1. The
Applicant in these proceedings is the First Named Notice Party in the title of
the matter. Originally known as Thesio Limited, it changed its name to
Dungarvan Energy Limited and the title of the proceedings were amended
accordingly. The Applicant in the proceedings, Collette O’Connell, is
the Respondent in this Application to strike out her proceedings seeking
Judicial Review of a decision of the Respondent.
2. It
was submitted on behalf of Collette O’Connell that Dungarvan Energy
Limited does not have a sufficient
locus
standi
to maintain this application. I disagree.
3. The
Respondent in the Judicial Review proceedings is the Environmental Protection
Agency and the matter in respect of which Orders are sought concerns the
granting by the Respondent on the 3rd January, 2001 of an Integrated Pollution
Control Licence under the Environmental Protection Agency Act, 1992, which
licence related to the development at Dungarvan on a former Agribusiness site
adjoining the Town of a one hundred megawatt Combined Cycle Gas Turbine
Electricity Generating Plant for which Dungarvan Energy Limited, on the 1st
September, 2000 received a Grant of Planning Permission from An Bord Pleanala,
consequent upon an Appeal to that Body by Collette O’Connell from a
decision of Dungarvan Urban District Council on the 28th November, 2000
granting planning permission.
4. The
Court was informed by Counsel for Dungarvan Energy Limited that IR£21
million has already been expended by that Company in acquiring the property,
launching this project, obtaining the necessary Grant of Planning Permission
and the necessary Integrated Pollution Control Licence and in carrying out such
site clearance works as were authorised by the Terms of the Planning
Permission. The Court was informed that time sensitive funding arrangements
had been made for the construction and commissioning of the proposed Plant
costing 78 million euro with ancillary works costing an additional IR£10
million. The Court was told that under agreements with the Department of
Public Enterprise, a supply of natural gas for the proposed plant had been
secured by Dungarvan Energy Limited but that this supply could be allocated
elsewhere if it was not taken up by September, 2002. In addition a Bond in the
sum of IR£5.3 million had been furnished by Dungarvan Energy Limited to
the Minister for Public Enterprise to secure a penalty of approximately
IR£30,000 per day in the event that the proposed plant was unable to
supply power to the National Electricity Grid by the 9th September, 2002. In
addition Counsel stated that the loss of revenue to Dungarvan Energy Limited if
start up was delayed would be in the region of 48,000 euro per day.
5. Counsel
for Dungarvan Energy Limited drew to the attention of the Court that these
facts were stated under oath by Mr. Alistair Jessop, a Director of Dungarvan
Energy Limited at paragraph 31 of an Affidavit sworn by him on the 29th
January, 2001 in proceedings taken by Collette O’Connell against
Dungarvan Energy Limited pursuant to the provisions of Section 27 of the Local
Government (Planning and Development) Act, 1976, as substituted by Section 19
(4), (g) of the Local Government (Planning and Development) Act, 1992. These
proceedings were determined substantially in favour of Collette O’Connell
by a judgment of the High Court, (Mr Justice Finnegan), given on the 28th
February, 2001.
6. In
my judgment, having regard to the decisions in
East
Donegal Co-operative Livestock Mart Limited -v- The Attorney General
(1970)
I.R. 317 and
O’Keeffe
-v- An Bord Pleanala
(1993)
1.I.R.39, on the foregoing assertions, Dungarvan Energy Limited, whose rights
would be very seriously affected by the avoidance of the Integrated Pollution
Control Licence must have a sufficient
locus
standi
to maintain this application, even though it has not been joined as a
Respondent in the proceedings as directed by the Supreme Court in the latter
case, (see p. 78 of the Judgment per Finlay CJ), and could and should have
applied itself to the Court to be added as such as a party, (p. 66/67 of the
same Judgment). It would in my view amount to a total denial of fairness and
justice to this company if it could not intervene in this manner
notwithstanding any procedural irregularity to protect its lawful interests and
if all it could do was to fretfully and anxiously await the outcome of the
issue between Collette O’Connell and the Environmental Protection Agency,
or try to prevail upon the Employment Protection Agency to make this
Application essentially on its behalf, which I am certain that Body, given its
statutory function would be entirely reluctant to do.
