High Court of Ireland Decisions
You are here:
BAILII >>
Databases >>
High Court of Ireland Decisions >>
Beshoff Brothers Ltd. v. Select Service Partner Ireland Ltd. [1998] IEHC 122 (28th July, 1998)
URL: http://www.bailii.org/ie/cases/IEHC/1998/122.html
Cite as:
[1998] IEHC 122
[
New search]
[
Printable RTF version]
[
Help]
Beshoff Brothers Ltd. v. Select Service Partner Ireland Ltd. [1998] IEHC 122 (28th July, 1998)
THE
HIGH COURT
No.
1998/8102 P
BETWEEN
BESHOFF
BROTHERS LIMITED
PLAINTIFF
AND
SELECT
SERVICE PARTNER IRELAND LIMITED
DEFENDANT
JUDGMENT
of O'Sullivan J. delivered 28th day of July 1998.
1. The
Plaintiff is a well-known fish and chip outlet operator and seeks to compel the
Defendant to include its name and brand as an element in a forthcoming tender
for the catering concession in Dublin Airport to be submitted to Aer Rianta
before the end of August. This application is made to enforce an agreement
dated the 24th June 1998 of which a memorandum of agreement has been signed by
the parties. Because this memorandum, at Clause 8, refers to the intention of
the parties to
"enter
into a more formal agreement subsequently"
it has been referred to as a
"heads
of agreement"
,
although it is not so self-styled.
2. Subsequent
to this agreement, and I accept in good faith, the Defendant discovered that it
had an overall agreement with Harry Ramsden plc which is currently in existence
and whereby it has agreed:-
"....for
itself and on behalf of its group companies not... to undertake or
become
concerned in or have any interest in any capacity whatsoever in any
fish
and chip business in any company in the world...."
3. Simply
put, the Defendant now says that it has two conflicting contractual obligations
and that any Court Order compelling it to specifically perform its contract
with the Plaintiff will cause it to be in breach of its agreement with Harry
Ramsden plc.
4. It
accepts that it is or intends to be in breach of its agreement with the
Plaintiff, but it says that the Court should not make an interlocutory
mandatory Order requiring it to specifically perform that agreement for the
following reasons:-
1.
The
agreement is not complete: specifically there is no termination
clause.
Clearly any reasonable termination clause would at most allow one year's
termination period and since it is not intended that the Plaintiff's outlet
would open prior to the year 2000, the agreement could - at least arguably - be
terminated prior to that date. An Order directing inclusion of the Plaintiff
in the Defendant's tender would, therefore, fail to reflect this reasonable
view of the contractual relationship between the parties;
2. Damages
is an adequate remedy: the fact that damages may be
difficult
to calculate does not mean that they are not an adequate
remedy;
3. The
balance of convenience clearly favours the Defendant. The effect
of
an Order would preclude the Defendant from tendering, or force
them
to tender on a basis which could undermine their arrangements at
Dublin
Airport by reason of the consequential breach of their
agreement
with Harry Ramsden plc. They refer to two hundred
catering
jobs in Dublin Airport which are involved and say that
damages
would clearly be an inadequate remedy;
4. The
Plaintiff, they say, is free to tender to Aer Rianta in its own right.
The
Defendant undertakes not to include Harry Ramsden plc or any
other
fish and chip outlet in its tender. The Defendant says that
damages
is an adequate remedy for the Plaintiff.
5. On
the other hand the Plaintiff says:-
1. This
case is unusual in that it is a clear case in the sense that the Court at trial
will be in possession of no better evidence or material on the legal question
between the parties than it is now because the Defendant admits that it is or
intends to be in breach of its agreement;
2. Furthermore,
the contract is clear and any ambiguity relates only to
clauses
which are not relevant at this stage because the Plaintiff is
seeking
to enforce the unambiguous clauses;
3. The
Court by refusing an injunction would be permitting the Defendant to select by
reference to its own best advantage and contrary to the requirements of justice
which contract it would breach. By making an Order the Court would be
effectively compelling the Defendant to breach its agreement with Harry Ramsden
plc;
whereas by refusing to make an Order it is allowing the Defendant to break its
contract with the Plaintiff thereby handing over the election to the Defendant
itself.
CONCLUSIONS
1. I
consider that the agreement is sufficiently clear and unambiguous for present
purposes;
2. I
agree with the Plaintiff that the Court is now in as good a position as
it
will be at the trial of the action on the central legal issue between the
parties
in the sense that the Defendant accepts that it is or intends to
be
in breach of its agreement with the Plaintiff;
3. That
being so, I consider that I should approach this application in accordance with
the principles laid down by the Supreme Court in
Dublin
Port and Docks Board -v-Britannia Dredging Company Limited
(1968 IR 136) and in particular by the then Chief Justice O'Dalaigh C.J. at
page 147 where he said:-
"...and
the position is therefore not different from what it would be if at the trial
the Court should reach the same conclusion. The principle stated in
Doherty
-v- Allman
(1907:AC:351) is accordingly applicable and the Court is not concerned to
examine either the balance of convenience or the amount of damage".
6. I
must, accordingly, enforce the agreement unless in the exercise of my
discretionary jurisdiction I should refuse the remedy of specific performance.
7. If
this were the Plenary hearing of the action I would have to consider the
Defendant's plea of mistake. I would have to consider, not whether the
Plaintiff is entitled to a remedy (which in principle it clearly is) but
whether the Court in its discretion should refuse the remedy of specific
performance on the grounds of the Defendant's mistake, including a
consideration of whether the hardship which the Order of specific performance
will cause to the Defendant is such as would warrant a refusal of the relief of
specific performance to the Plaintiff.
8. I
do not think the kind of hardship now prayed in aid by the Defendant - the
hardship anticipated (but not necessarily certain) as a consequence of its
breach of its agreement with Harry Ramsden plc - is of the order of hardship
which justifies a Court in refusing a decree of specific performance to which a
Plaintiff is otherwise entitled. I refer generally to the judgment of Costello
J. (as he then was) in
O'Neill
-v- Ryan
(3) (1992:1:IR:191).
9. Against
this hardship is the hardship of the Plaintiff if I refuse a decree of specific
performance. The Plaintiff would be deprived of an enhanced opportunity of
procuring a premier international showcase for its fish and chip outlet and I
do not consider damages an equivalent remedy to a decree of specific performance.
10. Accordingly,
I will make the Orders sought by the Plaintiff at paragraphs 1 and 2 of the
Notice of Motion.
© 1998 Irish High Court