Judgment Title: E. S. B. & Anor -v- Commins Composition of Court: Judgment by: Laffoy J. Status of Judgment: Approved |
Neutral Citation Number: [2011] IEHC 316 THE HIGH COURT 2011 6062 P BETWEEN ELECTRICITY SUPPLY BOARD AND EIRGRID PLC PLAINTIFFS AND
JOHN COMMINS DEFENDANT Judgment of Miss Justice Laffoy delivered on 22nd day of July, 2011.
1. The application
(b) an order restraining the defendant from preventing the plaintiffs or either of them from entering on the defendant’s said lands and making such inquiries, investigations and examinations as they think proper relating to the 110 kV line in question, which is known as the Dalton-Galway 110 kV loop line, and, in particular, the construction thereof, and the monitoring, approval and inspection of the said construction pursuant to – (i) s. 20(4) of the Act of 1927, and (ii) Regulation 8(2) of the European Communities (Internal Market in Electricity) Regulations 2000 (S.I. No. 445/2000) (the Regulations) for the purpose of the exercise or performance of the powers and functions conferred on the plaintiffs by the Act of 1927, as amended, and/or the Regulations, as amended.
2. Factual background 2.2 The Dalton-Galway loop line passes over the defendant’s lands registered on Folio 8736 County Galway. The ESB requires to construct one double wood poleset structure on the lands, from which three continuous wires will be suspended by insulators, with two earth wires located on the top of the structure. 2.3 On 6th May, 2010 statutory wayleave notices pursuant to s. 53 of the Act of 1927 were served on Patrick Commins, the father of the defendant, who was then the registered owner of the lands registered on Folio 8736 and on the defendant. The defendant became registered as full owner of the lands registered on Folio 8736 in succession to his father on 26th November, 2010. 2.4 Unfortunately, due to human error, at the pre-planning application stage in 2004 the lands registered on Folio 8736 were mapped as being the property of an adjoining landowner and that had a number of consequences. One was that the defendant’s predecessor, Patrick Commins, was not identified as a person with an interest in land or structure affected by the proposed development on the application for planning permission. Another was that the adjoining landowner was incorrectly served with a wayleave notice on 13th October, 2009 in the belief that she was the owner of the lands registered on Folio 8736, which, in fact, at the time were owned by Patrick Commins. In consequence, on 3rd March, 2010 the ESB entered on the lands registered on Folio 8736 to advance the construction of the Dalton-Galway loop line without having first served a wayleave notice on the owner of the lands. A stone wall was knocked down on the boundary, but that has since been reinstated from the adjoining landowner’s property. It is acknowledged that the ESB trespassed on the defendant’s property and an apology has been tendered to the defendant for the trespass. As regards the historic trespass, the position of the plaintiffs is that any damage occasioned to the lands by virtue of the trespass was fully reinstated at the time. However, it is acknowledged that, apart from his entitlement to compensation pursuant to the provisions of the Acquisition of Land (Assessment of Compensation) Act 1919 pursuant to the wayleave notice served on him in May 2010, the defendant, if he wishes, may take proceedings in the civil courts against the plaintiffs for damages for trespass.
3. The bases of the defendant’s opposition to entry on the lands 3.2 However, counsel for the defendant recognised that, having regard to the decision of the High Court (Clarke J.) in ESB v. Burke [2006] IEHC 214, which was followed by this Court in ESB v. Roddy [2010] IEHC 158, it is not open to the defendant to question the validity of the planning permission granted by An Bord Pleanála or the extension thereof in these inter partes proceedings. To do so, the defendant would have to proceed by way of application for leave to apply for judicial review in accordance with subs. (2) of s. 50 of the Planning and Development Act 2000 (the Act of 2000), as substituted by s. 13 of the Planning and Development (Strategic Infrastructure) Act 2006, within the period of eight weeks prescribed in subs. (6) of s. 50 or such extended period as might be allowed by the Court in accordance with subs. (8) of s. 50. Therefore, the issue of the validity of the planning permission and the extension as a bar to granting the plaintiffs the relief they seek was not pursued on this application, although the possibility of the defendant seeking relief under the Act of 2000 was not ruled out. 3.3 The consequence of the defendant not pursuing the planning point is the recognition by the defendant that ESB is entitled to orders in the terms sought by it. 3.4 The defendant maintained his objection to interlocutory relief being granted to EirGrid, however, on the basis that EirGrid does not have statutory power to enter on the defendant’s lands. Whether that contention is correct or not is the core issue on this application.
4. EirGrid’s entitlement to relief: the submissions
4.2 It was confirmed to the Court by counsel for the plaintiffs that notwithstanding that the defendant was not objecting to interlocutory relief being granted to the ESB, that would not solve the problem and that it is necessary for EirGrid to be granted the interlocutory relief it seeks. 4.3 I propose now outlining the statutory provisions and the regulations on which EirGrid relies. 4.4 Section 20(4) of the Act of 1927 provides:
4.5 Regulation 8(2) of the Regulations, insofar as is relevant for present purposes provides:
(a) … (b) section … 20, … of the [Act of 1927], (c) … (d) … (e) … (f) … which is necessary for the discharge of the transmission system operator’s functions under these Regulations shall, to that extent, be regarded as a function of the transmission system operator and not of the Board, other than where it is also necessary for the Board to discharge its functions as transmission system owner in which case that function shall be a function of the Board and the transmission system operator.”
(ii) “function” is defined as including a power and a duty. 4.6 While reference was made in the legal submissions of counsel for the plaintiffs to an infrastructure agreement between ESB and EirGrid, which deals with the distribution of functions between them, that agreement is not before the Court and no reliance can be placed on it. 4.7 Counsel for the defendant submitted that the functions given to EirGrid in the Regulations could not have been envisaged by s. 20(4) of the Act of 1927 when it was enacted. It was pointed out that Regulation 8(2) does not transfer any function under s. 53 of the Act of 1927 on EirGrid. It was submitted that s. 20(4) does not cover what EirGrid intends to do on the ground; that the functions conferred on EirGrid do not include entry on the land of the defendant as a right. The right claimed by EirGrid is an interference with a constitutional right, presumably, the right to property and such a right must be expressly conferred by legislation, it was submitted on behalf of the defendant.
5. Conclusions 5.2 I am satisfied that the plaintiffs have also satisfied the other criteria for the grant of an interlocutory injunction, namely, that damages would not be an adequate remedy for the plaintiffs if an injunction were refused and the balance of convenience favours the grant of an injunction. In fact, no issue was taken by counsel for the defendant in relation to the case made out by the plaintiffs’ deponents in relation to both of those issues.
6. Order
|