1. The
Applicants in these proceedings are residents of the Carrowbrowne area of
County Galway. The Respondent is Galway Corporation, a local authority and, of
course, a planning authority within its own functional area. In these
proceedings the Respondent is sued as a developer of lands which are situate in
the functional area of its sister local authority, namely Galway County Council.
This
application concerns a dump which is situate at Headford Road, Carrowbrowne,
County Galway. It has had a chequered history. In November 1995 in this Court
Keane J made an order closing down part of the dump. The reason for that order
being made was the failure on the part of the Respondent to comply with certain
obligations imposed upon it on foot of a planning permission obtained in
respect of the dump.
Thereafter
an application for a fresh planning permission was made in respect of the site
in suit and permission was sought to use that site as a dump for a period of
five years. In the first instance that application was dealt with by the
planning authority, Galway County Council, and it resulted in a permission
being granted which, in turn, was appealed to An Bord Pleanala.
An
Bord Pleanala conducted an oral hearing in respect of that appeal. It was
conducted by an inspector appointed by the Board. In addition the Board
appointed an independent assessor who is a hydrogeology expert. In due course
An Bord Pleanala granted planning permission and it is that permission which is
the subject matter of these proceedings.
The
planning permission was dated 9 April 1997. It contains a number of very
stringent conditions which I will consider presently. It is manifestly a
temporary permission.
The
First Schedule to the permission recites:
"Having
regard to:
(a)
the planning history of the site,
(b)
the location in an area with a sparse settlement pattern,
(c)
the location in an area which is not designated for amenity purposes in the
current Galway County Development Plan,
(d)
the availability of good access and proximity to the principal source of waste,
and
(e)
the need to provide temporary landfilling facilities while proposals for
acceptable alternative facilities are developed,
it
is considered that, subject to compliance with the conditions set out in the
Second Schedule, the proposed operation of the landfill for a limited period
not exceeding two years would not be prejudicial to public health and would not
be contrary to the proper planning and development of the area.
In
any event, this planning permission comes to an end in April 1999.
In
the Second Schedule to that permission there are set forth 14 different
conditions. The reason for each condition is also set forth in detail.
The
Applicants in these proceedings contend that there have been and continue to be
many breaches of the conditions upon which this permission was granted. A large
list of such breaches have been contended for by the Applicants. For the
purposes of this application, however, I am going to confine myself to the
major ones, many of which are now admitted.
Perhaps
the most important of all the conditions was that contained at No 6. It reads:
"Rehabilitation
measures including site perimeter drains, roadway, fencing, flood protection
bund, leachate collection treatment and pumping system, pumping main and
gravity sewer to Galway Main Drainage System, entrance control and civic
amenity site, maintenance building and weighbridge shall be installed and
operational within a period of one year from the date of this order."
That
meant that that condition had to be complied with not later than the 9 of April
of this year. The condition went on:
"No
landfilling shall take place on the site after one year from the date of this
order unless and until all of the rehabilitation measures listed are installed
and operational to the satisfaction of the planning authority."
The
reason given for this condition was "in the interest of protecting the
amenities of the area, and the proper planning and development of the area."
It
is now accepted that many of these requirements, which were to have been
complied with by April of this year, were not so complied with and, indeed,
have not been met even by today.
The
condition is crystal clear. In my view it was known to Galway Corporation; they
fully appreciated the import of it and they ought to have ceased landfill no
later than the 9 of April of this year. They did not. They now accept that they
have been in breach of this condition and accept that, in so far as they have
not complied with it, they have been involved in the commission of a criminal
offence.
Condition
No 8 recites as follows:
"(a)
Within 3 months of the date of this order the developer shall agree with the
planning authority a phased programme for the landfilling and landscaping of
the site over the two year period."
The
condition goes on to set forth what the details of the programme ought to be.
