1. By
a Notice of Motion dated the 15th of June 1999, the Notice Party (hereinafter
referred to as “S.G.S.”) seeks to have these Judicial Review
proceedings struck out
in
limine
due to the applicant’s failure to comply with the three month time limit
prescribed in Order 84 A RSC 1986 or in the alternative due to the
applicant’s inordinate and inexcusable delay in instituting these
proceedings. These Judicial Review proceedings were initiated following on the
respondents decision to award a contract to S.G.S. for the establishment and
operation of a system for testing private cars in Ireland. The applicant
(hereinafter referred to as “Dekra”), was an unsuccessful tenderer
for this contract and had been informed by the respondent that it was ranked
second to S.G.S. on the criteria set out in the invitation to tender.
2. Dekra
is a joint venture vehicle of Dekra International S.A. C.I.E. and the Society
of the Irish Motor Industry (“S.I.M.I.”) and was established to
seek the National Car Testing contract. It was one of the parties that
submitted a request for qualification to the respondent but did not succeed in
winning the contract. The respondent awarded the contract to S.G.S. and
supports S.G.S. in this Motion. S.G.S. also submitted a request for
qualification to the respondent and was successful in winning the contract.
S.G.S. is the moving party in this Motion.
3. E.U.
Directive No. 96/96 O.J. No. L46, dated 17th of February 1996 requires Member
States of the Union to introduce a system of periodic testing of the road
worthiness of motor vehicles. In compliance with this Directive on the 31st of
March 1998, the Irish Government launched the tendering process with the
publication both in the Irish National Newspapers and in the Official Journal
of the European Communities of a notice relating to the award of a contract to
establish and operate such a system. On the 7th of July 1998, the applicant
was one of the five undertakings invited by the respondent to submit tenders.
This invitation, which stated that the target date for the award of the
contract was the 11th of December 1998 was accepted by Dekra before the
deadline of the 27th of September 1998.
4. On
the 23rd of November 1998, following the submission of a report to the
Minister, the respondent contends that a decision was made to award the
contract to S.G.S.. The following day the 24th of November 1998, Dekra and the
other unsuccessful tenderers were informed both verbally and in writing that
“subject to contract” the tender of S.G.S. would be accepted. On
the 8th of December 1998, a “debriefing” meeting was held between
the representatives of Dekra and the respondent. On the 14th of December 1998,
the respondent informed Dekra that the formal announcement of the award of the
contract would take place the following day. Having learned from other sources
that S.G.S.’s proposed re-test fee was substantially in excess of its
own, Dekra through its solicitor wrote to the respondents raising this issue
inter
alia
.
Not being satisfied with the response of the respondent Dekra in another
letter of the same date put the respondent on notice of its intention to seek
injunctive relief unless the respondent refrained from awarding the contract to
S.G.S.. A further meeting was held that evening between the representatives of
Dekra and the respondent and it was agreed between these parties to meet again
in order to provide a more comprehensive debriefing to Dekra. However the
respondent subsequently by letter of the 5th of January 1999 informed Dekra
that it did not consider further discussions on the subject appropriate.
5. On
the 15th of December 1998, the award of the contract to S.G.S. was announced at
a public ceremony and was signed by the respondent and a representative of
S.G.S. Between then and the institution of these proceedings on the 25th of
March 1999 there was an exchange of a number of letters between Dekra and the
respondent. In this correspondence Dekra sought reasons for the
respondent’s decision and clarification on a number of issues. Dekra
contends that the responses received from the respondent were inadequate and
did not deal with many of the queries raised.
8. On
the first of these issues namely the date from which time runs S.G.S. make the
following submissions:-
9. S.G.S.
submitted that on any view of when time began to run, the time limits
stipulated in Order 84(A) Rule 4 RSC 1986 had not been complied with by Dekra.
10. S.G.S.
submits that the obligation of Order 84(a) is to apply “at the earliest
opportunity” and that this obligation arises independently of the three
month time limit. S.G.S. submits that Dekra had such an opportunity in
December 1998 but for reasons which have not been adequately explained this
opportunity was not availed of and hence Dekra failed to comply with the
requirement in Order 84(a) Rule 4 to make the review application “at the
earliest opportunity”.
