. This risk will be mitigated through the mitigation
measures which will be carried out under the quarry’s current planning permission
and the mitigation measures proposed as part of this application with respect to
dust and noise emissions”.
135. Under the heading “Summary of potential for significant effects – natural environment” it
is acknowledged that quarrying operations at Raffeen Quarry would result in the
disturbance, both direct and indirect, of semi – natural habitats under the quarry
footprint, access routes and adjoining areas including in situ wetland habitats, scrub, semi
– natural grasslands, and areas of recolonising bare ground which support the
pennyroyal, a plant species protected under the Flora Protection Order 2015. It is also
acknowledged that the quarrying operations may affect breeding bird activities upon
areas of quarried cliff face, principally through indirect disturbance, which had previously
supported breeding peregrines. It continues:-
“Quarrying activities may also result in increased release of dusts and particulate
matter which can reduce photosynthetic potential for plants associated with in situ
and adjacent semi – natural habitats. Construction of the road will also result in the
disturbance and removal of semi – natural habitats and pennyroyal, resulting in the
potential for cumulative effects to these species during the construction phase of
the road and the operation phase of the quarry. A habitat and species management
plan has been developed for the M28 road to reduce negative effects from the road
resulting in negligible impacts over the short to medium term and thus the potential
for cumulative impacts associated with quarrying activities is avoided. There is a
potential for cumulative impacts on sensitive ecosystems from dusts and particulate
matter during the construction and operational phases of the road and quarrying
activities. Dusts and particulate matter can be deposited on the leaves of plants
reducing the photosynthetic potential. The literature suggests that the most
sensitive species appear to be affected by dust deposition at levels above 100
mg/m² per day. As such, once dust deposition rates are maintained within the
standard guideline for human nuisance (350 mg/m² per day), as set out in the
mitigation measures specified in Chapter 13: Air and Climatic Factors , the impact
of construction dust on sensitive ecosystems is considered negligible.”
136. The mitigation measures are specified are as follows:-
“Implementation of the mitigation measures as set out in planning documents for
both projects. No further mitigation required. No additional mitigation required.
Page 45 ⇓
Implementation of a habitat and species management as part of the M28 road at
the quarry.”
137. Individual environmental effects are considered in chapters 5 to 17. Terrestrial ecology is
addressed in chapter 12. Potential impacts during the construction phase are addressed in
Table 12.19. It is stated that in the event that aggregate materials are extracted from the
existing quarry to facilitate the proposed project, there is potential for indirect and
cumulative impacts to sensitive receptors within the quarry. This may include the loss or
disturbance of habitat comprising recolonising bare ground which supports protective
plant species, scrub and semi-natural grasslands, in addition to the disturbance of faunal
species associated with the quarry. The direct impacts during both construction and
operational phases, insofar as the quarry is concerned, are considered in Table 12.19. It
is acknowledged that there will be landscape and associated habitat removal, and
fragmentation disturbance to semi-natural habitats. The pennyroyal is addressed and it is
stated that the construction phase would result in the removal of nesting. Direct impacts
were also identified as including potentially, direct collision of faunal species with
construction machinery, especially should night-time works be conducted. No direct
impacts to the quarry were identified for the operational phase. The quarry was
considered to be of county importance and it was stated that impacts to this receptor
during construction and operational phases would be significantly negative at the county
level in the absence of avoidance and mitigation measures. This was further addressed in
a table at 12-149. It is recorded that in order to avoid direct and indirect disturbance of
ongoing breeding activity within the quarry it was proposed to undertake construction
works in this area outside the breeding season, 1st March until the 31st August, inclusive.
Residual impacts, including the direct loss of suitable nesting and breeding habitats were
also addressed. Construction works would not compromise the structural integrity or
suitability of the remaining cliff face habitats located to the south of the footprint.
Landscaping measures were proposed in respect of the operational phase of the project.
It was recognised that such landscaping proposals would directly affect the peregrine
falcon. Details of the landscape mitigation at the quarry were presented in a separate
volume.
138. In Chapter 13, air and climatic factors were considered. Dust emission in the construction
phase were addressed and it was acknowledged that in the event material is extracted
from the quarry to facilitate the project, and to avoid the need to import material from off
site, there was a potential for indirect dust impacts on the nearest sensitive receptors.