It is not necessary for the purposes of this application to recite in detail
the other provisions in No 8, but the reason for these are recited to be in the
interests of good management of the site, to protect the amenities of the area
and in the interests of visual amenity.
It
is accepted by Galway Corporation that it has not, even to this day, obtained
the agreement of the planning authority for the programme for landfilling and
landscaping that was to have been done within three months of April 1997.
To
put it in the words of the affidavit of Mr O Lochlainn, having sent details to
Galway County Council on 18 June 1997, they are "still awaiting a response" in
December 1998. I regret to say that that sort of approach on the part of the
Respondent to these proceedings is rather indicative of their whole attitude as
demonstrated from the affidavit evidence before me. I am afraid that the
response of Galway Corporation leaves a very great deal to be desired. Some of
it is quite alarming, particularly as it emanates from a body which is itself a
planning authority in its own functional area and is responsible for the
enforcement of planning control.
On
the evidence before me I am satisfied that the Respondent Corporation is in
serious breach of the planning laws. It is the recipient of a planning
permission and it quite flagrantly has not complied with the terms of that
permission.
In
defence of these proceedings, as is clear from the affidavits, it criticised
the Applicants, a criticism which in my view was wholly unjustified, and went
on to criticise An Bord Pleanala.
In
the course of the replying affidavits, one was sworn by Mr Monahan. He says -
and he does not appear to be alone in this -that Galway Corporation had
understood that it would take 18 months to two years, and more likely two
years, to complete the works which are contemplated in condition No 6. They say
that they are carrying out the works within the contemplated time frame, that
is to say, Galway Corporation's time frame, and that it proved impossible for
them to comply with the one-year period as arbitrarily decided by Mr Clohessy.
Mr Clohessy is a member of An Bord Pleanala.
A
number of features are notable in relation to this averment. First, there is a
suggestion that An Bord Pleanala behaved in some arbitrary fashion in fixing
the time which it fixed. If Galway Corporation were dissatisfied with the order
made by An Bord Pleanala they had rights and remedies available to them,
particularly if, as they allege, the decision of An Bord Pleanala was
arbitrary. They chose not to exercise any of those rights but rather to operate
on foot of their permission. Secondly, it shows a lack of understanding of the
way in which An Bord Pleanala conducts its business.
An
Bord Pleanala makes its orders as a Board. They are not made by an individual
member of the Board. This is an astonishing proposition to appear in an
affidavit sworn on behalf of a local authority which is itself, as I have
already pointed out, a planning authority. When I put these matters to Counsel
for the Respondent it is true that he disavowed, and in my view rightly
disavowed, them.
The
behaviour of Galway Corporation was perhaps influenced to some extent by the
fact that the planning authority for the area, Galway County Council, appears
to have taken no steps whatsoever to ensure compliance with the planning
permission granted by An Bord Pleanala. Indeed, the silence from Galway County
Council, which was its response to the documents that were sent to it in June
1997, is a silence which appears to permeate its relationship with Galway
Corporation.
During
the course of the hearing much time was expended in telling me of the problems
which have been encountered by Galway Corporation. It seems to me that many of
these problems would not have arisen if the Corporation had demonstrated
greater application and planning. However, when it became clear to them that
they were not going to be able to comply with condition No 6 of the planning
permission, they had no lawful entitlement to continue to allow the site to be
used for landfilling. To do so was to breach the terms of the permission and to
involve themselves in the commission of criminal offences under the Planning
Acts. It was, of course, open to them to apply for a fresh permission to Galway
County Council. at that time or well in advance of April 1998 but they did not
do so. Rather, they decided to continue with the breach of the condition.
