H345
Judgment Title: Winthrop Engineering Ltd -v- David Flynn Limited Neutral Citation: 2012 IEHC 345 High Court Record Number: 2010 5967S Date of Delivery: 31/07/2012 Court: High Court Composition of Court: Judgment by: Mac Eochaidh J. Status of Judgment: Approved |
NEUTRAL CITATION NUMBER [2012] IEHC 345 THE HIGH COURT [2010 No. 5967 S] BETWEEN WINTHROP ENGINEERING LIMITED PLAINTIFF AND
DAVID FLYNN LIMITED DEFENDANT JUDGMENT of Mr. Justice Mac Eochaidh delivered on the 31st day of July 2012 1. This is an application by the plaintiff for liberty to enter final judgment in the sum of €52,500. 2. The defendant was engaged as the contractor to construct a hotel, office and apartment development pursuant to a Building Contract. The plaintiff was the nominated subcontractor for mechanical installation works on the project and the nomination of the plaintiff was communicated to the defendant by the project architects on 30th January, 2006. 3. Article 16 of the Building Contract provides:
5. The parties agree that the plaintiff is owed the sum of €52,500 for services it provided in respect of the building works. 6. On 29th September, 2008, the defendant issued an invoice to the developer in the amount of €232,788.50 which included a claim in respect of the €52,500 owed to the plaintiff. The developer has not honoured this invoice. 7. Discussions took place between the parties to these proceedings, and on the 26th February 2009, an agreement was reached as to the amount of money owed to the plaintiff connected with the building project. The agreement of the 26th of February is at the heart of these proceedings because the plaintiff sues on that agreement and not on the Building contract. Taking account of a set-off not relevant to these proceedings, the sum said to be outstanding on that date was €192,500. About one month later an undated letter was written by the plaintiff to the defendant setting out what it believed had been agreed on 26th February, 2009. Briefly stated, the letter recorded that the overall sum owing to the plaintiff comprised €140,000 and a separate amount of €52,500. The plaintiff recorded that the sum of €140,000 was to be funded from an insurance claim and, critically, the letter says:
9. At paragraph 2(c) of the same letter, the question of the payment of the second sum of €52,500 is addressed in the following terms:
11. Paragraph 3 of the undated letter recording the agreement of 26th February, 2009, is in the following terms:
12. In these proceedings, the plaintiff sues the defendant for breach of the agreement reached between them on 26th February, 2009. There is a dispute between the parties as to what was agreed on that day, but there appears to be no dispute that the defendant agreed to pay the plaintiff the sum of €52,500 on receipt of those monies from the developer. The defendant argues that the undated letter records an obligation to discharge this sum when Noel Burke Developments Limited discharges the same sum to the defendant, and more particularly, that the defendant will pay the plaintiff that sum within seven days of receipt by it of the sum from Noel Burke Developments Limited. As none of the sum owing to the plaintiff has been received from the developer, the defendant asserts that it does not owe the money sought in this application. 13. The issue for decision on this application is whether the defendant has asserted a real defence to the plaintiffs claim.The judgment of McKechnie J. in Harrisrange Ltd. v. Michael Duncan [2003] 4 IR 1, summarises the principles governing the exercise of discretion on an application for summary judgment. I refer to the following passage:
(vii) the test to be applied, as now formulated is whether the defendant has satisfied the court that he has a fair or reasonable probability of having a real or bona fide defence; or as it is sometimes put, 'is what the defendant says credible?', which latter phrase I would take as having as against the former an equivalence of both meaning and result; (ix) leave to defend should be granted unless it is very clear that there is no defence; 16. For the sake of completeness I should add that evidence adduced by the parties as to a promise of work for the plaintiff to be arranged by the defendant as a form of settlement of this dispute is not relevant to this application and does not operate, whether by estoppel or otherwise to prevent the defendant from seeking to assert a defence to the proceedings and a trial on the merits of the plaintiff’s claim 17. I refuse the relief sought in the notice of motion and I adjourn the application to to plenary hearing in accordance with Order 37 RSC and I will hear the parties as to directions for pleadings etc as, if the matter had been commenced by plenary summons.
|