The potential for dust emissions from the construction phase of the project, including the
“quarry operation under its current planning permission” was stated to have been
addressed qualitatively in accordance with the NRA guidelines. It was further noted that
while the quarry was not currently operational there was the potential for windblown dust
from the surfaces of open faces and stockpiles on the quarry and in the event that the
quarry is to become operational as a result of the project or under its current permission,
there was a heightened risk of windblown dust from materials handling impact properties
in the immediate vicinity of the quarry. Regarding mitigation measures, in addition to the
standard methods which were outlined in the report, measures were identified to be
Page 46 ⇓
applied to sensitive areas such as the area adjacent to the quarry, in the event that
material is extracted for the purposes of the project, to prevent the potential for dust
impacts on sensitive receptors in close proximity. These included speed restrictions on
site traffic, minimising of dropouts from plant to plant to stockpile, the introduction of
water vouchers, and the requirement to maintain monthly dust level below certain
guidelines. It was felt that with the implementation of such mitigation measures and
adherence to good working practice, the levels of dust generated were unlikely to cause
an environmental nuisance. Where dust levels are found to be above a threshold of 350
mg/m² per day, the mitigation measures must be reviewed as part of a dust minimisation
plan.
139. Noise is considered in chapter 14. Referring to the quarry, it was noted that the quarry
has planning permission for blasting, rock processing and material storage. It was
anticipated that the quarry will be in operation during the construction stage of the road
either for the purposes of supplying material or other needs under its current planning
conditions. Specific reference is made to condition 21 which limits noise emissions, and
condition 24 which controls blasting. The potential impact of the quarry during
construction was addressed and once again the planning permission attaching to the
quarry was identified. It is proposed to utilise the quarry resource for the construction of
the road project to minimise the impact upon material onto the site, from external
sources. Potential noise and vibration impacts from machinery and construction were
included in the construction stage model. At p. 14-32 the predominant noise sources from
the quarry were identified as being from the various items of plant and machinery
involved in quarrying activities, as well as from blast events. It was considered likely that
noise from blast events will be audible at some sensitive receptors, the nearest of which
was approximately 100m from quarry but, it was also acknowledged and stated that noise
from the quarry blast will be intermittent with an average of four blasts per month as set
out in the existing quarry permission, at condition 24.
140. Potential impacts on aquatic biodiversity were considered in chapter 10. In the context of
construction phase impacts it was acknowledged that in the absence of mitigation,
suspended solids impacts would be expected to be largely negative on a local scale with
short-term impacts during the construction phase for freshwater receptors, including the
Glounatouig stream.
141. In the NIS, it is stated at p. 66 that quarrying operations at the quarry would not
contribute to cumulative or in combination impacts to Cork Harbour SPA. This is
particularly addressed in Table 5.6 of the NIS as follows:-
“Quarrying operations at Raffeen Quarry will not contribute to cumulative or in-
combination impacts to Cork Harbour SPA. Quarrying operations to be regulated by
terms of planning to include attenuation of water run-off to the Glountouig stream
which is a tributary of Cork Harbour SPA. In addition, Raffeen Quarry or its
immediate surrounds do not support suitable habitat for over wintering avifauna
Page 47 ⇓
associated with Cork Harbour SPA, therefore quarrying activities will not contribute
to disturbance effects to SCI species for this European site.”
142. The overall conclusion of the NIS was that the Cork Harbour area supports a number of
developments that have been granted planning permission which could, in combination
with the proposed M28 Road project, result in cumulative or in combination effects to that
SPA. It was noted that the large infrastructure developments in the Cork Harbour area
had been granted planning permission on the basis that targeted and site-specific
mitigation is completed to minimise potential impacts. What was considered to be the
remote and tenuous connectivity of the Great Island Channel SAC to the road project
meant that potential impacts were unlikely. The implementation of best practice design,
construction and operational measures were considered to negate the potential future
impacts to that site. All possible sources of effects from the road project, in combination
with all other sources in the existing environment and any other effects likely to arise
from other proposed plans or projects had been identified, and robust and effective
mitigation measures were outlined.
The Board’s Assessment
143. The Board accepted the contents of the inspector’s report before arriving at its decision
and thus the Board’s decision and Ms. Kennelly’s report must be read together.
144. Ms. Kennelly assessed the proposed development, the submissions received from the
applicant, prescribed bodies and third-party observers and the traffic consultant’s report.
She considered the assessment issues arising from the proposed scheme, including the
policy context and the need for the development and the adequacy of the EIA and the AA.
In the second part of the report, she assessed the CPO. At p. 57 of the report, she noted
that one of the issues which was raised by observers was that of project splitting. This
issue was raised, however, in the context of the contention that the road was contended
to be part of the Cork Port project and tied to the expansion of the Port.
145. Issues regarding the quarry were more particularly addressed in chapter 17 of her report
in the context of flora and fauna. The issue raised was described as follows:-
“Cumulative impacts-EIS inadequate-The cumulative effects of the development of
the road and the resumption of the extraction from the quarry have not been
adequately addressed. There would be a phenomenal increase in the rate of
extraction of stone from the quarry for 30 years (as granted under the planning
permission) to 3 years, required for the project.”
