1. This
is an application by the Applicants, each of whom resides at Blackglen Road,
Sandyford, County Dublin, for the following reliefs:
2. By
Order of this Court made on 24th July, 1995 by Lavan J. the Applicants were
granted leave to apply for the foregoing reliefs by way of application for
judicial review.
3. The
evidence adduced by the Applicants in support of their application was an
Affidavit of the second named Applicant, Jack Whelan. Mr. Whelan averred that
the residents of the Blackglen Road area first became aware of "the proposal to
establish a permanent halting site at the Blackglen Road for forty caravans" as
a result of a report in the Evening Herald on 19th May, 1995. There had been
no public consultation and, moreover, it appeared that the local Councillors
had only become aware of the proposal when they had been informed by the first
named Respondent of his decision at a meeting on the previous day. Mr. Whelan
averred that none of the Applicants has any animosity towards travellers, but
they object to the proposal having regard to its size, the manner in which it
was originated, the location on the Blackglen Road and the other matters set
out in his Affidavit. In essence, the Applicants base their entitlement to the
relief they claim on the opinions of three experts, John Sugars of John Sugars
& Partners, Architects, Brian J. McCann of Thorburn Colquhoun, Consulting
Engineers and Dr. Brian Meehan, Planning Consultant, whose reports were
exhibited in Mr. Whelan's Affidavit. The Applicants made the three experts
available for cross-examination by the Respondents' Counsel. However, only Mr.
Sugars was cross-examined.
4. In
his report, Mr. Sugars set out to demonstrate that the location of a halting
site at Blackglen Road was inconsistent with the persistent policy of the
Respondent and its predecessor, Dublin County Council, over the previous ten
years, which was to refuse planning permission for any development accessed
from Blackglen Road, on the grounds that such development would create a
serious traffic hazard because of the inadequacy of Blackglen Road, and of the
inadequacy of the water supply and the deficiency of the drainage system. Mr.
Sugars expressed the opinion that the site at Blackglen Road is totally
inadequate for use as a halting site for, inter alia, the following reasons:
5. In
his oral testimony, Mr. Sugars expressed the opinion that the rationale
underlying the planning policy of the second named Respondent and its
predecessor, as evidenced by previous planning decisions in relation to land
abutting Blackglen Road, was based on sound logical criteria, on common sense
and represented good planning policy. In relation to the proposal to locate a
halting site at Blackglen Road, he testified that the proposal would not work
and it could not meet basic criteria. He opined that, if he were to lodge a
planning application for the proposal, the application would be refused and the
planning authority would be acting properly in refusing it.
6. Mr.
McCann, in his report, stated that the Blackglen Road functions as a local
distributor, district distributor and outer circumferential ring road between
Blackrock and Tallaght. He stated his belief that a permanent traffic counter
maintained by the second named Respondent near Lamb Doyles Public House records
an average daily weekday flow on Blackglen Road between Monday and Friday of
16,600 vehicles. He inspected Blackglen Road in the vicinity of the proposed
halting site on the afternoon of Thursday 6th July, 1995 between 5.00 p.m. and
6.00 p.m., at a time when there was heavy traffic travelling east-west at a
very low level of speed and service. He noted -
7. Mr.
McCann concluded from his inspection that the traffic volumes greatly exceeded
the capacity of the road with consequent severe reduction in the level of
service and significant increase in traffic hazard to pedestrians, cyclists and
vehicles. He summarised his opinion as follows:
8. Dr.
Meehan expressed the opinion in his report that the location of a halting site
at Blackglen Road would be contrary to the proper planning and development of
the area and would constitute a material contravention of the relevant
development plan, that is to say, the 1993 Dublin County Development Plan (the
Development Plan). The site is located within an area zoned F - to preserve
and provide for open space and recreational amenities. While the location of
halting sites is "permitted in principle" in an area zoned F, by the terms of
the Development Plan "permitted in principle" is subject to compliance with
relevant policies, standards and requirements set out in the Development Plan.
