Irish Competition Authority Decisions
You are here:
BAILII >>
Databases >>
Irish Competition Authority Decisions >>
Esat Telecommunications Ltd/CIE/Iarnr d Eireann- non-exclusive licence to lay cables [2000] IECA 577 (28th January, 2000)
URL: http://www.bailii.org/ie/cases/IECompA/2000/577.html
Cite as:
[2000] IECA 577
[
New search]
[
Printable RTF version]
[
Help]
Esat Telecommunications Ltd./CIÉ/Iarnr d Éireann - non-exclusive licence to lay cables [2000] IECA 577 (28th January, 2000)
COMPETITION
AUTHORITY
Competition
Authority Decision of 28th January 2000 relating to a proceeding under Section
4 of the Competition Act, 1991.
Notification
No CA/8/98 - Esat Telecommunications Ltd./CIÉ/ Iarnród
Éireann - non-exclusive licence to lay cables.
Decision
No. 577
Price
£1.20
£1.70
including Postage
Notification
No. CA/8/98: Esat Telecommunications Ltd./CIÉ/ Iarnród
Éireann - non-exclusive licence to lay cables.
Decision
No: 577
1. Introduction
1. Notification
was made on 20 August 1998 with a request for a certificate under
Section 4(4)
of the
Competition Act, 1991, as amended or, in the event of a decision by the
Authority to refuse a certificate, a licence under
Section 4(2) in respect of
an agreement whereby CIÉ and Iarnród Éireann have granted
to Esat Telecommunications Ltd. a non-exclusive licence to lay fibre optic
cable along the railway lines operated by Iarnród Éireann for 20
years, with a possibility of renewal for a further 10 years. Notice of
intention to issue a certificate in respect of the agreement was published in
the Irish Times on 10 December 1999. No submissions were received from
interested parties.
2.
The
Facts
(a) Subject
of the Notification
2. CIÉ
and its subsidiary, Iarnród Éireann have granted Esat
Telecommunications Ltd. a non-exclusive licence to lay fibre optic cable on
their property along the railway lines operated by Iarnród
Éireann. The duration of this licence is for twenty years with the
possibility of renewal for another ten years. Esat Telecommunications Ltd.
intends to create a national fibre optic cable network in Ireland and has
subcontracted to Iarnród Éireann the construction and maintenance
of this network. As part consideration for this licence, Esat Telecom has
granted CIÉ six fibre pairs, one of which CIÉ can use for its own
internal communications needs and the remainder of which CIÉ can lease
or sell to third parties, subject to a right of first refusal for Esat
Telecommunications Ltd.
(b) The
Parties Involved
3. Esat
Telecommunications Limited (“Esat Telecom”) is a wholly-owned
subsidiary of the Esat Telecom Group plc, which was formed to combine
shareholdings in two telecommunications businesses - Esat Telecom and Esat
Digifone Limited (“Esat Digifone”). Esat Telecom has its
registered office at The Malt House, Grand Canal Quay, Dublin 2. It provides
telephony services for businesses, including broadband data services and long
distance services, and had a turnover of IR£16, 794,274 for the year ended
31 December, 1997. The Esat Telecom Group plc also owns 45% of Esat Digifone
Ltd., which operates a national cellular mobile telephony system using the GSM
(digital) standard. The Esat Telecom Group plc had a turnover of
IR£17,040,000 for the year ended 31 December, 1997, and for the year ended
31 December 1998 had a turnover of IR£ 37,483,000.
4. Córas
Iompar Éireann (CIÉ) is a state-owned holding company whose
purpose is to provide public transport services in Ireland. It has three
subsidiary companies:
-
Iarnród Éireann (Iarnród Éireann), which provides
railway services
throughout
Ireland;
-
Bus Éireann, which provides bus services throughout Ireland; and
-
Bus Átha Cliath (Dublin Bus), which provides bus services in Dublin.
CIÉ
has its registered offices at Heuston Station, Dublin. It had a turnover of
IR£341,200,000 for the year ended 31 December, 1997. Iarnród
Éireann has its registered offices at Connolly Station, Dublin. It had
a turnover of IR£129,026,000 for the year ended 31 December, 1997.
(c) The
Product and the Market
5. The
relevant product or service market is that for the provision of terrestrial
transmission capacity for telecommunications services. The network is intended
and designed for national traffic; it will link switched locations between
Irish cities based on the existing railways infrastructure. The relevant
geographic market is therefore the State.