When
confronted with an application of this sort, the position of this Court has
been authoritatively stated by the Supreme Court in Morris v Garvey [1982]
ILRM, 177. I need do no more than cite a passage from the judgment of Henchy J
where he says in relation to the jurisdiction which I am now exercising, which
was the old section 27 jurisdiction under the 1976 Act and now section 19 of
the 1992 Act:
"S
27(2) is one of the most important and least understood or used provisions of
the planning code. The section expressly recognised for the first time that a
member of the public (as well as the planning authority), regardless of his not
satisfying any of the qualifications based on property or propinquity or the
like (which are usually required to justify bringing proceedings), once he
discovers that a permitted developer is not complying with, or has not complied
with, the conditions of the relevant development permission, may apply in the
High Court for an order compelling the developer 'to do or not to do, or to
cease to do, as the case may be, anything which the court considers necessary
to ensure that the development is carried out in conformity and specifies (sic)
in the order'."
He
goes on to say:
"The
jurisdiction thus vested in the High Court is extremely wide. It recognises the
fact, which has been stressed in other decisions of this Court, that in all
planning matters there are three parties: the developer, the planning authority
(or the Planning Board, in the case of an appeal) and the members of the
public. Compliance with the statutory conditions for development is expressly
recognised in s 27(2) to be the legitimate concern of any member of the public.
We are all, as users or enjoyers of the environment in which we live, given a
standing to go to court and to seek an order compelling those who have been
given a development permission to carry out the development in accordance with
the terms of that permission. And the court is given a discretion sufficiently
wide to make whatever order is necessary to achieve that object."
"If
s 27(2) were to be treated as merely giving the court power to interdict a
continuance of the development in an unauthorised manner, the new jurisdiction
given by the sub-section would be self-defeating and would run contrary to the
expressed purpose of the subsection, which is 'to ensure that the development
is carried out in accordance with the permission
Later
in the judgment he goes on to say:
"When
s 27(2) is invoked, the court becomes the guardian and supervisor of the
carrying out of the permitted development according to its limitations, and in
carrying out that function it must balance the duty and benefit of the
developer under the permission as granted against the environmental and
ecological rights and amenities of the public, present and future, particularly
those closely or immediately affected by the contravention of the permission.
It would require exceptional circumstances (such as genuine mistake,
acquiescence over a long period, the triviality or mere technicality of the
infraction, gross or disproportionate hardship, or suchlike extenuating or
excusing factors) before the court should refrain from making whatever order
(including an order of attachment for contempt in default of compliance) as is
necessary to ensure that the development is carried out in conformity with the
permission
In
so far as this planning permission is concerned, I have come to the conclusion
that the Respondent has been guilty of a deliberate and conscious violation of
its terms.
It
has been said to me that the Court ought to withhold its order in this case for
a number of reasons, the first of which relates to the difficulties encountered
in the Corporation's endeavours to comply with the terms of the permission. In
my view many of these endeavours came about late in the day. The difficulties
would not have arisen had the Corporation involved itself in the exercise of
planning in good time for waste disposal. In any event, when it became manifest
to the Corporation that the difficulties were likely to involve it in an
inability to comply with condition No 6, the course for the Corporation was
clear: it should have applied for a fresh planning permission and should not
have continued to operate in breach of condition No 6.
Secondly,
it is said to me that an order made today will give rise to very considerable
difficulties for the Corporation in complying with its statutory obligations
under, for example, the waste management legislation. In my view the
Corporation has nobody but itself to blame if such difficulties are created. I
cannot conceive of a situation where the Court can, in order to enable Galway
Corporation to comply with its statutory obligations under one piece of
legislation, permit it to breach obligations imposed upon it by another piece
of legislation. In particular the Court cannot permit the fulfilment of a
statutory obligation, for example, under the Waste Management Act by the
commission of criminal offences under the planning legislation.
Finally,
it is said to me that the granting of an order by this Court will give rise to
very considerable inconvenience to the citizens of Galway in disposing of their
waste.