Dr. Meehan expressed the view that the implementation of the proposal to locate
a halting site at Blackglen Road would be at variance with the policies,
standards and requirements set out in the Development Plan in the following
respects:
9. Dr.
Meehan also referred to the objectives set out in the Development Plan of
providing or securing the provision of sites for the settlement of travelling
families who normally reside in Dublin County and the objective of
re-establishing the Joint Sub-Committee for the settlement of Travelling People
in the Dublin area to further that objective and to assist in the
implementation of the settlement program. He contended that, pending the
re-establishment of the Joint Sub-Committee, a halting site development of the
nature and extent proposed at Blackglen Road is premature and at variance with
the stated procedural objective set out in the Development Plan. In all of the
foregoing respects, Dr. Meehan contended that the implementation of the
proposal would materially contravene the Development Plan.
10. The
evidence adduced by the Respondents in response to the application and in
support of their Statement of Opposition comprised Affidavits of three
officials of the second named Respondent, namely, Ciaran Ryan, an
administrative officer in the Housing Department, Richard Cremins, Senior
Planner and Patrick Dullaghan, County Engineer. These Affidavits identified a
Managers Order made by the first named Respondent on 23rd June, 1995 as being
the relevant decision. Each of the deponents was cross-examined by Counsel for
the Applicants.
11. Before
outlining what the evidence establishes as to the context and manner in which
the Order dated 23rd June, 1995 was made, I propose considering what the Order
shows on its face. As is usual, the Order is preceded by a report, in this
case a report from the Senior Administrative Officer in the second named
Respondent's housing department. The Order was expressed to be made in
accordance with the provisions of the Housing Acts, 1966 to 1992 and granted
approval for the carrying out of the works detailed in that report and shown on
a drawing identified, that is to say, "to develop a temporary Halting Site at
Blackglen Road, Sandyford for a maximum of 20 families". The report recorded
the following matters:
12. On
the evidence, I find that the sequence of events which led to the making of the
Order dated 23rd June, 1995 was as follows:
13. This
is the report from the County Engineer which is recorded in the report to the
first named Respondent on foot of which the Order of 23rd June, 1996 was made.
14. This
is the report from the County Planning Officer which is recorded in the report
on foot of which the Order of 23rd June, 1995 was made. A supplemental report
was submitted by the County Planning Officer on 28th June, 1995 in which he
indicated that a small portion of the site, in the vicinity of the entrance, is
zoned G with the objective 'to protect and improve high amenity areas'. It was
indicated that a halting site is 'permitted' in this zone.
15. The
specific concerns raised by the Applicants' experts were addressed in the
Affidavits filed on behalf of the Respondents and in the oral testimony of the
deponents. Mr. Patrick Dullaghan, the County Engineer, averred that during
1995 a figure in the order of £60,000 was expended by the second named
Respondent on Blackglen Road in resurfacing and marginal widening. A footpath
will be provided for the residents of the temporary halting site enabling the
residents to access the present roadside footpath at Blackglen Road leading to
Lambs Cross. There will be a splayed vehicular access with adequate with sight
lines. Public lighting will be provided. As it has proved impossible to tap
into the public water main at Blackglen Road, a new source of water supply has
had to be identified. It is proposed to pipe the water from the existing
reservoir at Sandyford Road by means of an underground pipe through a clearing
in Fitzsimons Wood. The design of the halting site prepared by the Consulting
Engineers provides for the provision of storm drainage to an adjacent storm
drain, which has spare capacity. Foul sewerage will be discharged to an
adjacent foul sewer, which has spare capacity.
16. Richard
Cremins, in the Affidavit sworn by him and in his oral testimony, disputed that
decision to locate a temporary halting site at Blackglen Road is at variance
with the policy of the second named Respondent and its predecessor, as
evidenced by decisions on previous planning applications. He contended that
the planning history illustrates that the policy was to oppose "one of" housing
fronting directly onto Blackglen Road. He also disputed Dr. Meehan's assertion
that the implementation of the proposal would materially contravene the
Development Plan and I will return to this aspect of his evidence later.