7. The
first basis upon which Dungarvan Energy Limited seeks an Order striking out the
Judicial Review proceedings is that the proceedings are statute barred having
regard to the provisions of Section 85 (8), of the Environmental Protection
Agency Act, 1992.
9. It
was contended on behalf of Dungarvan Energy Limited that an application for
Judicial Review is not
“instituted”
within the meaning of this subsection until after Leave to apply for Judicial
Review has first been granted and an application for Judicial Review made by
originating Notice of Motion or, if directed by the Court, by plenary summons.
The date upon which the decision was made to grant the Integrated Pollution
Control Licence in this case was the 3rd January, 2001. By Order of the High
Court (Mr Justice McKechnie) made on the 2nd March, 2001 Collette
O’Connell was granted leave to apply for Judicial Review with respect to
the granting of this licence. It is common case between the parties that an
application for Judicial Review as provided for by Order 84 Rule 22 of the
Rules of the Superior Courts, 1986, was not made within the period of two
months commencing on the 3rd January, 2001.
10. In
my judgment an application for Judicial Review is clearly a
“proceeding”
within the meaning of the Section 85 (8) of the Environmental Protection Agency
Act 1992, and accordingly must be instituted within the stipulated period of
two months. It was held by the High Court in the case of
NiEili
-v- The Environmental Protection Agency and Others
(1997)
2I.L.R.M.454 that the Court has no power to extend the time allowed by the
Section. I agree with the decision of Mr. Justice Kelly in that case.
11. In
my judgment an application for Judicial Review for the purpose of this
subsection is
“instituted
”
as soon as a motion
ex
parte
for leave to apply for Judicial Review is moved before the Court. The
interpretation contended for by Dungarvan Energy Limited would in my judgment
lead to the most extraordinary results. By Order 84 Rule 20 sub-rule 6 of the
Rules of the Superior Courts, 1986 it is provided that where the Court grants
leave to seek Judicial Review, it may impose such terms as to costs as it
thinks fit and may require an undertaking as to damages. By Order 84 Rule 20
sub-rule 7 of the Rules of the Superior Courts, 1986 it is provided that where
leave to apply for Judicial Review is granted then:-
12. Should
the Court refuse leave to seek Judicial Review, the Applicant has a right of
Appeal to the Supreme Court under Order 58 Rules 1 and 13 of the Rules of the
Superior Courts 1986. If the interpretation contended for by Dungarvan Energy
Limited is correct, then the Legislature in framing and enacting this Act must
be assumed to have decided to disregard not alone an application invoking the
power of the High Court but further, a possible application invoking the power
of the Supreme Court in determining the relevant date. Also, if an Applicant
should be successful in an Appeal to the Supreme Court from a refusal of leave
it would be an exercise in futility as the ensuing application for Judicial
Review would almost invariably be instituted out of time. I cannot accept that
this was the intention of the Legislature.
13. The
Environmental Protection Agency at, 1992, does not itself contain any
definition of the phrase,
“proceedings
are instituted
”
or of any word comprised in the phrase. The same is true of the Interpretation
Act, 1937. In the case of
Re:
Vernazza
(1960) 1.A.E.R.183 Wilmer, L.J., at page 191 referred to,
“the
almost impossible task of drawing an exact line between that which does and
that which does not amount to ‘instituting’ proceedings.”
In the case of in
Re:
Becker
(1975) 1.W.L.R., 842, Evleigh J., pointed out that the meaning of the word
“
proceedings”
may
vary depending on its context. In my judgment the same may be said of
“instituted”.
14. Looking
at the policy of the Environmental Protection Agency Act, 1992 and the possible
abuse which was sought to be remedied by Section 85 (8) of that Act, - the
proper protection of the Environment and the right of individuals and
organisations to be involved in that process but with a limitation placed upon
the time within which the validity of a licence or revised licence might be
challenged so as to give some measure of certainty to developers without
excluding objectors with a genuinely perceived and formulated grievance, - I
find nothing to indicate that the second stage of the procedure commencing on
the date of application for Judicial Review rather than the first stage
commencing on the date of application for leave to seek Judicial Review was
intended by the framers of the subsection. Indeed as the Courts have already
expressed some concern as to the shortness of an equivalent period in the
Planning Code, the further shortening of this period of 2 months which must
almost inevitably result if the application for leave to seek Judicial Review
is required to be made within that period would in my judgment render the
subsection constitutionally infirm and such a construction must be avoided if
an alternative construction is available which without doing violence to the
language of the subsection maintains its constitutional integrity.