6. Until
1 July 1997, Telecom Eireann (now Eircom) was the only entity authorised to
provide domestic transmission facilities in Ireland. All competing telecom
operators, including Esat Telecom, have had to lease their domestic
transmission capacity from Telecom Eireann in order, for instance, to provide
connection to customers and among their regional switches. Liberalisation of
alternative infrastructure for certain telecommunications services in Ireland
occurred on July 1, 1997, thus enabling Esat Telecom to build and operate its
own national infrastructure. In this respect, Esat Telecom was granted a
licence by the Director of Telecommunications Regulation on December 23, 1997.
In February 1998, BT announced plans to enter into a joint venture (named
“Ocean”) with the Irish Electricity Supply Board
(“ESB”) to operate a national broadband network using ESB’s
surplus bandwidth. Full competition on the Irish telecommunications market,
including voice telephony services, was introduced on 1 December 1998. On 30
November 1998, Esat Telecom Group plc surrendered the licence granted to it on
23 December 1997, and was granted a General Telecommunications Licence by the
Director of Telecommunications Regulation, which,
inter
alia
,
allows it to operate a network.
7. The
size of the market is difficult to estimate. The notifying party states that
Telecom Eireann’s turnover from private circuits was, for the year ended
2 April 1998, around IR£75.3 million and, for the year ended 2 April 1997,
around IR£58.8 million. Because the construction of alternative
infrastructure is still at a relatively early stage, it is impossible to
estimate market shares in the relevant product market. However, it is expected
that Telecom Eireann, Esat Telecom and Ocean will be the major providers of
transmission capacity in Ireland.
Regulatory
issues
8. The
construction of alternative infrastructure requires a licence under Section 111
(2) of the Postal and Telecommunications (Services) Act 1983. Licences are
granted by the Office of the Director of Telecommunications Regulation.
Applicants are required to give basic elements of their network construction up
to 1999, but are not obliged to make investments on foot of those
representations. The construction of alternative telecommunications networks
takes place pursuant to the Telegraph Act of 1863 as amended and the Local
Government Planning and Development Act 1963. In general, where public property
is being traversed, the consent of the relevant municipal authority is
required. The 1863 Act provides for a system whereby upon notification an
authorised company is permitted to install telecommunications infrastructure.
9. In
order to roll out a national network, the necessary rights of way must be
obtained. In the case of Esat Telecom’s arrangements with CIÉ,
neither party needs to negotiate rights of way as CIÉ/Iarnród
Éireann control most of the property on which the railways operate and
they have licensed Esat Telecom directly to lay cable on their property. On
the other hand ESB’s physical infrastructure is based on wayleaves, which
need to be carefully negotiated.
(d) The
Notified Arrangements
10. CIÉ
and Iarnród Éireann concluded with Esat Telecom on 31 July 1998 a
Licence Agreement whereby the former grants Esat Telecom a non-exclusive
licence to lay over 2 000 km of fibre optic cable on their property along the
railway lines operated by Telecom Eireann. The licence is granted for a period
of 20 years, renewable for another 10 years. The intended cable will contain
either 48 fibres, 96 fibres or 160 fibres armoured, depending on Esat technical
specifications. The choice of routes for laying the cable would take account
of existing cable routes and the requirement to allow for additional cable
routes in the future. In consideration of the grant of the licence, Esat
Telecom is to pay CIÉ a fixed annual licence fee and a variable
performance fee, and to grant CIÉ six pairs of dark fibre.
11. The
construction of Esat Telecom’s fibre optic cable network along the
railway will be made by Iarnród Éireann according to a
Construction Agreement. Iarnród Éireann will also ensure the
maintenance, servicing and updating of the network according to a Maintenance
Agreement.
12. Under
Clause 3.5, Esat Telecom is obliged to grant CIÉ six pairs of optical
fibres. These pairs are divided into A fibres, which consist of one fibre pair,
and B fibres, which consist of the remaining five pairs of fibres. Pursuant to
clauses 3.5.6.1 and 3.5.6.2, the CIÉ “A fibres” may be used
by CIÉ and Iarnród Éireann only for their own internal
communications, and between them and their customers in respect of the road and
rail transportation businesses of CIÉ and its subsidiaries. The
CIÉ A fibres may not be used by CIÉ or Iarnród
Éireann for the commercial provision of leased lines and data services
to end users. The use of B fibres by CIÉ for the commercial provision of
leased lines and data services to end users is restricted under a number of
conditions (clause 3.5.7.1), including a preferential right in favour of Esat
Telecom: before activating those fibres, CIÉ must offer them first to
Esat Telecom at the then prevailing market rate in Ireland for a pair of dark
fibres. The parties have agreed on a schedule of events, linked to the status
of deployment of the network, which trigger Esat’s right of first refusal
to lease one pair of B fibres at a time over a period of time extending 17 years.