11. The
respondent fully supported the submissions of S.G.S. and made the following
additional submissions:-
12. The
respondent points to the fact that upon the signing of the contract that S.G.S.
would have acquired rights and obligations and undertaken investment and
expenditure which would have been well known to Dekra and in delaying
instituting proceedings Dekra created a situation in which S.G.S. potentially
acted to its detriment in perhaps incurring great losses.
13. The
respondent submits that there are no constitutional issues arising which would
justify an extension of time and it submits that the delay on the part of Dekra
in initiating the proceedings was in all the circumstances unconscionable and
hence there is no good reason to extend the time.
14. The
respondent therefore submits that there was no ambiguity as to the date of the
decision to award the contract, the date of its signing or the provisions for
its implementation.
15. The
respondent submits that in commencing the review procedure by a letter of the
14th of December 1998 threatening legal proceedings yet failing to
“prosecute” the action for an excess of three months is an abuse of
process. The respondent submits that this is especially so having regard to
the applicant’s knowledge at all material times of the date of the
decision to award the contract, of his rights and remedies and of the
inevitable resulting prejudice to S.G.S. and the respondent. As the tardy
prosecution induced the respondent and S.G.S. to act to their detriment the
court is asked that the applicant do not benefit from such abuse of process and
for this reason alone the proceedings should be dismissed
in
limine
.
18. Dekra
submits that S.G.S. has no standing to make the present application as no
relief is being sought against it and as a consequence these proceedings cannot
cause it to suffer any injury or prejudice. S.G.S. has no interest which a
court could recognise which is injured or affected by these proceedings.
19. Moreover
the applicant relies on the dicta of O’Higgins C. J. in
Norris
v. The Attorney General
[1984]
IR
36, 58 for the purpose of submitting that S.G.S. is relying on a
jus
tertii
as
it seeks to rely on the rights of the respondent.
21. Dekra
accepted that the date of the award of the contract was the 15th December 1998
and for the purposes of Order 84 A Rule 4 that time began to run from the 15th
December 1998 and thus the three months expired by the 15th March 1999. On
this basis Dekra contends that the delay was only of ten days duration. Even
if the earlier date contended for by S.G.S. and the respondent were to be
accepted as the date upon which the grounds for the application arose the delay
was still only one month and one day.
23. Dekra
admitted that there were a number of over-riding considerations
which
should govern the exercise of the court’s discretion as follows:-
24. Dekra
raised this issue contending that S.G.S. have no
locus
standi
to bring the Motion seeking the striking out of the proceedings
in
limine
,
on the grounds that no relief is sought in the proceedings against S.G.S. and
having regard to the fact that Dekra seek only damages and not the setting
aside of the award of the contract, the proceedings do not threaten any
prejudice to S.G.S..
25. S.G.S.
say that in order to get damages Dekra must prove that the award of the
contract was illegal and obtain a declaration from the court to that effect.
They say the granting of such a relief would place in jeopardy the contractual
arrangements between S.G.S. and the respondents, perhaps rendering that
contract unenforceable.
26. Whether
or not the effect of such a declaration would go so far as to render the
contract between the respondents and S.G.S. unenforceable is not a question
which I have to decide on this Motion. I am satisfied however, that whatever
be the ultimate legal effect of such a declaration on that contract, that a
pursuit of such a declaration in these proceedings, and if it were obtained
would undoubtedly have in the words of Buxton L.J. in the
Matra
case “an unsettling and disruptive effect on that process”. It
would seem to me that at the very least such a declaration would give rise to
uncertainty as to the status of the contract and the obligations thereunder of
the parties, and would inevitably lead to damage to public confidence in the
car testing system. I am of the view that these would be real prejudices to
both S.G.S. and the respondents and hence in my view, S.G.S. have a real
interest in the outcome of these proceedings and have in my view a
locus
standi
to bring this Motion.