15. The
second and alternative ground upon which Dungarvan Energy Limited seeks to
strike out these proceedings for Judicial Review is that Collette
O’Connell failed to make her application for Judicial Review
“promptly” as required by Order 84 Rule 21 (1) of the Rules of the
Superior Courts, 1986. This order provides that,
“an
application for leave to apply for Judicial Review shall be made
promptly......”.
This
requirement of promptness in seeking the comprehensive new remedy of Judicial
Review has always been an incident of the former prerogative remedies of
Certiorari, Mandamus and Prohibition. In my judgment Section 85(8) of the
Environmental Protection Agency Act, 1992, while imposing a non-expandable
upper time limit within which an application for leave to apply for Judicial
Review must be brought does not in any way suspend or lessen the requirement
that every application for leave to apply for Judicial Review must be made
promptly within that stipulated period.
16. The
Court in that case found that the delay of four months after the
Applicant’s legal advisers had been formally notified that another
candidate had been recommended for the position was
“excessive
and unreasonable”.
I think that it may be fairly inferred from the decision of Keane, J., (as he
then was) in
Director
of Public Prosecutions v. Johnson
(1988) I.L.R.M., 747 at 750 that a relatively short delay would not deprive an
Applicant of what has been described as,
“The
great remedy available to citizens”
,
and that the delay would have to be such as might be categorised as,
“substantial”
in all the circumstances of the particular case, one such circumstance being
the overall period of time allowed for the application.
17. In
the instant case the date when grounds for this application for Judicial Review
first arose was the 3rd January, 2001 when the decision was made by the
Environmental Protection Agency to grant the Integrated Pollution Control
Licence to Dungarvan Energy Limited. This is the decision which Collette
O’Connell contends is unlawful and
ultra
vires
the powers of that body as having been made without a prior Environmental
Assessment Study.
18. Collette
O’Connell is a citizen whose dwellinghouse is located approximately 100
metres from the proposed power station and whose property could be adversely
affected by emanations from that plant and who therefore has a sufficient
interest to maintain this application. She is acting on her own behalf and on
behalf of her husband Mr. Otteran O’Mahony and their four children and is
not acting on behalf of and so far as the Court has been made aware, does not
have the support of any group or organisation or association either local or
national. On the 12th October, 2000 Collette O’Connell lodged an
objection with the Environmental Protection Agency opposing the application of
Dungarvan Energy Limited for an Integrated Pollution Control Licence without a
prior Environmental Assessment Study.
19. It
was argued on behalf of Dungarvan Energy Limited that this was a very full and
comprehensive document and accordingly, there was no valid explanation or
excuse for her delay in seeking leave to apply for Judicial Review in
consequence of which the Court should not entertain her application which was
not made until the very last day of the statutory two month period of
limitation. They submit that given that Collette O’Connell must have
been fully aware at the very latest when she received the Affidavit of Alistair
Jessop sworn on the 29th January, 2001 in her proceedings pursuant to Section
27 of the Local Government (Planning and Development) Act, 1976 as substituted
by Section 19(4)(g) of the Local Government (Planning and Development) Act,
1992 of the time frame within which Dungarvan Energy Limited must have built
the power station and brought it into production and of the various substantial
penalties and losses which could be imposed and incurred should they fail to
meet those targets, the delay on her part until the 2nd March, 2001 in bringing
on her application for leave to apply for Judicial Review is excessive,
unreasonable and inexcusable.