17. No
direct evidence was adduced by the Respondents as to the considerations to
which the first named Respondent had regard in making the Order of 23rd June,
1995 in the form of an Affidavit sworn by or oral testimony of the first named
Respondent himself, a fact which was commented on critically by Counsel for the
Applicants. The evidence clearly establishes that the first named Respondent
had before him the report of the Senior Administrative Officer in the housing
department, to which the Order is appended, which incorporates the advice of
the County Planning Officer and the County Engineer. In my view, the failure
of the Respondents to adduce direct evidence is not a matter which should give
rise to any adverse inference against the Respondents.
18. Before
leaving the evidence, it is perhaps worth noting that the evidence clarifies
certain factual matters of which the Applicants were not aware when this
application was instituted and when their claim for relief was framed. First,
the proposed halting site will comprise 20 bays and house 20 travelling
families. Each bay will accommodate two caravans but, on the evidence, only a
small percentage of traveller families have two caravans. Secondly, while a
decision in principle to proceed with the development of the site at Blackglen
Road was made in early April 1995, the Order of the first named Respondent was
actually dated 23rd June 1995.
19. The
grounds on which the Applicants contend that they are entitled to the relief
claimed are as follows:
20. The
last ground is unsustainable. Article 34 of the Local Government (Planning
& Development) Regulations, 1990 (S.I. No. 25/1990), on which the
Applicants rely, was repealed by the Local Government (Planning &
Development) Regulations, 1994 (S.I. No. 86/1994). Article 116 of the 1994
Regulations replaces Article 34 and provides as follows:
21. Article
24 of the European Communities (Environmental Impact Assessment) Regulations
1989 (S.I. No. 349/1989) provides that development of the class as set out in
Part I and Part II of the first schedule to those regulations is specified for
the purposes of those regulations. The Applicants contend that the proposed
halting site comes within paragraph 11(a) of Part II of the first schedule
which itemises -
22. The
proposed halting site will accommodate a maximum of 40 caravans and clearly
does not come within paragraph 11(a).
23. Counsel
for the Respondents submitted that the parameters of this Court's power to
quash the managerial order of 23rd June, 1995 are defined by the decision of
the Supreme Court in
O'Keeffe
-v- An Bord Pleanala
,
(1993) 1 I.R. 39. While Counsel for the Applicants acknowledged that the
principles enunciated by the Supreme Court in that case are applicable in
determining issues which arise on this application, it was contended that they
are not exclusively applicable. Nonetheless, before considering the remaining
grounds relied on by the Applicants, I think it is important to summarise the
principles laid down by the Supreme Court as to the circumstances under which
this Court can intervene to quash the decision of an administrative officer or
tribunal on the grounds of unreasonableness or irrationality, which are set out
in the judgment of Finlay C.J. at page 70 et seq. The principles are as follows:
24. While
the decision impugned on this application is not a planning decision per se, in
essence, the Applicant's challenge is founded on planning considerations. In
short, they say that the decision to locate the halting site at Blackglen Road
is a bad planning decision.
25. While
the proposed development of the halting site at Blackglen Road, which is in the
functional area of the second named Respondent, is an exempted development
under Section 4(1) of the Local Government (Planning & Development) Act,
1963 (the 1963 Act), Section 39 of the 1963 Act precludes the Respondent from
effecting any development which contravenes materially the Development Plan.
Counsel for the Applicants argued that decisions of this Court, for instance,
the decision of Flood J. in
Tom
Chalke Caravans Limited & Anor. -v- Limerick County Council
,
(unreported) delivered on the 20th day of December, 1991 and the decision of
Carney J. in
Keogh
-v- Galway Corporation
(unreported) delivered on 9th September, 1994, illustrate that the issue as to
whether a proposed development materially contravenes the relevant development
plan is determined without reference to the O'Keeffe principles. There are
undoubtedly situations, as the cases cited illustrate, in which the O'Keeffe
principles have no part to play in determining whether a proposal would
constitute a material breach of a development plan. For instance, the second
named Respondent's current development plan might have provided that halting
sites are not permitted on lands zoned F and G, in which case the proposed
development at Blackglen Road would clearly constitute a material
contravention. However, as the evidence established, halting sites, which, in
my view, includes temporary as well as permanent halting sites, are "permitted
in principle" on the site at Blackglen Road "subject to compliance with
relevant policies, standards and requirements" set out in the Development Plan.