27. A
number of issues were raised concerning the construction of various parts of
this rule which reads as follows:-
28. The
respondents submitted that where the “earliest opportunity”
occurred within the three months period, that the rule does not permit or
create a jurisdiction to extend the three month time limit. Conversely, they
said it was only when the earliest opportunity arose outside of the three month
time limit that the court could extend that time limit.
29. I
cannot agree with this submission. It would seem to me that the phrase
“unless the court considers that there is good reason for extending such
period”, as it comes after the conjoined events, namely, at the earliest
opportunity and within three months, and there being no distinction made
between them, must in my view be construed as including both of these
eventualities. The rule seems designed to confer upon the court a discretion
to extend time. If the respondents submission were correct there would in
effect be no discretion; as where the “earliest opportunity”
occurred within the three months, the time period could not be extended, and
where the “earliest opportunity” occurred outside of the three
month period an extension of time would be inevitable. Accordingly therefore I
am of the view that the rule permits an extension of time whether or not the
“earliest opportunity” occurs within or outside the three month
time limit.
30. Dekra
submitted that the “earliest opportunity” would have to be
construed as only arising after the notification to the contracting authority
of the infringement alleged and of its intention to seek a review and the
response on the contracting authority thereto. In this case Dekra, by a letter
of the 14th December 1998, gave the notification required and the respondent
gave his response to that notification also in a letter of the 14th December
1998. Thus Dekra were in a position to comply with Order 84 A Rule 3 from the
15th December 1998 onwards, and hence insofar as their obligation under this
rule could have effected the “earliest opportunity”, their
obligation under Order 84 A Rule 3 could not have postponed the “earliest
opportunity” past the 15th December 1998 or within a day or two later as
may have been necessary in order to prepare the necessary papers for the
purposes of the application.
31. S.G.S.
and the respondent contend that time began to run from the 24th November 1998
when Dekra were notified both verbally and by letter that a decision to award
the contract to S.G.S. had been made. Dekra concedes that the contract was
awarded on the 15th December 1998 and that therefore grounds for the
application existed from that date and hence the three month time limit ran
from that date. They contend that because of the use of the phrase
“subject to contract” in the letter of the 24th November 1998 that
it was reasonable for them to take the view that a final or firm decision had
not been made to award the contract to S.G.S. at that time.
32. Order
84 A Rule 4 deals with two stages of the process of the awarding of a public
contract. The first is the “decision to award” and the second is
the “award of a public contract”. The facts as deposed on
Affidavit convince me that by the 23rd November 1998 the respondents had made a
“decision to award” the contract to S.G.S.. There is no doubt that
they communicated their decision in that regard to Dekra and other unsuccessful
tenderers both verbally and by the letter of the 24th November 1998. It seems
to me that the terms of the letter are quite clear and unequivocally convey the
fact that a decision had been made to give the contract to S.G.S.. While I
would accept that the inclusion of the phrase “subject to contract”
may have given rise to some reflection as to what it precisely meant in the
context in which it was used, its inclusion, in this letter does not in my
view, at all diminish the clear intent expressed in the letter namely to award
the contract to S.G.S. and does not negate the knowledge that a decision to
that effect had been made by the respondent.
33. Hence
I reject Dekra’s contention that it was reasonable for them to understand
this phrase as a meaning that no final decision to award the contract had been
made. It would seem to me that the most obvious meaning of the phrase in the
context in which it was used was, that the decision to award, was subject only
to the formal execution of the contract itself, in the light of the fact that
as Dekra points out, there were no terms of the contract which were opened to
negotiation. While it might very well be the case that in that context the
phrase “subject to contract” could be equated as it was submitted
by Dekra with “the existence of the contract being denied”, that of
course could not amount to a negation of the facts that “the decision to
award” the contract had been made. Thus while the phrase “subject
to contract” could be said to have conveyed to Dekra that the contract
was not yet formally awarded to S.G.S., it could not have conveyed to them an
understanding that a decision to award the contract to S.G.S. had not been
made. However I would accept that Dekra did not know of grounds for
dissatisfaction with that decision until some time later. Between then and the
14th of December, they learned, of the S.G.S.’s re-test fee, from
“other sources”. Thus it can be said that notwithstanding the fact
that “grounds for the application first arose” on 24th November
1998, that the “earliest opportunity” to apply for review occurred
later.