- In
practice, this right of first refusal will be triggered by Esat Telecom’s
placing into service of its own fibres between various points of the network or
upon specific anniversary dates of the Licence Agreement as follows:
- upon
50% of Esat Telecom’s fibres being placed into service (i.e. powered, lit
and connected to Esat Telecom’s network), Esat Telecom has a right of
first refusal to lease one of CIÉ’s B fibre pairs;
- upon
60% of Esat Telecom’s fibres being placed into service, Esat Telecom has
a right of first refusal to lease a second CIÉ B fibre pair;
- upon
70% of Esat Telecom’s fibres being placed into service, Esat Telecom has
a right of first refusal to lease the third pair:
- upon
80% of Esat Telecom’s fibres being placed into service, it has a right of
first refusal to lease the fourth pair;
- upon
90% of Esat Telecom’s fibres being placed into service, it has a right of
first refusal to lease the fifth pair.
13. To
the extent that these fibre pairs have not been offered pursuant to the above
schedule, Esat Telecom also enjoys a right of first refusal respectively upon
the tenth, fourteenth, fifteenth, sixteenth and seventeenth anniversary of the
Licence Agreement for the lease of one B fibre pair at a time. If Esat Telecom
does not exercise its right of first refusal within 60 days, then CIÉ is
free to lease or sell these fibre pairs to third parties
Under
Clause 6.10, on termination of the agreement, CIÉ retains the ownership
of the cable. However, CIÉ is not free to place the cable in service on
its own account or to offer it to third parties without offering first to Esat
Telecom the lease of the entire cable network for the remaining useful life.
This provision does not apply if the agreement is terminated because of Esat
(clause 5 defines the events of default).
14. Finally,
pursuant to Annex 8 of the agreement as originally notified, CIÉ could
not install or permit the installation of any other telecommunications cable on
its property prior to the conclusion of the works relating to the construction
of Esat Telecom’s network pursuant to the Construction Agreement.
Thereafter, it had to give notice to Esat Telecom before it allows the
installation of any other cables. The period of notice decreased in accordance
with the degree to which Esat Telecom’s network had already been
installed, tested, debugged and had its spur lines and customer connections
installed. The minimum notice period required was to be twenty months at its
greatest, that is if the other cable were laid within a year of the conclusion
of the works. At its least, the minimum notice would be seven days, if the
other cable were laid five years or more after the conclusion of the works.
15. The
Construction and Maintenance Agreements do not contain any restrictions on the
parties in relation to their freedom to take independent commercial decisions
and are simply straightforward subcontracting and service arrangements.
The
Supplemental Agreement
16. This
agreement was also notified to DGIV of the European Commission. In the course
of the notification procedure, the parties, according to the Commission,
clarified the formulation contained in the original agreement in order to
address possible concerns about the nature of the access rights granted to
Esat. Consequently the parties entered into a Supplemental Agreement. This
involved the deletion of the original Annex 8 to the agreement, and its
replacement by a new version. Under the new version of Annex 8, CIÉ may
install or permit the installation of other telecommunications cables for third
parties provided that, in the period from the date of conclusion of the
agreement to 31 March 2001 (the priority period) Esat Telecom will be granted
priority access over CIÉ infrastructure for the purposes of deploying
and putting into service of its network.
17. On
making a determination to install or permit the installation of cable for third
parties, CIÉ is to give Esat Telecom two months’ written notice of
its intentions. If Esat Telecom determines on reasonable grounds that such an
installation is likely to hinder or delay the completion of its own network,
the installation of the third party cable shall be postponed until the end of
the priority period.
18. Notwithstanding
the foregoing provisions, CIÉ is entitled:
-
to permit the installation of telecommunications cable merely for the purposes
of crossing its infrastructure;
-
to maintain and permit the maintenance of telecommunications cables in place,
of the kinds and to the extent to which it is obliged pursuant to the
agreements to which it is already party;
-
to permit the installation of other cable if and to the extent that the
installation thereof on CIÉ’s infrastructure is the only possible
means whereby a telecommunications network can be constructed.