20. In
answer Counsel for Collette O’Connell submitted that she acted with all
reasonable diligence and despatch having regard to the particular circumstances
of this case. Counsel submitted that in the days following Wednesday 3rd
January, 2001 Collette O’Connell had to consider her position and to
decide whether she would take the matter further. In order to do this she
sought and obtained access to the full Environmental Protection Agency file in
the matter which was not available until after the 3rd January, 2001. At this
vital juncture her attention to this matter was distracted because she became
aware that Dungarvan Energy Limited its agents and contractors appeared to be
carrying out work on the site in breach of the conditions attached to the Grant
of Planning Permission of 1st September, 2000. To be certain she had to
obtain access to and carefully consider the Planning Files of Dungarvan Urban
District Council. She then consulted her legal advisers in the matter. On
Monday 22nd January, 2001 by Motion ex parte she sought leave to apply for
Judicial Review against Dungarvan Urban District Council and by way of separate
proceedings sought interim relief against Dungarvan Energy Limited pursuant to
the provisions of Section 27 of the Local Government (Planning and Development)
Act, 1976 as substituted by Section 19(4)(g) of the Local Government (Planning
and Development) Act, 1992. On the 23rd January, 2001 she obtained from the
High Court (Mr. Justice O’Neill), a prohibitory interim order in the
Section 27 Proceedings and an Order granting her leave to apply for Judicial
Review. This Prohibitory Order was served on Dungarvan Energy Limited on the
24th January, 2001 but the work complained of continued notwithstanding. What
happened thereafter is best set out in summary form as follows:-
21. Collette
O’Connell alleged breaches by Dungarvan Energy Limited its agents and
contractors of conditions 3,4,6,9,10,11,12 and 13 of the Planning Permission.
Dungarvan Energy Limited denied these allegations and in addition put in issue
the
bona fides
and
motivation of Collette O’Connell by reference to a series of meetings and
agreements between the parties.
Collette
O’Connell replied in detail to these allegations. The result of all this
was a file of Motions, Affidavits and Exhibits five millimetres thick. The
matter came on for hearing before the High Court (Mr. Justice Finnegan), on
Wednesday, Thursday and Friday the 31st January, the 1st February and the 2nd
February, 2001. The Court reserved its decision and judgment was given on the
28th February, 2001. Collette O’Connell succeeded as regards most of her
claim and was awarded two days costs.
22.
In the absence of Affidavit evidence as to specific dates, I think it a fair
inference to be drawn from the Affidavits and the sequence of events therein
disclosed that it was sometime in the week preceding the 22nd January, 2001
that Collette O’Connell became aware of the apparent breaches by
Dungarvan Energy Limited, its agents and contractors of the conditions attached
to the Grant of Planning Permission, and having checked the Planning Files of
Dungarvan Urban District Council determined to take legal proceedings to
prevent such breaches. Prior to this there was a period of approximately a
week to twelve days during which she was considering her position and examining
the newly available complete file of the Environmental Protection Agency in
respect of the application for and the decision to grant the Integrated
Pollution Control Licence. This short period could not possibly amount to
excessive, substantial or unreasonable delay on her part.
23. In
my judgment any delay after this initial period at least until Monday 5th
February, 2001, being two days after the conclusion of the hearing of the
Section 27 Proceedings in the High Court before Mr. Justice Finnegan, was due
solely to the wrongful activities of Dungarvan Energy Limited, its agents and
contractors. In my judgment, it would be altogether unjust and unreasonable
that Dungarvan Energy Limited should benefit from its own breaches of the
Planning Permission which Collette O’Connell properly took legal
proceedings to prevent and which I am satisfied resulted in her being
distracted from and neglecting to prosecute an application to seek leave to
apply for Judicial Review of the decision of the Environmental Protection
Agency to grant a Integrated Pollution Control Licence in respect of the power
plant. Thereafter an overall period of 26 days, including 20 working days,
elapsed before Friday 2nd March, 2001 when the application for leave to apply
for Judicial Review was made to and granted by the High Court, (Mr. Justice
McKechnie).