146. The inspector noted that the quarry had been subject to much survey and analysis in the
EIS and was also the subject of considerable discussion and debate in both written and
oral submissions. The discussion of the issues relating to the quarry was more particularly
focused on protecting plant and bird species; the pennyroyal and the peregrine falcon.
She noted that the proposed road traverses the southern end of the quarry, necessitating
a substantial area of fill and that the authority intended to source the stone material for
the overall road project from the quarry, which is in separate ownership.
Page 48 ⇓
147. At para. 17.2.2, the inspector referred to issues which had been raised by the Department
concerning the extant of the quarry permission and the conditions regarding restorative
works following excavation. The criticism of the applicant is that these issues were not
adequately addressed or particularly followed up by the Board. At p. 242 the inspector
noted that the quarry had been the subject of considerable discussion and debate, both in
written and oral submissions, and had also been the subject of much survey and analysis
in the EIS. Particular reference was made to the peregrine falcon and the pennyroyal. The
inspector also noted that:-
“…Direct impacts on Raffeen Quarry, during the construction phase, would
principally involve land take leading to habitat removal, fragmentation and
disturbance as well as collision of fauna and avifauna with machinery. Indirect
construction impacts were identified as disturbance and destruction of semi natural
habitats located outside the footprint of the project, such as pennyroyal. No direct
operational impacts were predicted for this receptor. Potential indirect impacts
include ongoing disturbance/avoidance by fauna, vehicle collision, eutrophication
and alteration of the great regime…”
It is also instructive to note, that while the particular emphasis is on habitats, when the
inspector referred to issues raised by the NPWS and third-party observers, she stated that
an issue had been raised by Dr Goodyear that it was impossible to assess the impact on
the habitats within the quarry without certain drawings and that the cumulative impact of
the two projects had not been properly considered. Reference is stated to have been
made to court decisions where it had been established that all elements that are material
to the project for example, which connections must be considered as part of the project.
At p. 249, the inspector continued as follows:-
“On this basis, it was asserted that the proposal to extract stone from the quarry to
facilitate the construction of the road must be considered as part of the overall EIA
of the M28 road project. She further considered that the EIS submitted with the
application for the quarry did not adequately reflect the ecology of the quarry as it
currently exists.”
148. It was noted that while the applicant for the quarry permission had sought to continue
extraction over a period of 150 years on a campaign basis, which would have involved
five phases and extraction well below the water table, the Board decided to restrict the
permission of the first phase with a further restriction on excavation below 16m OD. The
inspector also addressed the concerns regarding the restoration/after-care
recommendations in respect of the quarry development, but observed that these
restoration and aftercare recommendations were stated to be principally to maximise the
benefits for flora and fauna. It was noted, that part of the argument was that those
proposed plans were based on extraction over several phases on a campaign basis and
would have resulted in extraction to a level approximately 20m below the water table. It
was proposed that once the phases were complete, the quarry floor would be flooded to
the natural water level, to form a lake. The argument had been made that this would
Page 49 ⇓
have necessitated substantial drawdown of water and the topography and environment of
the quarry would be dramatically different to that which received planning permission,
which provided that there would be no extraction below the water table. The inspector
continued at p. 251 of the report:-
“Thus, the restoration plans on file are considered to be indicative only. In addition,
as the proposed road project occupies much of the southern part of the quarry and
would be constructed on an embankment with an elevation of approximately 20 m,
together with proposals to recreate wetland and other habitats on either side of the
embankment, it is considered that the previously proposed restoration plan cannot
be implemented as originally envisaged. However, the restoration of these areas of
the quarry outside the CPO line are beyond the scope of this application and the
remit of the Board.”
149. While the inspector agreed that, ideally, a revised topographical plan of the “worked-out
quarry”, with the road in place, would be useful in terms of assessing the impact of the
two schemes, it was considered that the nature of the established use and the terms of
the permission granted by the Board, together with the information submitted with both
the application for the quarry and the current application for the road project, provided a
sufficient level of information upon which the Board could make a decision on the
application which was before it. It is clear that the inspector considered issues relating to
flora and fauna in the context of the restoration plan for the quarry, with the potential of
cumulative impacts being identified. She concluded that provided mitigation measures
and monitoring regimes were implemented as proposed, she did not consider that there
would be significant adverse impacts on the habitat of the species it supports.