(e) Submissions
of the Parties
Submissions
in support of the issue of a certificate
19. The
parties submitted that the arrangements did not have the object and would not
have the effect of preventing, restricting or distorting competition. They were
a direct response to the liberalisation of alternative infrastructure in
Ireland. By enabling Esat Telecom to construct its own high-capacity network,
the arrangements would allow it to compete more effectively on the market by
ending its dependency on the incumbent operator for its backbone network.
Moreover, Esat Telecom would now be able to meet the increasing demand for high
speed broadband digital communications in Ireland.
20. The
parties submitted that the arrangements would not affect the competitive
position of third parties, as the market for bandwidth in Ireland was still in
its infancy and there was enough room for the development of alternative
networks. Moreover, CIÉ was not precluded from granting further similar
licences to other operators, as the licence it had granted to Esat Telecom was
non-exclusive. In addition, third party operators would be able to benefit from
an alternative source of bandwidth from Esat Telecom and would no longer have
to rely only on Telecom Eireann.
21. The
parties also made submissions in support of their request for a licence. As
these are not considered relevant to the decision, they are not reproduced here.
(f)
Submissions
of Third Parties
22. OCEAN,
a telecommunications joint venture between British Telecom and the Electricity
Supply Board of Ireland, submitted that the effect of the agreement would be to
prevent, restrict or distort competition in the telecommunications market in
Ireland. OCEAN understood that the first cable (“the CIÉ
cable”) was wholly owned by CIÉ, and that the other (“the
Esat cable”) was the subject of an agreement between Esat and CIÉ,
although CIÉ did have access to capacity on six fibres of that cable.
23. OCEAN
stated that in June 1998 it had opened discussions with CIÉ concerning
business arrangements for leasing fibre capacity on CIÉ’s
telecommunications infrastructure. No substantive progress had been made since
then in engaging CIÉ in meaningful negotiations. CIÉ had now
communicated to OCEAN that for “operational and engineering
reasons” it was not in a position to proceed with these discussions.
OCEAN understood that these perceived difficulties related to the utilisation
of the CIÉ cable for railway signalling purposes and for carrying the
traffic of external telecommunications operators. Given the capacity of fibre
cable, OCEAN could not understand the basis for these objections. While OCEAN
accepted that there might possibly be operational reasons for
CIÉ’s refusal to negotiate at that time in relation to the
CIÉ cable, it could only conclude that there was some form of
exclusivity in the agreement with Esat which prevented CIÉ from
utilising the spare capacity on the Esat cable.
24. OCEAN
believed that the Competition Authority should take into account the concerns
of the European Commission in a similar case relating to an agreement between
Cegetel, SNCF and Telecom Développement. It appeared that following the
intervention of the Commission, the clauses governing guarantees of
“priority right of access” to SNCF land for the purposes of
installation of the network were clarified to ensure that SNCF would be able to
make any remaining capacity available to other network operators. OCEAN argued
that the concerns of the European Commission in that case were equally
applicable in this instance, and that any clause with a similar effect in the
agreement between CIÉ and Esat fell within the prohibition in
section
4(1) of the
Competition Act and was not eligible for a licence. One of the main
obstacles to full competition in the telecommunications sector was the lack of
infrastructure which was not controlled by the incumbent. A nation-wide network
such as that which had been constructed on CIÉ’s network should
not be reserved for the use of a single telecommunications operator. OCEAN
believed that the fact that CIÉ controlled nation-wide wayleave rights
meant that it was in a unique position from the point of view of a network
operator who wished to achieve rollout of a national network in as short a time
as possible. Theoretically, there were other entities in Ireland which had
alternative networks which could be used for network rollout by
telecommunications operators. This fact had been alluded to in the Commission
decision IV/M.1132
BT/ESB/AIG
in which the Commission gave its approval to the joint venture agreement
between OCEAN’s parent companies. OCEAN quoted paragraph 17 of that
decision which stated that:
“The
necessary infrastructure made available to Newco [OCEAN] by the ESB is equally
available from other sources as demonstrated by Esat Telecom’s joint
venture with CIÉ, or the availability of the infrastructure of Bord
Gáis.”
25. OCEAN
argued that the infrastructure made available to it under the agreement with
the ESB was not equivalent to CIÉ’s rail network. Firstly, the ESB
did not have the ability to grant wayleave rights as CIÉ did, and
therefore the rollout of a network on the ESB lines was subject to obtaining
prior agreement from a very large number of landowners. OCEAN had no legal
powers to compel these landowners to grant it any necessary wayleaves.