24. At
paragraphs 3 and 4 of her Supplemental Affidavit sworn on the 11th May, 2001in
this Application Collette O’Connell deposes as follows:-
25. It
is deposed by Collette O’Connell at paragraph 8 of the Affidavit sworn by
her on the 30th January, 2001 in the Section 27 Proceedings that she possesses
a University Degree in Social Science and that her husband possesses a
University Degree in Electrical Engineering. I have read the Objection
submitted by Collette O’Connell on the 12th October 2000 in the
Environmental Protection Agency in opposition to the application of Dungarvan
Energy Limited for an Integrated Pollution Control Licence. While this is a
comprehensive and technically proficient document I cannot accept the
submission of Counsel for Dungarvan Energy Limited that there is in essence no
material difference between it and the Statement to Ground the Application for
leave to seek Judicial Review so that no proper or acceptable explanation for
the delay in the making of the Application for leave to apply for Judicial
Review has been advanced by Collette O’Connell upon whom the duty to
explain an excuse this seeming delay lies.
26. I
have considered the Statement of Grounds dated the 2nd March, 2001, and while
it naturally has echoes of the Objection which was submitted by Collette
O’Connell on the 12th October, 2000, I am satisfied that the former could
not in any sense be described as a mere repetition or transcription of the
latter but is a careful pleading raising a considerable number of apparently
serious issues to be determined by the Court. Even if it took essentially the
same form and raised no further issues than the Objection it must still be
regarded as an entirely different document with a wholly different significance
notwithstanding that the consideration of lawyers and the advice of experts
produced no material difference in form or content. From the original
Objection. It would be absurd to suggest that the time devoted by lawyers and
experts should be regarded as mere delay unless it resulted in a fundamental
departure from the matters addressed in the Objection.
27. I
accept that Collette O’Connell sought and obtained the advice of an
expert on issues relative to the environment before delivery of the Statement
of Grounds. While it would have been altogether more satisfactory if these
matters had been addressed fully by her in her Supplemental Affidavit sworn on
the 11th May, 2001, I accept the submission of her Counsel that in addition to
instructing Solicitors to act, it was necessary that Counsel with a competence
in this area of law, both national and european be retained and that such
Counsel when retained had to find time while attending to all his other
professional commitments to consider the case, attend consultations and settle
the Statement of Grounds bearing in mind that this could not thereafter be
expanded, and all within a period of 20 working days or less.
28. No
case was made to the Court that Dungarvan Energy Limited took any steps,
entered into any agreements or commitments or set in motion any plans on foot
of the decision of the Environmental Protection Agency on the 3rd January, 2001
to grant an Integrated Pollution Control Licence for the power plant of which
Collette O’Connell was aware or ought reasonably have foreseen. Indeed,
having regard to the purpose of Section 85(8) of the Environmental Protection
Agency Act, 1992, which both parties to the application accepted was the
elimination of unmeritorious and tardy challenges and the conferring of a
degree of certainty in these matters, any such course might be said to be
foolhardy. However, I wish to make it abundantly plain that I am not deciding
that it is necessary for a party in Judicial Review proceedings to establish
prejudice in order to succeed in an argument on delay. Prejudice is simply one
of the factors and no more which the Court takes into account in determining in
the circumstances of each individual case the reasonableness or otherwise of
the lapse of time before leave to apply for Judicial Review is sought.
29. I
am satisfied that Collette O’Connell has fully excused and explained any
seeming delay on her part in seeking leave to apply for Judicial Review. In
such circumstances it is not necessary for the Court to consider the question
of whether the two month time limit imposed by Section 85(8) of the
Environmental Protection Agency Act, 1992, is a breach of the Principle of the
Effectiveness in European Community Law, or whether the Court should seek a
Ruling of the Court of Justice under Article 234 of the Treaty establishing the
European Community. I wish to express my appreciation of the helpful and
incisive submissions on these questions by Counsel for Collette O’Connell
and Counsel for Dungarvan Energy Limited and the Solicitor for the second and
third named Notice Parties.
30. The
third basis upon which Dungarvan Energy Limited seeks to have the proceedings
struck out is on the assertion that they are frivolous and vexatious and
disclose no reasonable cause of action against Dungarvan Energy Limited or any
other party. This argument suffers from the infirmity that the cause of action
of Collette O’Connell is against the Environmental Protection Agency and
since that party has not made an application under Order 19 Rule 28 of the
Rules of the Superior Courts, 1986, or by reference to the inherent
jurisdiction of the Court, I greatly doubt whether Dungarvan Energy Limited can
make such an argument on their behalf. However, it is unnecessary to determine
this matter or to express an opinion as to whether a Notice for the purpose of
Order 84 Rule 20 is a
“pleading”
within Order 19 Rule 28 having regard to the provisions of Order 125 Rule 1 of
the Rules of the Superior Courts, 1986.
