1. This
matter comes before the court as an application for an interlocutory injunction
restraining the defendants its servants or agents and any other person or
persons whomsoever from carrying out and/or continuing any works in relation to
the construction and/or erection and/or development of a permanent halting site
and/or hard stand at Croghran Road, Birr, Co Offaly.
The
circumstances in which the application arises can be summarised, in so far as
is relevant to the present application, as follows.
The
respondents propose to develop and construct two permanent hard stand and/or
halting sites to accommodate members of the travelling community at Croghran
Road, Birr, Co Offaly and on the Roscrea Road, Birr, Co Offaly. This
application relates to the proposed development at Croghran Road.
As
it is relevant to the defence advanced by the respondents I set out in short
form the history of this proposed development.
The
development of these sites has been in the contemplation of the respondents
since May of 1994. Advertisements were inserted in the newspapers, reports were
circulated and meetings were held between interested parties and the Birr Urban
District Council in and around the months of June and July of 1994. As a result
of representations the halting sites were reduced in size so as to accommodate
six members of the travelling community instead of ten. A decision was made at
that time to proceed with the proposed development.
It
was not until November of 1996 that finance for the development was sought by
the Birr Urban District Council. This was sanctioned in September of 1997.
Tenders had already been sent out in May of 1997 and on the 4 of November, 1997
contracts were signed with the contractors for the carrying out of the work.
Works commenced on the 6 of November, 1997 and the applicants sought leave to
challenge the development by way of judicial review on the 15 of December, 1997.
The
case being advanced by the applicants is that this development is an
unauthorised development and in judicial review proceedings they have sought
inter alia a declaration that this work is unlawful and is in breach of section
39(2) of the Local Government (Planning and Development) Act, 1963. Leave to
seek this relief by way of judicial review was granted to the applicants by
order of Geoghegan, J on the 15 of December, 1997.
It
is not anticipated that these judicial review proceedings will be disposed of
for some considerable time.
The
applicants now apply for interlocutory relief on the basis that they wish to
preserve the status quo pending the determination of the judicial review
proceedings.
The
submissions made by the applicant can be summarised as follows. It is accepted
by the applicants that a development by a Council of an Urban District in such
a district is an exempted development by virtue of section 4 of the Local
Government (Planning and Development) Act of 1963. However, such a development
loses this status if it is a development which "contravenes materially the
development plan" (see section 29(3)) of the Local Government (Planning and
Development) Act, 1963.
The
applicants submit that an examination of the relevant Development Plan clearly
establishes that the proposed development is a material contravention of the
Development Plan. The relevant part of the 1988 Birr Urban District Council
Development Plan is paragraph 4.7 under the heading "Temporary Dwellings,
Caravans etc". That paragraph is in the following terms;
"for
the purpose of this written statement, temporary dwellings are taken to include
caravans, chalets, mobile homes and huts. It is an objective of the Development
Plan to prohibit the use of temporary dwellings for permanent residential
purposes on the grounds that such structures are generally unsuitable for human
habitation throughout the year. Exceptions will however be made in dealing with
acute housing emergencies. In this case, any permission granted will be for a
limited period only and such temporary homes should not be obtrusively sited.
The placing of caravans and temporary structures on isolated sites will not be
allowed to proliferate. However the provision of such caravan parks and chalet
estates as may be essential to meet social needs for specific groups in the
community will be considered for limited periods. In the layout of such sites
full account will be taken of the appropriate standards for same".
In
the zoning matrix a reference to "caravan park holiday" and "caravan park
residential" appears.
The
respondents claim that paragraph 4.7 is in sufficiently broad terms to embrace
a development of a hard stand and halting site for the use of members of the
travelling community.
In
the determination of this application for interlocutory relief I apply the well
established test approved in the Supreme Court in Campus Oil Limited v Minister
for Industry and Energy and Others 1983 IR 88 namely "that probability of
success at the trial is not the proper test to be applied: the applicant for an
interlocutory injunction, to be successful, must establish first that there is
a fair question to be determined at the trial of the action concerning the
existence of the right which he seeks to protect or enforce by injunction and
secondly that the circumstances are such that the balance of convenience lies
on the side of granting the injunction".
While
not purporting to determine the overall issue in the case I am left in no doubt
that the applicants have established that there is a fair question to be
determined at the trial of the action.
I
next pass to consider the balance of convenience.
On
behalf of the applicants it is submitted by Mr Walsh that if the work is not
halted then when the elected members come to consider the revised Development
Plan for the Birr Urban District Council, which is now in the course of
preparation, they will without any doubt pass a plan which would protect and
validate halting sites which have been constructed and completed rather than
not do so and so waste the monies already expended on the construction of the
site and moreover expose the Urban District Council to the additional cost of
removing the development and making good the lands. In these circumstances he
submits that if the applicants are to obtain any effective relief justice
requires that the works be halted.
On
behalf of the respondents Mr Finlay submits that the halting of the works now
will expose the respondents to a substantial claim by the contractor for
damages for the loss that he will have sustained by being unable to complete
the works.
In
the determination of this issue I am left in no doubt that the balance of
convenience is in favour of granting the injunction. In making this judgment I
take into account the fact that the loss sustained by the contractor and
possibly recoverable from the respondents can at least to some extent be
cushioned by the fact that he is able to occupy part of his work force for some
time on the halting site on the Roscrea Road which is not to be effected by any
order made by this court. Moreover it is apparent that the respondents or at
least some of them are persons of good standing who have given an undertaking
as to damages which would appear to protect the respondents against loss.
There
remains to consider the significant point advanced by the respondents relating
to the applicants alleged laches to the extent as to deprive them of the relief
claimed.
The
submission is made that ever since June of 1994 the applicants have been aware
of the proposal to develop the halting sites and yet took no active step in
relation to them until the 15 December, 1998 when they sought leave to seek
relief by way of judicial review.
In
my view the earliest date upon which the applicants could reasonably be
expected to realise that the proposal to construct these halting sites was
becoming a reality was when the finance for the project was sanctioned. This
occurred in September of 1997. By July of 1997 the applicants solicitors Messrs
John J Reidy and Company were in correspondence with the respondents in
relation to this matter and it was not until November of 1997 that an
acknowledgement was received to this correspondence. It is my view that the
applicants moved with all due expedition and certainly without undue delay by
bring the matter before the court and seeking relief by way of judicial review
on the 15 December, 1997.
There
is another factor in relation to this issue. In Mahon and Others v Butler and
Others (heard 1 of August, 1997) the Supreme Court has held that the High Court
had no jurisdiction to make an order under section 27 of the 1976 Planning and
Development Act in relation to an anticipated breach of the planning code nor
did it have jurisdiction to extend the statutory jurisdiction by way of the
general equitable jurisdiction of the High Court. On the basis of this decision
it would appear that it was only open to the applicants to seek relief when
work commenced on the 6 November, 1997.
Accordingly,
I grant the applicants the relief sought.