Secondly, the agreement between Esat and CIÉ had now been in operation
for some time and a large amount of fibre had already been laid. Hence,
capacity on this telecommunications infrastructure would be immediately
available to OCEAN, and other licensed operators, but for the restrictions
which OCEAN believed to have been placed on CIÉ by Esat by virtue of
their agreement.
26. For
the above reasons, OCEAN argued that CIÉ was in a dominant position in
the provision of telecommunications infrastructure in Ireland of the type
defined in the Commission’s decision on
BT/ESB/AIG,
as quoted above, and that its effective refusal to negotiate with OCEAN for the
use of that cable network was an abuse of that dominant position. OCEAN
believed that any clause of the agreement which gave any form of exclusivity to
Esat in relation to the Esat cable was not eligible for a licence under
Section
4(1) of the
Competition Act, 1991, that any spare capacity on this type of
cable should be made available, on an open and transparent basis, to other
telecommunications operators, and that exclusive agreements such as that
between Esat and CIÉ should not be permitted to inhibit the rollout of
network in the telecommunications industry.
(g) Other
Relevant Issues.
Competition
Authority report of investigation of the Eircell proposal to
locate
antennas at Garda sites/masts
27. In
its 1998 “Report of Investigation of the Eircell proposal to locate
antennas at Garda sites/masts”, the Authority stated its views on the
practice to be adopted in granting competing utility operators access to State
owned facilities
as
follows:
-
State organisations should be free to enter into commercial transactions with
any/all entrants, subject to general principles of competition law;
-
State organisations should award access to their facilities to the entrant who
offers them the most advantageous terms and therefore these organisations
should encourage competitive bidding for access to facilities;
-
State organisations should avoid entering into any arrangements with an entrant
which would have the effect of restricting their ability to fully exploit the
commercial potential of their facilities; therefore, for example, they should
not enter into any agreement that prevents them from selling available capacity
to any potential bidder or prevents them from making that potential capacity
available.
28. The
Authority therefore concluded that the essential facilities doctrine should not
be applied to the Garda masts and that a key element in the Eircell proposal,
that provides for equal access to every Garda site, should be opposed. The
Authority formed the view that access to Garda sites should be determined by
the Garda Síochána, who should be free to enter into profit
maximising commercial transactions with any/all entrants, subject to general
principles of competition law.
Commission
Decision on Telecom Développement
29. In
a Decision of June 1999 (IV/36.581 - Télécom
Développement), the Commission found that it had no grounds for action
under Article 81(1) of the EC Treaty in respect of notified agreements relating
to the co-operation between
Société
Nationale des Chemins de Fer
and
Cégétel
through their joint subsidiary
Télécom
Développement.
Under
the agreements, Cégétel, a new telecommunications operator in
France, and SNCF, the French national railroad company, co-operated through a
jointly-owned subsidiary, Télécom Développement (TD), to
develop and run a national long-distance telecommunications network along the
French national railway network. In an agreement concluded on 22 November 1996,
SNCF granted TD a non-exclusive right to occupy public railway land for a
period of thirty years, to allow it to deploy a telecommunications network. In
order to enable TD to complete the installation of its network in the shortest
possible time, SNCF also granted it a “priority right of access” to
SNCF’s land, guaranteed by a penalty clause applicable for a period of
three and a half years, from 1997 to 2000.
30. On
18 March 1998, the Commission informed the parties that it considered the
clause governing the priority usage of railway premises by TD as falling within
the scope of Article 81(1) of the EC Treaty and that, as it stood, it was not
eligible for an exemption under Article 81(3). On 20 April 1998, the parties
proposed amending the clause in question in order to clarify the scope and
practical application of the priority access granted to TD, and thus to spell
out clearly the conditions under which the penalties provided for in the
agreement would be applicable. Taking into account the Commission’s
observations, the parties introduced on 31 July 1998 an amendment to the
original agreements by means of which they foresaw (i) an equal treatment for
third parties in those exceptional cases where the railway infrastructures in
question were the only possibility for putting in cables (narrow valley
structures) and (ii) that SNCF or its successor organisation, RFF, remained
free to give access to the railway infrastructures to other telecommunications
operators, provided that this could be done without interfering with the
development of TD’s own network.