34. I
am therefore of the view that time for the purposes of Order 84 A Rule 4, ran
from the 24th November 1998. Thus when Dekra initiated these proceedings on
the 25th March 1993 they were one month and one day outside of the three month
time limit.
35. It
is clear from Directive 89/665/E.C. and, indeed, from Order 84 A Rule 4 that no
distinction is made between claims for damages or other reliefs such as
suspension or the setting aside of the award, and that being so, I agree with
the following passage from the judgment of Buxton L.J. in the case of
Matra
Communication v. Home Office
(1999) 3 All E.R. at 570:-
36. Were
it the case that a different time limit were to apply in respect of a damages
claim, the question would then arise as to what that time limit was, there
clearly being no express provision for it in either the Directive or Order 84
A. It would seem to me that a differentiation in the treatment of damages as
distinct from other reliefs sought, arises not in the context of the time
limit, but in the context of whether or not the courts discretion to extend the
time limit should be exercised in favour of an extension.
37. Both
S.G.S. and the respondent rely upon a case of
O’Donnell
v. Dun Laoghaire Corporation
(1991) I.L.R.M. 301 and say that Dekra, in order to obtain an extension of the
time limit must both explain and justify the delay and that the test in this
regard is an objective one.
38. Dekra
submits that in exercising its discretion, the court must have regard to the
well known dictum of McCarthy J. in the case
O’Flynn
v. The Midwestern Health Board,
quoted above and also that the court should be guided by the principles set out
in the English case of
Kaymed
(Medical) and Industrial Equipment Limited v. Forest Health Care NHS Trust.
39. It
would seem to me that there are no irreconcilable differences between the
approaches taken in these various cases. There is a primary onus on Dekra who
seeks an extension of the time limit to demonstrate on an objective basis that
there is an explanation for the delay and a justifiable reason for it. Of
relevance to a conclusion as to whether or not there is such an explanation and
such a justifiable reason are the factors set out in the
Kaymed
case. The respondent submits and I agree with him in this regard, that a
factor which must be taken into account is the public interest. This was
clearly envisaged by Costello J., as he then was, in the
O’Donnell
case. However, it would seem, to me that applying the dictum of McCarthy J. in
the
O’Flynn
case must result in tilting the balance in favour of extension of time where
that extension of time does not prejudice either the respondent or third parties.
40. Dekra
contend that the fact that the letter informing him of the decision to award
the contract was expressed to be “subject to contract” led them to
believe that a final decision to award a contract had not yet been made.
Although aware of the public ceremony on the 15th December, it was their belief
that this was merely for the purpose of announcing the award of the contract
and not the execution of the contract and they contend that they were unaware
of the execution of the contract and believed that it would not take place
until January 1999. They say that in the days following the 8th December 1998
when a “debriefing” meeting took place, they learned from
“other sources” that S.G.S.’s re-test fee was substantially
in excess of Dekras. As a consequence of this Dekra’s Solicitors Messrs.
Lee McEvoy wrote to the respondents on the 14th December 1998 raising
Dekra’s concerns in relation to the level of re-test fees. Dekra contend
that following upon a further lengthy meeting on the 14th December 1998 it was
agreed between Dekra and the respondents that a further meeting would take
place on the 12th January where the matters concerning Dekra and in particular
the question of the re-test fees would be fully explored. Dekra say that the
respondent reneged on his promise to attend this meeting in his letter of the
5th January 1999. Dekra say that in their letter to the respondents of the
24th February 1999 they raise the question of re-test fees and other matters
including the location of test centres and the issue of bias or conflict of
interest arising out of the engagement of Messrs. Coopers & Lybrand as
consultant to the respondent in relation to the tendering procedure. They say
that their specific queries raised in this letter were not addressed in the
reply of the respondent dated the 11th March 1999.