150. Reference was made at the oral hearing to previous court decisions involving windfarm
developments wherein it was held that all elements that were material to the project
must be considered as part of the project. It was therefore asserted that the proposal to
extract stone from the quarry to facilitate the construction of the road must be considered
as part of the overall EIA of the M28 road project. Dr. Goodyear also expressed the view
that the EIS submitted with the application for the quarry did not adequately reflect the
ecology of the quarry as it currently exists. Counsel for the notice party had addressed
this issue in his submissions to the inspector at the oral hearing. Reference was made to
the fact that the quarry had been subject to the EIA unlike the windfarm which were the
subject of court judgments referred to by Dr Goodyear.
151. At p. 251 of the report the planning permission for the quarry, the appeal process and the
registration of the quarry were referred to. The inspector considered the cumulative
impacts with the “permitted quarry at Raffeen” and addressed complaints that the EIS
was deficient, by reason of:
i. certain alleged inadequate assessment of alternatives;
ii. failure to comply with s. 15 of the Climate Change and Low Carbon Development
Act 2015;
Page 50 ⇓
iii. failure to address the species protected under Annex IV of the Habitats Directive,
for example, otters;
iv. inadequate surveys in the absence of mention of invasive species;
v. alleged deficiencies in the NIS with particular reference to the importance of and
intermittent usage of overwintering sites for wild birds; and
vi. issues regarding deficiencies in planning drawings and documents.
152. Ms. Kennelly referred in some detail to the EIS and considered in particular chapters 13,
14 and 18. She noted that provision for mitigation had been considered in specialist
chapters in the EIS where any potential impact to sensitive receptors, human or natural,
is likely. I have dealt with these above – suffice to note that these chapters were
considered by the inspector as were the potential for inter-relationship/in combination
effects as described in s.18.2, s. 18.3. and Table 18.4 which refer specifically to the
quarry. She noted that there was a potential for cumulative impacts from the proposed
development, in conjunction with existing, planned and proposed infrastructure should
construction periods coincide, particularly in terms of dust and noise. She observed that
the project included strict controls on dust and noise emissions during construction as did
the other planned projects in the vicinity. She further considered that local cumulative
effects in respect of noise, vibration and dust during the construction period which were
likely to arise in the vicinity of the quarry, but that the extraction of materials in the
quarry had the benefit of planning permission and had been subjected to EIA, with
associated mitigation measures to restrict such emissions. A similar conclusion was
reached in respect of the direct, indirect and cumulative effects on air and once again
while some cumulative effects may arise from the development together with existing and
permitted developments, these would be avoided, managed and mitigated by measures
which form part of the proposed development and through suitable conditions. She was
satisfied that the significant environmental effects arising as a consequence of the
proposed development had been adequately identified, described and assessed and that
these effects could largely be avoided, managed and mitigated by proposed mitigation
measures and suitable conditions. With regard to the direct, indirect and cumulative
effects on human beings, the inspector was satisfied that these issues had been
appropriately addressed in the application and information submitted by the applicant and
where adverse impacts were likely to arise, they would be avoided, managed and
mitigated by the measures which formed part of the proposed scheme, the proposed
mitigation measures and through suitable conditions. She concluded that the proposed
development would not have any unacceptable direct or indirect impacts in terms of
human beings.
153. Ms. Kennelly was satisfied that the EIA had been carried out in accordance with Article 3
of the 2011 Directive and s. 51 of the Act, and that it had assessed the impacts on human
beings, flora, fauna, soil, water, air, climate, landscape, material assets, cultural heritage
and the interaction between the foregoing.
Page 51 ⇓
154. The screening for AA was also considered by the inspector and she noted that there were
two European sites within the zone of influence of the project namely the Cork Harbour
SPA and the Great Island Channel SAC. However, she also concluded that as the site of
the proposed development was not situated within a European site, no direct impact
would arise. Nevertheless, indirect impacts were possible due to the proximity and
connectivity to these sites through three water courses and through disturbance of the
avifauna, during both construction and operational phases of the development. She
records that it was decided not to screen out the Cork Harbour SPA or the Great Island
Channel SAC and both sides were brought forward for an AA and the potential impacts of
the development, both direct, indirect and in combination effects on the sites was
considered in detail. Ultimately, the inspector concluded that there would be no direct
impacts on any Natura 2000 site arising from the development. She was satisfied that
there would be direct and indirect impacts on habitats during construction and indirect
impacts during the operational phase of the project. The direct impacts included a net loss
of wetland habitats and a loss of semi – natural grasslands. She was satisfied that
compensatory wetlands and grasslands would offset these impacts. At p. 301 of her
report she commented as follows:-
“Cumulative impacts on habitats from the proposed development in conjunction
with existing, planned or proposed development are unlikely to arise, except in
relation to the habitats within Raffeen Quarry. The issue was discussed in detail at
17.4.5 above. It is considered that routing the proposed road through the quarry
would result in the loss/fragmentation/disturbance of habitats, but as the quarry
has planning permission to extract materials across the entire footprint of the
quarry over the next 30 years, these habitats are likely to be lost permanently,
even if the road does not go ahead. In particular, the proposal to carefully recreate
high quality wetland areas in advance of the construction phase, including the
harvesting and translocation of species and vegetation will provide for permanent
benefits and opportunities for continuity of the existing biodiversity. It is
considered, therefore, that the cumulative impact of the proposed road and the
permitted quarry or habitats within the quarry will be positive, given that the
proposed development includes the provision of compensatory habitats which will
be carefully recreated and monitored to secure successful establishment of
equivalent conditions.”