In my view, where a controversy arises on judicial review as to the application
of the relevant policies, standards and requirements stipulated in a
development plan, that controversy must be resolved by reference to the
O'Keeffe principles.
26. In
relation to the three specific infringements contended for in Dr. Meehan's
report, the Respondent's position is as follows:
27. In
my view, the Applicants have not established that the decision to locate the
temporary halting site at Blackglen Road infringes the policies and objectives
of the Development Plan in relation to the preservation of views and prospects
and the protection of areas of scientific interest. It is clear from the
evidence that, before the Order dated 23rd June, 1995 was made, the relevant
officials of the second named Respondent were conscious of the material
provisions of the Development Plan and made value judgments as to compliance
with those provisions. In my view, one cannot conclude that those judgments
fly in the face of fundamental reason and common sense and, accordingly, on the
basis of the O'Keeffe principles, a decision founded on those judgments is
neither unreasonable nor irrational. Moreover, in my view, non-implementation
of the stated objective to re-establish the Joint Sub-committee does not in any
way preclude the second named Respondent from implementing in the manner
proposed in the Order its statutory duty under Section 13 of the Housing Act,
1988, which has been recognised by this Court in the judgment of Barron J.
delivered on 21st February, 1991 in
University
of Limerick -v- Ryan & Ors
.
(unreported) and the judgment of Flood J. in
County
Meath VEC -v- Joyce
(1994) 2 I.L.R.M. 210, to provide halting sites for travellers.
28. It
was contended on behalf of the Applicants that the evidence shows that the
decision making process of the Respondents was irrational and that it resulted
in an unreasonable and irrational decision. The Respondents, it was contended,
turned reason on its head in deciding in the first and second week in April
1995 to locate the halting site at Blackglen Road and thereafter attempting to
give it a veneer of rationality. The decision is contrary to the clear
planning policy of the second named Respondent during the previous ten years.
In particular, it ignores the second named Respondent's stated policy on road
traffic and runs counter to it. At the time it was made, no proper regard was
had to sewerage disposal or water supply. There were and are no services,
educational, social and such like, available to service the halting site. The
project itself if grossly disproportionate to all other halting site projects
in the second named Respondent's functional area. Its capital cost represent
three times the second named Respondent's annual allocation from the Department
of the Environment in respect of halting sites in the previous two years. The
halting site is designed to accommodate a great number of travellers of
indeterminate category. A combination of these factors, it was argued, has
produced a decision which flies in the face of fundamental reason and common
sense.
29. On
the evidence, I find that the decision to locate the halting site at Blackglen
Road was a departure from the prevailing planning policy of the second named
Respondent and its predecessor in relation to the development along Blackglen
Road, as evidenced by planning decisions during the previous ten years, which
seems to me to be an appropriate period over which to assess the planning
policy. Moreover, I think it is probable that had a private developer
embarking on a commercial project sought planning permission for a caravan or
mobile home park at the site of the proposed halting site, permission would
have been refused. Neither of these factors renders the decision to partially
fulfill the second named Respondent's objective in relation to traveller
accomodation by locating a temporary halting site at Blackglen Road irrational.
30. I
also find that the decision in principle to proceed with the development of a
temporary halting site was made at the beginning of April 1995 and that there
is a high degree of probability that the only factor which would have resulted
in its reversal was the unavailability of funding from the Department of the
Environment. At that time no alternative solution to the second named
Respondent's immediate traveller accommodation problems had been under
consideration for three months. Between the time the decision in principle was
made and the time it was formalised in the manner required by law, Consulting
Engineers were retained and the views of the relevant departments of the second
named Respondent were elicited. What occurred during this period, in my view,
is not fairly characterised as merely an attempt to give a veneer of
respectability to the decision. On the contrary, concerns in relation to the
project were identified and the need to address them was recognised. In my
view, even if the ultimate technical solution to a particular difficulty, for
example, the provision of the footpath, had not been determined by 23rd June,
1995, this of itself would not have rendered the formal decision made on that
day irrational.