41. Dekra
contended that it was reasonable for them to seek answers to their queries
before launching the proceedings and when it was apparent that their endeavours
in this regard were not going to be successful following the letter of the 11th
March 1999, they promptly thereafter commenced the proceedings. They say that
as a matter of principle and public policy, litigants should not be forced to
issue a writ or otherwise commence proceedings without first taking steps to
establish that the proceedings are warranted. Specifically they say that they
were entitled to pursue their enquiries with the respondents as there was
always the prospect that there might have been a reasonable and convincing
explanation as to why the tender of S.G.S. was preferred, and in which
circumstance proceedings would not be warranted, and the expense thereof could
be avoided.
42. Both
S.G.S. and the respondent in contending that Dekra have not offered either a
reasonable explanation or a justifiable reason for the delay, point to the fact
that they were informed of the decision to award the contract on the 24th
November, by the 14th November as a result of the debriefing meeting on the 8th
December and their own enquiries, they were aware of the three issues which
caused them concern, namely the level of the re-test fee proposed by S.G.S.,
the conflict of interest issue involving Coopers & Lybrand, and the
location of the test centres proposed by S.G.S.. They say that they were
informed of the ceremony for the execution of the contract and invited to
attend and they say that as a result of what transpired at that ceremony
together with the press releases issued and the attendant publicity about it in
the media on the 16th December 1998 that Dekra were fully aware of the issues
which are subject matter of the substantive proceedings herein. They point to
the correspondence of the 14th December 1998 where they raise these concerns
and in particular the re-test issue and in which they give the notification as
required by the relevant E.U. Directive of their intention to seek injunctive
and other relief. They query as to why having taken that step and having
regard to the knowledge which they had at the time, they did not promptly, then
institute the proceedings and they say that no reasonable explanation has been
advanced for this failure nor has there been any justification for the delay in
initiating the proceedings up to the 25th March 1999.
43. In
addition, the respondent contends that Dekra, in its Affidavits and in
particular its statement grounding the proceedings and Affidavit of
Verification have failed to make a full disclosure and indeed, that the
statements and averments made in these documents are materially deficient,
misleading and in breach of the principle of good faith and designed to
obfuscate the facts and misled the court as to its true knowledge concerning
the date of the decision to award the contract to S.G.S.
44. For
the reasons already given, I do not accept that their reliance on the phrase
“subject to contract” is an acceptable explanation of any delay
from the 24th September 1998 to the 15th December 1998. By the 16th December
1998 in my view, Dekra were aware of the three issues which became of concern
to them, namely the re-test fee, the location of tests centres and the conflict
of interest issue.
45. I
would be prepared to hold that the issues which were of concern to Dekra were
complex in particular the issue of the re-test fees and that they may indeed
have been baffled by the appellant discrepancy between the proposed re-test fee
of S.G.S. and their own proposed re-test fee and that they strove for an
explanation of this. To fully understand the difference between the two, I
would readily be prepared to accept, would involve an exploration of the
unlying data relevant to the concepts of variable cost and profit. Clearly
discussion took place on these issues in the debriefing meeting of the 8th
December 1998 and in the further meeting on the evening of the 14th December
1998 but, I would infer from the fact that a further meeting was arranged for
the 12th January, that the parties involved in that meeting did not arrive at
any kind of agreed conclusion or outcome.
46. The
fact that Dekra did not initiate these proceedings pending the meeting on the
12th January 1999 is not surprising and I am inclined to view that their
explanation of delay up to the point at which they were notified of the
cancellation of that meeting is reasonable and justifiable. However, nothing
was done from the receipt by them of notification of the cancellation of that
meeting until their letter of the 24th February 1999, a full six weeks. There
is no explanation whatsoever offered of this six week delay, a delay which
formed a very significant part of the period of three months in Order 84 A Rule
4. At that point, namely 24th February 1999, they re-engaged in the same
enquiries but obviously with greater elaboration. Having regard to the fact
that the respondents had cancelled the meeting on the 5th January, they thereby
intimated an end so far as they were concerned, to the discursive process
related to the outcome of the tendering procedure.
47. In
my view having regard to the essential urgency which was undoubtedly required
having regard to the terms of the E.U. Directive 89/665 and Order 84 A Rule 4
the recommencement of correspondence of this kind on the 24th February 1999 was
not justified.