155. Ms. Kennelly concluded at p. 335 of her report that on the basis of the best available
scientific knowledge, the proposed development would not adversely affect the favourable
conservation status of overwintering avifauna populations, including curlew or any other
qualifying interests, associated with Cork Harbour SPA or of the qualifying interests of
Great Island Channel SAC. She was therefore satisfied that on the information which was
in file, which she considered adequate to carry out the Stage 2 AA, that the proposed
development, individually or in combination with other plans or projects would not
adversely affect the integrity of any European site.
Page 52 ⇓
156. The inspector also considered issues regarding the peregrine falcon and its nesting
habitats, together with mitigation measures proposed during the construction phase in
order to direct the peregrine falcon away from the quarry during that phase and
concluded:-
“It is considered, therefore, that the proposed suite of mitigation measures
presented in the EIS, HSMP and at the oral hearing, apart from the proposed Lough
Beg artificial structure (16/11/17), together with the presence of suitable
alternative habitat within the Zone of Influence, would provide for adequate
alternative nesting sites for breeding peregrine falcon, which is no longer a species
of conservation concern. The proposed woodlands screen planting would also serve
to deter this species from nesting during the operational phase at the cliff face in
close proximity to the motorway. Provided that the mitigation measures and
monitoring regime are implemented as proposed, I do not consider that there
would be significant adverse impact on the species or its habitats.”
157. The inspector thought questionable the suitability of the quarry as a breeding site and
observed that it was accepted that there were potentially suitable habitats in the wider
district for breeding peregrine falcons which are no longer a species of conservation
concern. Notwithstanding this, she stated:-
“It is considered that the proposed mitigation measures to direct the species away
from the motorway and to provide for alternative artificial nest sites, together with
monitoring, would help to avoid and offset the potential adverse impacts.”
158. A proposed artificial nest box should not be implemented on the grounds of proximity to
the SPA and a possible conflict with the bird species for which the SPA had been
designated. The inspector concluded that the cumulative effect on the peregrine falcon
was likely to be positive as no compensatory measures were proposed as part of the
permitted quarry development, but mitigation measures as part of the road project would
minimise impacts on the species.
159. Similarly, Ms. Kennelly addressed the position of the pennyroyal mint, a protected plant
species. She noted that Dr Goode of the NPWS informed the hearing that translocation of
the plant species is not required because the variety identified as growing within the
footprint of the proposed road was non – native and did not have biological status.
Nevertheless, because s. 21 of the Wildlife Act 1976 and the Flora Protection Order 2015
refer to pennyroyal mint as a species without distinguishing variety, an application for a
licence to take, alter or interfere with the habitat and environment of pennyroyal mint
was still required, and thus the inspector considered the position of this species.
160. At para. 20.6 of the report, having considered the likely significant direct and indirect
effect on human beings, flora and fauna, soil, water, air, climate and landscape, material
assets and cultural heritage, and the interactions between the foregoing, she considered
that the significant environmental effects arising as a consequence of the proposed
development had been adequately identified, described and assessed. She was satisfied
Page 53 ⇓
that these effects can largely be avoided, managed and mitigated by the proposed
mitigation measures by suitable conditions. Where any residual impacts remain without
being fully mitigated, she considered that the environmental effects would not justify
refusal of approval, having regard to the overall benefits of the proposed development.
