H349
Judgment Title: Kevin O'Halloran & Ors -v- Ken Fetherston & Ors Neutral Citation: [2012] IEHC 349 High Court Record Number: 2009 10633P Date of Delivery: 31/07/2012 Court: High Court Composition of Court: Judgment by: Mac Eochaidh J. Status of Judgment: Approved |
NEUTRAL CITATION NUMBER [2012] IEHC 349 THE HIGH COURT [2009 No. 10633 P] BETWEEN KEVIN O'HALLORAN AND TERESA O'HALLORAN PLAINTIFFS AND
KEN FETHERSTON AND BERNADETTE FETHERSTON AND BLACKROCK INNS LIMITED AND ELLEN CONSTRUCTION LIMITED AND PAUL C. O'DWYER TRADING AS O'DWYER AND ASSOCIATES AND WYG IRELAND LIMITED DEFENDANTS AND
MCKELAN CONSTRUCTION LIMITED THIRD PARTY JUDGMENT of Mr. Justice Mac Eochaidh delivered on the 31st day of July, 2012 1. This is an application to set aside a third party notice because it is said that the requirements of s. 27 of the Civil Liability Act 1961, that such a notice be served as soon as reasonably possible were not met. 2. The fifth named defendant was the architect of a building in which the plaintiffs purchased an apartment in late 2004. It is noteworthy that he did not perform a supervisory role during the construction of the building and carried out no inspections of the building works as they progressed. Whilst this is very often a function assigned to the architect on a project, this was not what happened in this case. 3. The third party was the main sub-contractor for the project and is said to have carried out most of the building works on the site. The main contractor (the fourth named defendant) is in liquidation, a factor which may explain why the main contractor has not sought to join its sub-contractor - something one might expect where there are allegations of shoddy building works. 4. The plaintiffs say that they have suffered from significant damp and mould problems at their home and that remedial efforts have failed. On 3rd September, 2009, their solicitors wrote 'O'Byrne' letters to five intended defendants but of these only two were ultimately sued. I note that though the third party was indicated as an intended defendant in the O'Byrne letter, the plaintiffs ultimately did not sue the third party. I also note that the plaintiffs have not now sought to join the third party as a co defendant. 5. A statement of claim was delivered on 1st March, 2010, and para. 15 alleges negligence and breach of duty by the architect in the design, specification and construction of the property. Reasonably elaborate particulars of this plea are set out describing the absence of insulation, missing membranes, non-complaint U-values, absence of a thermal brake, absence of vertical damp-proof coursing and other matters all connected with what the plaintiffs assert is the cause of the dampness in the apartment. The plaintiffs also say that an opinion on compliance furnished by the fifth named defendant was false, inaccurate and misleading. The reason I refer to the detail contained in the statement of claim is to show that all of the defendants are elaborately informed that the plaintiffs believe that the dampness is caused by poor design and construction and inadequate materials. As the fifth named defendant was not a supervisor of the works, he could not have known of inadequate materials or poor constriction methods. Nor could he have known of any deficiencies covered up by completed works. 6. An exchange of particulars took place between the plaintiffs and the fifth named defendant which provided quite technical detail of allegations of want of compliance with Building Regulations amongst other matters. 7. The fifth named defendant delivered its defence on 1st November, 2010. The defence notes the involvement of the third party in the construction of the apartment and there are numerous references to matters in respect of which the third party had responsibility. Based on this, the third party says that on the date of the delivery of the defence, the fifth named defendant had sufficient knowledge to join it as a party. 8. For the most part, the references to the third party in the fifth named defendant's defence assert what the third party's responsibilities were, but make no clear allegations against the third party except that para. 20 of the defence says:-
12. In the second affidavit of the fifth named defendant (sworn on 20th July, 2012) further detail is given in relation to the inspection of the plaintiffs' apartment. The Court is told that the plaintiffs facilitated an inspection on 19th July, 2011 - some eight months after the defence was delivered. The plaintiffs excavated holes in the floor of their apartment to facilitate an inspection of the insulation of the floor slab by the fifth named defendant's expert. On the same day, a detailed and invasive inspection of the rest of the apartment was conducted and this included an investigation of the cavity insulation and ventilation. The fifth named defendant's expert produced a report on 25th October, 2011. 13. I accept that the investigations carried out by the fifth named defendant's expert armed him with sufficient information to ground procedings against the third party and this is information which he did not have at the time the defence was filed. There is a significant difference between the general references and allegations relative to the third party in the defence and the specific allegations contained in the third party notice, as set out above. In this connection I note the comment by McMahon J. in Robins v. Coleman et al [2010] 2 I.R. 18, at 194, as follows:
'Even though there were pleas in the defence relevant to the third party, there is a difference between a general plea in a defence and swearing an affidavit setting out the basis on which it is alleged counsel [i.e. the proposed third party} was negligent. A statement from Mr. Murphy was relevant to this. It was not unreasonable to have sought a statement from Mr. Murphy and awaited its arrival, it was a prudent action'." 15. In the recent decision of EBS Building Society v. William E. Leahy and Others [2010] IEHC 456, Hogan J. usefully summarises recent judicial comment on s. 27 of the Civil Liability Act 1961, as follows:
10. Second, the concept of what is "as soon is reasonably possible" within the meaning of s. 27(1)(b) is a relative one and depends on the circumstances of the case: see, e.g., Connolly v. Casey, .Molloy v. Dublin Corporation [2001] 4 JR. 52 and Robins v. Coleman. The Oireachtas did not seek to fix a set time period, but rather imported a concept of relative urgency which is designed to compel the defendant to seek to issue a third party notice with all deliberate speed having regard to all the relevant circumstances. As Murphy J explained in Molloy [2001]4 JR. 52 at 56-57): 'The statute is not concerned with physical possibilities but legal and perhaps commercial judgments. Proceedings cannot and should not be instituted or contributions sought against any party without assembling and examining the relevant evidence and obtaining appropriate advice thereon. It is in that context that the word 'possible' must be understood. Furthermore, the qualification of the word 'possible ' by the word 'reasonable ' gives a further measure of flexibility ... " Conclusion 18. I have also considered two other factors in deciding not to set aside the third party notice. The fifth named defendant says that it anticipated that another of the defendants (namely, the main contractor) would seek to join its sub-contractor as a third party given its presumed state of knowledge about the involvement of the third party in the building project. This was not an unrealistic expectation on the part of the fifth named defendant although the fact the main contractor did not ultimately do so highlights the danger of waiting for another party to join a third party to proceedings. 19. The other factor I have considered is that no real prejudice is suffered by the third party arising from the 14-month delay. Though the third party claims that seven years have passed since it was last involved in the project, such period is not solely or even mainly attributable to the actions of the architect. Even if the third party notice had issued immediately after the delivery of the defence, the period between the last involvement of the third party and such an event would have been about six years. The extra year or so occasioned by the delivery of the third party notice, in my opinion, does not ground a plea of prejudice and, fairly, counsel for the third party did not press this matter. 20. I refuse to make an order setting aside the third party notice, but in view of pending trial of the main action, I require the parties to engage with the Court to establish a strict timetable for exchange of pleadings and any interlocutory matters in the third party proceedings to ensure that the plaintiffs' action proceeds as planned and that the third party action closely accompanies that action. I will hear the parties on the timing of all matters pertaining to the third party action.
|