48. Having
regard to the foregoing I am of opinion that the “earliest
opportunity” for the purposes of Order 84 A Rule 4 occurred in the week
or so after the cancellation or the receipt by Dekra of notice of the
cancellation of the meeting of the 12th January 1999.
49. While
I would readily agree with Dekra’s submission that in general as a matter
of public policy, litigants should not be forced to issue proceedings before
they have a reasonable opportunity to satisfy themselves that the proceedings
are warranted, having regard to the cancellation of the meeting on the 12th
January 1999, any belief that they may have had that they would quickly reach a
full understanding of the problem and fully inform their conclusion as to
whether proceedings were warranted, must have been shattered by the
cancellation of that meeting, leaving them under no doubt but that proceedings
would be necessary if they were to progress their complaint.
50. The
statement of Dekra grounding the proceedings together with the Affidavit of
Verification could be said to have the appearance of a lack of candour,
particularly in the light of the contents of the letter of the 14th December
1998 from Lee McEvoy Solicitors for Dekra where they say “we would be
very grateful if you would respond to us in relation to this concern prior to
the formal execution of the contract on Tuesday”.
51. It
was submitted on behalf of Dekra that whatever deficiencies were there, they
could not and did not mislead the court in the sense of getting the court to do
something it might otherwise not have done because there was no application for
leave and no application for interim relief. Undoubtedly this is so, but
nevertheless the grounding statement and verifying Affidavit present an unhappy
incompleteness. However without the benefit of the full hearing I would not be
prepared to allow the exercise of my discretion on the issue raised in this
Motion be swayed against Dekra on this ground alone.
52. Having
regard to the foregoing, in my opinion, both the respondent and Dekra
contributed to the delay up to the cancellation of the meeting on the 12th
January 1999, thereafter the delay was entirely the responsibility of Dekra.
53. Both
the respondent and S.G.S. claim that they are prejudiced by Dekra’s delay
in instituting these proceedings. Both say that notwithstanding the fact that
Dekra does not seek to set aside the contract between them but merely seeks
damages, that nonetheless in order to obtain damages Dekra will have to obtain
a declaration to the effect that the award of the contract to S.G.S. was an
infringement of the relevant Directives and hence unlawful, and they point to
the declaratory reliefs that are claimed in the originating Notice of Motion of
Dekra. Both S.G.S. and the respondent contend that the granting of a relief of
this kind would, perhaps, render the contract between S.G.S. and the respondent
unenforceable or at the very least cast a doubt over the status of the contract
and that this uncertainty would be prejudicial to them both. They both also
point to the fact that S.G.S. has invested a great deal of money and other
resources in the setting up of the N.C.T.’s and that all of this may be
placed in jeopardy.
54. The
respondent additionally contends that he was prejudiced in been unable to
precede in timely fashion to conduct a competition to select the independent
supervisor for the implementation of the N.C.T.'s and as a result of the delay
ended up having to pay for two competitions, the first to engage a temporary
supervisor and the second a permanent supervisor.
55. It
is readily to be appreciated that the existence of these proceedings and the
reliefs claimed would have an “unsettling” effect on the
relationship between S.G.S. and the respondent. While it is the case that the
setting aside of their contract is not sought, nevertheless if Dekra succeeds
in obtaining the declarations that are sought in its originating Notice of
Motion and its statement grounding the proceedings, some doubt will be cast on
the contractual relations between S.G.S. and the respondent giving rise to
uncertainty. However, although it is unnecessary for me to decide the matter
in these proceedings, it would seem that there is a clear distinction to be
drawn between an infringement or illegality in the process whereby the contract
was awarded, and the existence and status of the contract itself. No issue at
all arises in these proceedings concerning the terms or obligations of the
contract between S.G.S. and the respondent and given that Dekra does not seek
to have it set aside, it is hard to see how it is in reality threatened by the
reliefs that are sought by Dekra in these proceedings.
56. Nevertheless
I could envisage a situation where if those reliefs sought by Dekra were
granted that there would be an undermining of public confidence in the N.C.T.'s
which could create a variety of problems for and pressures on both S.G.S. and
the respondent, emanating from a disgruntled public.