The adequacy of the Assessment and Report of the Inspector
161. It is quite clear that the inspector was aware of the necessity to consider the development
cumulatively with other developments and in particular the extraction of material from the
quarry. I am satisfied that the inspectors conclusions were based on the quarry operating
within the confines of its existing permission. It is also clear from the contents of her
report, when read in its entirety and in context, that she cannot but have been aware of
the conditions relating to the planning permission, the EIS which accompanied the
application for that permission and the subsequent assessment which was conducted in
2012. It is perhaps true to say that quarry permission was more significantly and directly
raised in relation to concerns regarding the effect of the flora and fauna within the quarry,
but it is clear from p. 250 of the inspector’s report that she was aware of the quarry
permission, the registration of the quarry, the fact that the original conditions were
appealed and the restrictions confining excavation to the first phase. She was also aware
of conditions which were attached placing restrictions on noise, blasting, groundwater
monitoring and implementation of a restoration plan, to which I have previously referred.
162. It is true that the validity of the quarry permission was not specifically raised but the
applicant has expressly disavowed any attempt to collaterally challenge that permission;
albeit implicit in its argument is that in the context of assessing cumulative impacts, the
nature of the previous permission, and perhaps some legal frailty underpinning it ought to
be taken into account, something which was not done by the authority, the Board, or its
inspector. The point at issue here is that the applicant maintains that it is impermissible
to regard the quarry development as being a discrete development from that the road
itself and that in this regard the quarry EIA was on a substantially different development
to the one proposed here. I am not satisfied that this is the case.
163. In Friends of the Curragh Environment Limited v. An Bord Pleanála the applicant sought
leave to apply for judicial review, and an of certiorari quashing two decisions of An Bord
Pleanála whereby it granted permission for a realignment of approximately one kilometre
of roadway on the Curragh, and secondly the demolition of the western half of the west
stand of the Curragh Racecourse and the construction of a 72 bedroom hotel and ancillary
facilities. The Turf Club had engaged in the redevelopment of the Curragh Racecourse
complex which had been undertaken under a master plan. This plan aimed to create a
modern racing complex with improved stands, visitor facilities and stables. The first phase
of the redevelopment consisted of the realignment of the road, the demolition of part of
the existing stand and construction of a 72 bedroom hotel and ancillary facilities. It was
common case that there were further intended phases of the redevelopment. The Turf
Club submitted one EIS in relation to the applications for permission for the road
realignment and hotel development. It is to be noted, however, that it was also common
case that an EIS was not mandatory, having regard to the threshold set by the Planning
Page 54 ⇓
and Development Act 2000 and the Regulations made thereunder. The failure of the
respondent to assess the impact on the environment of the overall master plan for the
racecourse prior to making its decision on the two appeals relating to road alignment and
hotel development, was central to a ground upon which the challenge was brought. In
essence, this was a project splitting ground. At p. 18 of the judgment, Finlay Geoghegan
J. described the questions required to be considered as being:-
“ … whether there is anything in Directive 85/337/EEC as amended which makes it
clear that a planning authority must assess not only the impact on the environment
of the development for which permission is sought but also the impact on the
environment of future or proposed related developments for which permission is
not yet sought.”
164. Having considered the provisions of Article 2 of the then applicable Directive 85/337/EEC,
she concluded that there was nothing in the Directive which made it clear that the:-
“the planning authority must assess not only the impact on the environment of the
development for which permission is sought, but also the impact on the
environment of future or proposed related developments for which permission is
not yet sought.”
165. With regard to the project splitting suggestion, she emphasised that there was no
allegation that the Turf Club had artificially divided the master plan to avoid the need to
lodge an EIS or an EIA on those parts of the project which were the subject matter of the
applications for planning permission. While it was clear that there are circumstances in
which a planning authority should have regard to related developments or even proposed
developments when considering whether an EIA is required, the issue in that case was
different. An EIS was submitted and an EIA conducted. Finlay Geoghegan J. concluded:-
“The conclusion which I have reached that Directive 85/337/EEC as amended only
requires an environmental impact assessment of the project or development which
is the subject matter of the application for planning permission and not of any
related project which may be the subject of future or proposed application appears
to me similar to the conclusion reached (albeit in relation a different national
statutory scheme) by Davis J. in the English High Court in R. (on the application of
166. I think it ought to be borne in mind that this dictum concerned the provisions of the
Directive 85/337/EEC, but in my view it nevertheless supports the proposition that the
Directive did not require an examination by way of EIA of anything except the project for
which the development consent was sought. This does not detract, however, from the
requirement to conduct cumulative assessments in appropriate cases.
167. Different consideration apply where circumstances give rise to project splitting. In
O’Gríanna v. Framore Limited [2014] IEHC 632 Peart J. held that the connection of a wind
farm to the national grid was an integral part of the overall development of which the
Page 55 ⇓
construction of the turbines was the first part. He therefore concluded that the Board had
failed to carry out an EIA in accordance with s. 172 of the Act of 2000 in that no
cumulative assessment of the proposed development and the necessary connection to the
national grid had been undertaken. Therefore, he quashed the decision of the Board
which granted the first permission and remitted the matter back for further consideration.