The
circumstances in which the Court can withhold an order have been the subject
matter of a number of judicial decisions and are set out in the various cases
which have involved orders under section 27 of the Act. They include genuine
mistake cases. This case is far from that. There are cases where there has been
acquiescence for a long period of time on the part of applicants. That clearly
cannot be the case here. An order can be withheld if the Court is satisfied
that the infraction concerned is a mere triviality or technicality. Whilst that
may be said of some of the complaints that are made here concerning, for
example, the type of records kept at the site, it certainly cannot be said of
the major infraction involved in the breach of condition No 6. It is also said
that the Court can withhold its order if gross or disproportionate hardship
occurs. Hardship, of course, carries little weight if it is brought about by
the conscious behaviour of a respondent to such proceedings. Whilst Galway
Corporation has demonstrated activity to deal with its problems in the
relatively recent past, in my view it has been wholly insufficient to meet the
situation with which it was con-fronted.
In
this case I have come to the conclusion that there must be an order from this
Court which will enforce the terms of the planning permission obtained by
Galway Corporation. To refuse to grant such an order would be to dishonour the
obligation imposed on the Court to enforce the planning laws. The Court has an
obligation to ensure that the planning code is enforced and it must do so. The
planning laws apply to everybody, including planning authorities where they act
as the developer of land under the Planning Acts. In my view it would be
entirely wrong for the Court to withhold an order in this case, particularly
when one considers that the Respondent, which is a planning authority itself,
is in gross breach of its obligations.
I
have therefore come to the conclusion that this is an appropriate case in which
to make an order in favour of the Applicants. Through its unlawful activity the
Respondent has already succeeded in continuing to use the dump in question from
April until today, a period of eight months of unlawful user and, as I have
already indicated, deliberate and conscious illegality. I am therefore going to
make an order forthwith restraining the use of the lands for dumping save in
respect of material from Corporation refuse trucks operated by Galway
Corporation. That is the only form of dumping permitted as of now and it must
cease one month from today.
It
follows that all landfilling operations on this site must be at an end by the
11 of January 1999. As of today, all landfilling except that from Corporation
refuse dumps must cease. The reason why I grant that concession - and I do so
reluctantly - is out of concern not for the Respondent, whose behaviour I have
found to be unacceptable, but out of concern for the citizens of Galway who may
find themselves confronted with great difficulties over the Christmas period if
their refuse cannot be disposed of. It is for that reason only that I permit
the continued use of this site for a period of one month from today solely and
exclusively for the purpose of receiving refuse from Corporation dump trucks..
The order takes effect as of now.
An
order is sought restraining the Respondent from acting in breach of the
conditions of its planning permission. It seems to me that the Respondent must
continue to service the dump by carrying out the obligations imposed on it
under the planning permission so as to ensure that the cure is not worse than
the disease.
The
Applicants seek an order restraining the Respondent from using the lands until
the conditions of the planning permission have first been complied with. It
does not seem to me that there is any necessity for that at the moment but
there will be liberty given to both sides to apply.
It
seems to me that an order should be made restraining the Respondent from acting
in breach of the conditions attached to Planning Permission Register Reference
No 96/1487. That means that the Respondent will be obliged to provide servicing
and that it will have to obtain the agreement of the planning authority for the
area in very short order in respect of condition No 5 and condition No 8. In so
far as it is required anywhere in the planning permission - and I have in mind
in particular condition No 5 and condition No 8 - the agreement of Galway
County Council will have to be procured within a month of today's date. The
Respondent will continue to provide whatever servicing is required to the dump
so as to minimise environmental and ecological damage.
The
Applicants are entitled to their costs, including reserved costs, as against
the Respondent, such costs to be taxed in default of agreement.
As
to the question of a stay, I am satisfied that this is not a case in which a
stay should be granted. To do so would effectively cut the ground from under
the order and would permit the Respondent to continue with the activity which I
have already characterised as being deliberate and conscious and unlawful. It
does not seem to me that a stay would in any way meet the legitimate
entitlements of the Applicants. I therefore refuse the application for a stay
for the purpose of an appeal to the Supreme Court.