57. However,
that is a consequence which would flow from the nature of the reliefs
themselves, were they to be granted, and do not appear to me to flow from the
delay of Dekra in initiating these proceedings. The only relevance of that
delay to these consequences is that it is clearly in the interest of all
concerned including the public that proceedings of this kind involving claims
for the reliefs that are claimed in these proceedings should be deposed of as
speedily as possible. In this context it could be said that the delay on
Dekra’s part could make a marginal contribution to any prejudice in this
regard that S.G.S. and the respondent might suffer. However having regard to
the time involved in the prosecution of the proceedings to a final
determination I would be of the view that the contribution of Dekra’s
delay in initiating the proceedings is insignificant in terms of that
prejudice.
58. In
the light of the fact that the setting aside of the contract is not sought by
Dekra, it would seem to me that the undoubted fact that S.G.S. has invested
heavily both in terms of money and other resources in the setting up of the
N.C.T.'s is irrelevant.
59. Having
carefully considered the evidence on Affidavit concerning the delay in the
holding of the competitions for the independent supervisor, I am left
unconvinced that the delay on Dekras part in initiating these proceedings
should be blamed for the difficulties that the respondent encountered in
engaging the supervisor. From the 24th November 1998 the respondent had made a
decision to award the contract to S.G.S.. A full four months elapsed between
then and the initiation of these proceedings on the 25th March 1999. No
explanation is offered by the respondent as to why the competition to engage
the supervisor was not held in this period, when it is clear from the time
scale involved in holding such a competition, that it could easily have been
done within that period.
60. The
respondents say that they were deterred from holding the competition because of
ambiguity in the Notice of Motion, statement grounding the proceedings and
verifying Affidavit concerning the reliefs to be sought and that this was not
finally cleared up until the letter of the 25th June 1999 from Dekra stating
unequivocally that it did not seek the setting aside of the contract.
61. It
is quite clear that the Notice of Motion dated the 15th March 1999 does not
seek an Order setting aside the contract or suspending it. In the Statement of
Grounds likewise in the paragraph headed “Relief Sought”, a setting
aside is not sought.
62. In
the paragraph headed “Relief Sought” at paragraph (x) (g) at sub
paragraph 6 the following is stated:-
64. While
I would except that one can perceive an element of ambiguity in these
documents relative to the relief claimed, it would seem to me that the
overwhelming thrust or sense of the documents indicates to the contrary and I
must confess to some surprise that the respondent would at the end of March or
during April or May 1999 been deterred from an obviously necessary course,
namely the holding of the appropriate competition to engage an independent
supervisor, because of this alleged ambiguity.
65. On
balance therefore, I am left unconvinced from the evidence that either the
delay of Dekra or any alleged ambiguity in relation to a reliefs claimed in its
Notice of Motion could be fairly blamed for whatever difficulties the
respondent had in preceding with that competition up to June 1999.
66. Dekra
contends that if these proceedings are struck out
in
limine
as
is sought, a grave injustice will be done to it because, what it contends is a
valid claim will be defeated without ever being heard and that nothing that is
advanced by either S.G.S. or the respondent as prejudice to them could be said
in any serious way to outweigh the gross prejudice to it, that would result
from these proceedings being struck out at this stage.
67. The
respondents submit that the court must have regard to the public interest in
exercising its discretion. The particular public interest that is advanced for
consideration is the orderly administration of public contracts and tenders for
public contracts. The respondents submit that were it the case that
applications for review of awards of public contract were to be entertained
outside the three month time limit, that this would lead to an administrative
nightmare for various government departments and public bodies charged with the
carrying out of these contracts, and that it would lead to great legal
uncertainty affecting a great many parties if the status of these contracts was
to be subject to uncertainty over a protracted period of time. In this regard
the respondents point out that at any time there are several hundred of these
contracts on going and that extensions of the three month time limits in
relation to reviews of them would place an impossible burden on government
departments and other public bodies.
68.