31. Of
the concerns raised by the Applicants in relation to the proposed development,
the risk of traffic hazard, in my view, is the gravest. There is undoubtedly a
formidable array of evidence before this Court that the proposed development
will constitute a significant risk to road users: the inferences which can be
drawn from the second named Respondent's prevailing planning policy in relation
to Blackglen Road, the views expressed in the minute dated 28th April, 1995
from the Roads and Traffic Department and the opinions of Mr. Sugars and Mr.
McCann. On the other hand, when he made his formal decision, the first named
Respondent had before him the advice contained in the minute dated 12th June,
1995 from the County Engineer, which was based on a layout prepared by the
Consulting Engineers. In applying the O'Keeffe principles in reviewing the
formal decision which was made on 23rd June, 1995, it is not the function of
the Court to evaluate the evidence before the Court on the merits or to assess
whether the opinions of Mr. Sugars and Mr. McCann are to be preferred to the
opinion of the County Engineer. The question for this Court is whether there
was material before the first named Respondent on which he could base the
decision to proceed with the proposal. In my view, there was.
32. I
have come to the conclusion that the Applicants have not surmounted the
difficult hurdle which the O'Keeffe principles place before a person who seeks
to challenge an administrative decision on the ground of irrationality and they
have not discharged the onus of establishing that the decision of 23rd June,
1995 was irrational in accordance with those principles.
33. Finally,
the Applicants challenged the utilisation by the first named Respondent of the
"emergency" procedure available under Section 27 of the 1988 Act. It is not
disputed that the decision made by the first named Respondent is an executive
function within the meaning of Section 17 of the County Management Act, 1940.
However, subsection (7) of Section 2 of the 1955 Act requires a manager to
inform the members of a local authority before any works (other than works of
maintenance or repair) of the local authority are undertaken. Subsection (9)
of Section 2 provides that nothing in the foregoing provisions of Section 2
shall prevent the manager from dealing forthwith with any situation which he
considers is an emergency situation calling for the immediate action without
regard to those provisions. Section 27 of the 1988 Act amended Section 2 of
the 1955 Act by the insertion of the following subsection after subsection (9):
34. The
practical consequence of a manager being able to deal with a particular
situation under subsection (9) of Section 2 is that the provisions of Section 3
of the 1955 Act are obviated. Section 3 empowers a local authority which has
been informed pursuant to Section 2 of any works (not being works which the
local authority are required by or under statute or by order of a Court to
undertake) to direct that the works shall not be proceeded with. The
Applicants contend that the onus is on the Respondents to show that the
"emergency" procedure was properly invoked and, in particular, that the first
named Respondent had regard to the factors which he is required to have regard
to - personal health, public health and safety considerations. A recital of
the relevant provision in the report on foot of which the Order of 23rd June,
1995 was made is not sufficient, it was submitted. I reject this submission.
On this application, the onus is on the Applicants to establish that the
decision is ultra vires, as they assert; it is not on the Respondents to
establish that it is intra vires.
35. The
use of the "emergency" procedure was also impugned on the ground that it was
used in a manner which offends the principle of proportionality. The emergency
which had to be met, so the argument goes, was the imminent necessity to
relocate the six families on the site at Merville, which the second named
Respondent was by Court Order obliged to close on 1st June, 1995. The
provision of a 20 bay halting site is disproportionate the objective of dealing
with that emergency. Even if I were to accept the proposition that the first
named Respondent was only to entitled to utilise the "emergency" procedure to
resolve the Merville problem and not the problem of roadside and unauthorised
encampments, I am not satisfied that the Applicants have demonstrated that the
principle of proportionality, as most recently enunciated by Costello P. in
Daly
-v- Revenue Commissioners
(1996) 1 I.L.R.M. 131, is applicable. The rationale underlying the principle
of proportionality is the protection of constitutional rights by requiring that
any restriction on the exercise of those rights permitted by law passes a
proportionality test. In this case, there is no evidence whatsoever that the
invocation of the "emergency" procedure infringed a constitutionally protected
right of any of the Applicants.
36. I
conclude that the Applicants are not entitled to any of the reliefs claimed and
I dismiss the application.