31. In
the words of Murphy J., (then of the High Court), in
Tassan
Din -v- Banco Ambrosiano Spa
.,
(1991) 1 I.R., 569 at 572,
“There
is no room for debate as to the approach which this Court should take in
dealing with an application of that nature.”
The learned Judge then cited the decisions in
Blair
-v- Crawford
(1906) 1 I.R.578 at 586 per, Palles C. B.;
Mulgrew
-v- O’Brien
(1953) N.I. 10 at 14 per Black, L. J., and
Barry
-v- Buckley
(1981) I.R. 306 at 308 per Costello, J.. I also consider that the decision in
Sun
Fat Chan -v- Osseus Limited
(1992) 1 I.R. 426 is relevant. These cases clearly establish that the Court
should exercise the utmost caution in depriving a party of the right to be
heard and should do so only where confident that the claim must inevitably
fail. In this case Collette O’Connell was by Order of the High Court
(Mr. Justice McKechnie), made on the 2nd March, 2001 granted leave to apply for
Judicial Review on 18 separate grounds which the Court clearly considered at
the very least to be stateable grounds. Unless there is evidence to satisfy me
that this Order was obtained by fraud, misrepresentation or material
nondisclosure this basis of challenge to the proceedings must fail. This leads
directly to the fourth and final ground upon which Dungarvan Energy Limited
seeks to have these proceedings struck out.
32. This
fourth ground asserts that the Order of the High Court made on the 3rd March,
2001 was obtained by material nondisclosure and additionally or alternatively
misrepresentation. It is submitted on behalf of Dungarvan Energy Limited that
Collette O’Connell failed it to disclose to the Court at the hearing of
the motion ex parte for liberty to apply for Judicial Review in which
circumstances there is an onus on the party applying to make full disclosure to
the Court of all relevant material, the challenge to the
bona
fides
of
her application by Dungarvan Energy Limited in the Section 27 Proceedings.
33. I
believe that I may accept what was offered by Senior Counsel for Collette
O’Connell, even in the absence of an Affidavit by the attending Solicitor
on that occasion, that his Junior offered to open to the Court at the hearing
of the Application all of the Affidavits sworn and filed in the Section 27
Proceedings but the Court did not require him so to do. Even if I should
proceed upon the basis that these matters were relevant I have to remain
cognisant of the fact that serious issue has been joined between Mr. Jessop and
Collette O’Connell on oath in lengthy Affidavits sworn by them in the
Section 27 Proceedings as to the events which occurred, the reasons why they
occurred, the manner in which they occurred, and the significance, (if any) to
be attached to them.
34. In
the circumstances, even if these matters and the Affidavits in which they are
set out had been fully opened to the Court in my judgment the Court would have
had no option but to entirely disregard them particularly in the context of an
application for leave to apply for Judicial Review where the Court is not
adjudicating on the merits of the particular application. I am making no
finding whatsoever as to any of these issues as to
bona
fides
but I do find that there was no material nondisclosure or misrepresentation on
the part of Collette O’Connell or her legal advisors in the course of her
application for leave to apply for Judicial Review in these proceedings.
35. The
final relief sought by Dungarvan Energy Limited in the Notice of Motion is an
Order requesting Collette O’Connell to provide what it terms a
“fortified” undertaking as to damages as a condition of being
permitted to continue these Judicial Review Proceedings.
36. Counsel
for Dungarvan Energy Limited relied upon the decision of Laffoy, J., in the
case of
Broadnet
Ireland Limited, Applicant -v- Office of the Director of Telecommunications
Regulation, Respondent and by Order, several Notice Parties
,
(2000)
2.I.L.R.M. 241, and the decision of Finnegan, J. in
Seery,
Applicants -v- An Bord Pleanala,
Respondent
and several Notice Parties
(unreported: 25/1/2001: written Judgment available).