I would readily accept that if the setting aside relief were to be sought in
reviews of the decision to award or the award of public contracts initiated
outside the three month limit, that this clearly could lead to kind of
“administrative nightmare”
that
the respondents apprehend. Clearly in that situation a great many valuable
public projects could be held up for lengthy periods of time and this would
cause considerable prejudice to a great many people namely the contractors and
all of the professionals involved, the departments of the State or other public
bodies charged with dealing with these matters and last but not least, the
publics enjoyment of the benefit of these contracts would be delayed for the
duration of the completion of the litigation.
69. Where
however, the setting aside of one of these contracts is not sought as in this
case, an entirely different situation pertains. In this circumstance, all the
public body or in this case the respondent is faced with is the task of
defending the litigation. The project itself can and indeed has gone ahead.
In this regard the litigation is in reality no different in terms of prejudice
to the respondents than any other of the myriad proceedings that are directed
against the state in general and this respondent in particular, on a daily
basis and for which the State has ample resources, save that there is this
difference, that under the relevant Directive 89/665 and under Order 84 A Rule
4 there is undoubtedly enjoined upon an Applicant for a review of the decision
to award or the award of a public contract an onerous obligation to move with
urgency and speed. On balance I do not see these proceedings as imposing any
unusual or oppressive burden on the respondent.
70. The
respondents also made the case that they are anxious to comply with their
obligations under E.U. Law to implement the car testing system and point to the
fact that they have heretofore been in breach of that obligation. This is
rightly a concern of the respondent. The fact that Dekra do not seek the
setting aside of the contract or a suspension of it means that these
proceedings do not inhibit the respondent in proceeding to effect compliance
with its obligations under E.U. Law. In fact the car testing system has been
set up since January of the year 2000 without any apparent effect from these
proceedings.
71. I
have come to the conclusion that neither S.G.S. nor the respondent will suffer
a significant prejudice that can be fairly attributable to the delay on the
part of Dekra. Such prejudice as is decernable is of a potential or indefinite
kind and would be the result of the proceedings themselves and the relief
sought therein rather than the result of any delay on the part of Dekra in
initiating these proceedings.
72. On
the other hand if these proceedings are to be struck out now without been
heard, a grave injustice may be done to Dekra. Balancing that prejudice
against any potential prejudice to S.G.S. or the respondent, I have come to the
conclusion that the balance must lie in favour of Dekra. I am mindful of the
fact that Dekra have been in delay and as I have found earlier, have not
explained a significant portion of that delay. Nevertheless the relief sought
in this Motion by S.G.S. is of the most drastic kind and in my view is such
that should only be granted in the clearest of cases where the default is gross
or the prejudice caused by it is real and substantial and immediate. In this
case the delay is short in terms of time, the extension of time required a
matter of some one month. While urgency is clearly required in applications
for reviews of the decision to award or the award of a public contract,
nevertheless the conduct of these reviews are not a new departure in our
jurisprudence such that a wholly different approach to the question of delay
should be adopted. The courts are there to administer justice and only in the
most extreme case should a party be repelled from the seat of justice unheard.
No doubt the award of public contracts is a matter of great public importance
involving potentially very serious obligations on the part of the State and
where wrong doing occurs remedies which may place a heavy burden on the public
purse. Be that as it may, the validity or the relevance to these reviews of the
time honoured maxim
Fiat
Justitia
Ruat Coelum
remains
undiminished.
73. For
the foregoing reasons therefore, I have decided to exercise my discretion in
favour of extending the time limit in Order 84 A Rule 4 to the 26th March 1999.
In the light of this, it is unnecessary for me to express an opinion on
Dekra’s submission, that the three month time limit in Order 84 A Rule 4
is
ultra
vires
on the grounds that it offers the principle of equivalence. However, for the
sake of completeness and in deference to the very erudite submission made by
S.G.S. and Dekra on the topic I am prepared to say that, I am satisfied, that
there is no comparator in our domestic law, breach of statutory duty being far
to wide and diffuse to be a valid comparator. Hence, I would adopt the
reasoning of Buxton L.J. in the
Metra
case and conclude that Order 84 A Rule 4 does not fall foul of the principle of
equivalence.