Subsequently, the Board issued a notice on the developer requiring it to submit a revised
EIS to incorporate sufficient information to enable the Board to conduct an EIA in relation
to the overall proposal, including the grid connection. In response, the developer
submitted a revised EIS, an AA screening report together with a NIS.
168. Further judicial review proceedings ensued. A number of issues arose. The first was
whether the Board had failed to carry out an EIA in respect of the grid connection works
and the wind turbine development by reason of the fact that the grid connection works
did not form part of the proposed development in respect of which the application for
planning permission was made. McGovern J. in his decision in O Gríanna v. An Bord
Pleanála (No. 2) [2017] IEHC 7 observed that an overriding objective of the Directive was
to ensure protection of the environment and quality of life. Noting that the process in
which the court was engaged was a judicial review, and not an appeal on the merits
against the decision of the Board, and also acknowledging the views expressed by Lord
Hoffman in Berkeley v. The Secretary of State for the Environment [2001] 2 AC 603,
that the EIA Directive should be given a purposive interpretation and should not be used
to strike down consents where there has in reality been substantial compliance with its
requirements, having identified with precision what those requirements are. McGovern J.
observed at para. 39:-
“39. The E.I.A. Directive and the Irish legislation envisage a situation where there may
be different stages of the consent procedure. This is recognised in the judgment of
Peart J. in determining that for an E.I.A. to be completed at this state of the
development, it was required to assess the cumulative impacts of the grid
connection and the wind farm. It is also acknowledged in condition no. 2 applied by
the Board. The grid connection was not authorised by a decision of the Board in
these proceedings.
40. The principle point raised for the applicants in the substantive High Court hearing
before Peart J. related to the absence of information on the grid connection to
enable a cumulative assessment to be carried out and is not impugned in these
proceedings.
41 . In the current application the applicants have not raised any point on the
substantive E.I.A. carried out nor have they purported to allege any deficiency in
the E.I.A. The judgments of the Supreme Court in O'Connor v. Environmental
Protection Agency [2003] 1 IR 530 and Martyn v. An Bord Pleanála [2008] 1 I.R.
336 suggest that an E.I.A. can be carried out at a stage wherein the partial consent
for part of an overall project has been given.”
Page 56 ⇓
169. McGovern J. stated that the applicants had not engaged with the content of the EIA nor
had they shown any prejudice regarding matters that characterise a significant alteration
to the application:-
“When all is said and done the overall development is still a six turbine
development with a connector and the decision impugned in this application
concerns the wind farm aspect of that development.”
He was satisfied that the EIA assessment conducted by the Board was adequate and was
a necessary consequence of the remittal by Peart J. in the substantive proceedings.
Decision
170. For the reasons outlined above, I am satisfied that the application in this case ought to
have been made, and was made, in accordance with the provisions of the 2011 Directive.
171. In my view, there is no question of project splitting in this case and the project for the
purposes of Article 2 (1) of the 2011 Directive is the road scheme. The quarry is owned
by a private operator and has its own planning permission which was obtained long before
this road project was prepared. The project is to be carried out, not by the owners of the
quarry, but by the authority and notice party to these proceedings. The cumulative
impacts and effects of the quarry and the road were in any event considered in great
detail. In my view, the inspector and the Board were aware of what was proposed in
terms of the quarry and the use of materials therefrom. I am also satisfied from my
review of the inspector’s report that the Board was also made aware of the essential
terms of the quarry planning permission and the 2012 screening. It is also quite clear, as
was reiterated on many occasions within the EIS, that the extraction of the materials, if
feasible or possible, is proposed to be in accordance with the quarry planning permission
and conditions attached thereto.
172. To the extent that the applicant maintains that there has been a cessation of quarry
activity, I find that the assessment of the quarry and cumulative impacts were conducted
on the basis of current ecology. Further, I am not satisfied that any case regarding the
adequacy of the AA has been established. It seems to me to be correct, as the
respondent submits, to say that the inspector was very much alive to water pollution and
how it could affect the SPA. It also appears to me, without finding it necessary to decide,
that there is much merit in the submission of the notice party that the applicant appears
to go no further than raise the fact of a hydrological link between the quarry and the SPA,
but without advancing any evidence of any likely effects.
173. Further, insofar as the screening assessment of the quarry is concerned, while the
applicant maintains that there is a frailty attached to the manner in which this
assessment was conducted, the quarry is not a European site and what was required to
be consider whether there were likely to be significant effects on the Cork Harbour SPA. I
am satisfied that such exercise was conducted and it was concluded that the quarrying
operations would not contribute to cumulative or in combination impacts with the Cork
Harbour SPA.