37. I
have some very considerable reservations as to the power of the Court to make
any form of Order, either against or in favour of a party who is on notice of
proceedings but who is not a Respondent in the proceedings, and this includes
an Order as to costs and also includes an Order that an applicant should give
an undertaking to pay damages to such a mere Notice Party for any possible loss
sustained by such Notice Party should the Applicant not be successful in the
proceedings against the Respondent.
38. However
no argument was addressed to the Court that the decisions upon which Counsel
for Dungarvan Energy Limited relied were incorrectly decided and ought not to
be followed so far as they relate to Notice Parties. Collette O’Connell
through her Counsel expressed a willingness to give an undertaking as to
damages if the Court considered it appropriate. Arguments were confined to the
issue of whether there were public law considerations in the case which should
cause the Court to exercise its discretion in favour of not requiring an
undertaking as to damages and to the issue of whether, if an undertaking was
sought by the Court it ought to be in the form of a, “fortified”
undertaking.
39. Collette
O’Connell sought and was granted a stay on the implementation of any
provision of the Integrated Pollution Control Licence. In such circumstances
these proceedings may delay the construction and commissioning of the Power
Station and may result in loss and damage to Dungarvan Energy Limited. Had
Dungarvan Energy Limited been joined, as in my judgment it ought to have been
joined, as a party in the proceedings, in the absence of same compelling
countervailing considerations. I would have had little hesitation in finding
that the justice of the situation required that such an undertaking as to
damages be given.
40. Counsel
for Collette O’Connell pointed to what he said were serious public
interest aspects of this Application and he instanced, the protection of
Natural Habitats in Dungarvan Bay and the Ecology of the Cumeragh Mountains
area; the alleged failure of the Environmental Protection Agency to implement
properly or at all the E.C. (Natural Habitats) Regulations, 1997; the alleged
failure of the Environmental Protection Agency to apply the, “totality
principle” derived, he said, from Council Directive 85/337 E.E.C. and the
failure of the Environmental Protection Agency Act, 1992, to provide for an
Appeal procedure which Counsel said was contrary to the provisions of Article
34.1 and Article 40.3.1 of the Constitution of Ireland. However, having regard
to all the circumstances of the Application and in particular having regard to
the terms of the Objection of 12/10/00, but without determining any matter at
issue between the parties, I have concluded that the real substance of this
Application is the preservation and protection of private property rights which
are normally protected by private law remedies and the apparent public law
aspects of this challenge are in fact subsidiary though important issues.
41. In
the circumstances I consider it appropriate that Collette O’Connell
should give an undertaking to pay damages to Dungarvan Energy Limited in
respect of any provable loss and damage sustained by it as a consequence of the
stay on any implementation of the Integrated Pollution Control Licence should
she not be successful in her challenge to the granting of that Licence.
42. In
our system of jurisprudence with a Constitutional right of access to the
Courts, the occasions on which a Court might properly require what is described
as a, “fortified undertaking to pay damages”, must be very few.
This is certainly not such an occasion.
43. In
the Broadnet Ireland Limited case Laffoy, J., held that an undertaking as to
damages from that particular Applicant would be worthless, (see p. 262 of the
Report). Counsel for Collette O’Connell in my judgment correctly pointed
to the very real difference between a limited liability company with no assets
or capital and Collette O’Connell for whom as a person resident in the
State of full age and not under any legal or other disability or incapacity and
with some interest in immovable property in the State, and undertaking to pay
damages was a very serious matter indeed. The fact that the potential loss to
Dungarvan Energy Limited might exceed her ability to make good that loss is no
basis for regarding her undertaking as worthless and an abuse of the process of
the Court. I therefore refuse the application that the undertaking to pay
damages which the Court requires to be given by Collette O’Connell should
be supported in anyway whatever by the giving of security or the payment of
money into Court or otherwise. Counsel informed the Court that he had
carefully advised Collette O’Connell as to the possible consequences of
this undertaking and that he was satisfied that she fully understood them and
was prepared to give the undertaking if sought by the Court.