Page 57 ⇓
174. Considerable emphasis was placed by the parties on the proper interpretation of the
quarry permission. Reliance was placed on decisions such as Re XJS Investments Limited
[1986] I.R. 750 and Lanigan v. Barry [2016] 1 I.R. 656. On the one hand, the notice
party suggests that on the application of that test to both the quarry development and
the development consent for the road project, that a proper interpretation of planning
permission is that neither permission intended to impose any restriction on the rate of
extraction of materials in the quarry. The applicant takes a completely different view.
There is no challenge to the validity of that permission before this court, and in my view,
despite various points raised by the applicant, the planning permission must continue to
enjoy the presumption of validity. It is clear that the Board was aware of the controversy
regarding the rate of extraction, as it was specifically raised in consideration of issues
relating to flora and fauna. As previously stated, in my view there is evidence from
various statements in the EIS to show that the Board was aware that it is proposed that
the majority of the shortfall of fill material required to construct the project, after the use
of excavated materials from the cuttings for the project, will be obtained from the quarry
in accordance with its permission where possible. The Board was alive to these issues and
it appears to me that it conducted its assessment with these considerations and
objections in mind.
175. While there may be a difference of opinion regarding the proper interpretation of the
quarry permission, I am not satisfied that there is anything in the inspector’s report which
was adopted by the Board which might be said to confer a planning status on the quarry
which it does not otherwise have. Nothing in this decision is to be taken as an expression
of the court’s views as to whether any activity which may be engaged in by the quarry
operators in the future, whether as part of the extraction of materials for the project, or
otherwise, may or may not amount to a breach of the planning permission or constitute,
or not, an intensification of user, requiring a further planning application. Given that the
road authority is the planning authority charged with the enforcement of planning
legislation, it is to be assumed that it will not abdicate its responsibility in this regard.
176. In all the circumstances, but particularly in the light of the very detailed review of the EIS
and AA conducted by the inspector, I am satisfied that the Board had before it
information on which to determine that the EIS, the NIS and the EIA of the road
project/scheme were adequate, including on those issues concerning the quarry.
177. Even if the court was to disagree with some particular aspect of the assessment
conducted by the Board, the proper role of the court in the consideration of an application
for judicial review must not be forgotten. In this regard, I have been referred to the
decision of Hedigan J. in Craig v. An Bord Pleanála [2013] IEHC 402, where he stated
that:-
“The adequacy of an EIS is thus clearly a matter for the Board which is the
decision-maker. The assessment of the adequacy of the EIS is a factual matter
involving considerable expertise in planning. It is classically especially a matter
Page 58 ⇓
upon which an expert body must decide. The test for this court in examining such
an assessment is thus the O’Keeffe one.”
In the light of the court’s observations and finding on the locus standi issue, this appears
to me to be particularly relevant in the context of a challenge based on grounds that were
not specifically raised before the decision maker. Nevertheless, and in any event, I am
satisfied that the Board had before it relevant material on which to consider the issues
raised in respect of the quarry.
Preliminary reference
178. The applicant maintains that this is similar to the recent decision of Simons J. in Friends
of the Irish Environment v. An Bord Pleanála [2019] IEHC 80 but it seems to me that
there is a relevant distinction between the facts of this case and those considered by
Simons J. There the applicant sought to extend the time of a permission which it enjoyed.
As explained by Simons J., the dispute centred on whether the competent authority had
to fulfil certain procedural requirements under the Habitats Directive, and in particular
whether they applied only on the occasion of the original grant of a planning permission
or whether they also applied to a subsequent decision which extended the duration of the
planning permission but involved no physical changes to the programme as permitted.
The permission was required to be implemented within 10 years and was extended for a
further period of five years. It was this decision to extend the duration of the planning
permission which was impugned in that decision. Here no such application is made by the
quarry operators. In my view, no issue arises which requires such a preliminary
reference.
Conclusion
179. Despite the skilful arguments of counsel for the applicant, I have come to the conclusion
that the EIS was required to be, and was, conducted in accordance with the requirements
of the 2011 Directive. I am not satisfied that the applicant has established that the
respondent has been in breach of its obligations under the 2011 Directive, or that the
approval of the scheme or the granting of the consent to the carrying out the
development are invalid for the reasons advanced. I am not satisfied that the applicant
has established that the project was not properly assessed or that the combined in
combination effects of the road and the quarry were not adequately addressed and
assessed.
180. In the circumstances, the applicant has failed to discharge the onus of proof which lies on
it and I must therefore refuse the relief sought.
Result: Reliefs refused