31. The
Commission considered that these amendments allowed SNCF to give access to its
infrastructures to other operators, provided that this could be done without
interfering with the development of TD’s own network. Furthermore, the
Commission considered that the priority period was limited to the minimum
period required to implement the network (1997 - 2000), and there was an
explicit understanding that the priority rights would not apply in the event of
other companies seeking access to specific portions of railway-owned land if
the installation of cables on these sites was the only way of creating a
telecommunications network.
Commission
Decision on Esat/CIÉ
32. On
12 October 1999 the Commission issued a comfort letter in respect of the
Esat/CIÉ agreement, as amended by the Supplemental Agreement.
Assessment
(a)
Section
4(1)
33.
Section
4(1) of the
Competition Act, 1991, as amended, states that ‘All
agreements between undertakings, decisions by associations of undertakings and
concerted practices, which have as their object or effect the prevention,
restriction or distortion of competition in trade in any goods or services in
the State or in any part of the State are prohibited and void.’
(b)
The
Undertakings and the Agreement
34.
Section
3(1) of the
Competition Act defines an undertaking as ‘a person, being an
individual, a body corporate or an unincorporated body engaged for gain in the
production, supply or distribution of goods or the provision of a
service.’ CIÉ and its subsidiary, Iarnród Éireann
are engaged for gain in the provision of passenger and freight transport
services within the State and are undertakings. Esat Telecom is engaged for
gain in the provision of telecommunications services within the State and is an
undertaking. The agreement is an agreement between undertakings and has effect
within the State.
(c)
Applicability
of Section 4 (1).
35. In
relation to the general principles to be followed in granting competing utility
operators access to State-owned facilities, the Authority’s views have
been set out in paragraphs 27-28. In line with this reasoning, the Competition
Authority would not regard access to CIÉ/Iarnród
Éireann’s property in order to lay cable as an essential facility.
The Authority would, however, take the view that CIÉ/Iarnród
Éireann should not grant exclusive access to its infrastructure and
thereby limit its freedom to enter into profit-maximising commercial
transactions with other operators. The Authority considers that Annex 8 of the
contract as originally notified, which required CIÉ to give up to 20
months’ notice to Esat before allowing the installation of any other
cables, would in effect have limited CIÉ’s freedom in this respect
and would have contravened
Section 4(1).
36. The
amendments proposed by Esat in its letter to the Commission of 30 November 1998
would appear to meet the concerns about third parties’ access to
Iarnród Éireann premises which arose from the restrictive clauses
of the original contract. They are also in line with the Commission’s
decision in the Telecom Dévéloppement case in that they allow
CIÉ to give access to its infrastructures to other operators, provided
that this can be done without interfering with the development of Esat’s
own network. Furthermore, the Authority considers that the priority period is
limited to the minimum period required to implement the network (from the
conclusion of the agreement to 31 March 2001). The revised version of Annex 8
also makes clear that the priority rights would not apply in the event of
other companies seeking access to CIÉ’s infrastructure if the
installation of cables on these sites was the only way of creating a
telecommunications network.
37. Clause
3.5 of the agreement concerns Esat’s right of first refusal over the
“B” fibres, and clause 6.10 concerns the post-termination rights of
Esat Telecom (i.e. the requirement on CIÉ not to place the cable in
service on its own account or to offer it to third parties without offering
first to Esat Telecom the lease of the entire cable network for the remaining
useful life). The Competition Authority’s view is that both these
arrangements are an integral part of the commercial transaction between Esat
Telecom and CIÉ/Iarnród Éireann, and one which does not
prevent, restrict or distort competition in the market for the terrestrial
provision of long-distance transmission services. Effectively, Esat and
CIÉ have negotiated a payment in kind - access to cable pairs - for the
services provided by CIÉ to Esat. Since Annex 8 has been amended, other
operators are not precluded from laying cables on CIÉ’s
infrastructure. The Authority therefore considers that these clauses do not
contravene
Section 4(1).
38. The
Authority has therefore concluded that the arrangements do not have as their
object or effect the prevention, restriction or distortion of competition in
trade in goods or services in the State or in any part of the State, and do not
contravene
Section 4(1).
The
Decision
39. In
the Authority’s opinion, CIÉ, Iarnród Éireann and
Esat Telecommunications Ltd. are undertakings within the meaning of
Section
3(1) of the
Competition Act, 1991, as amended, and the notified agreement is an
agreement between undertakings. In the Authority’s opinion, the notified
agreement does not have the object or effect of preventing, restricting or
distorting competition and thus does not contravene
Section 4(1) of the
Competition Act.
The
Certificate
The
Competition Authority has issued the following certificate:
The
Competition Authority certifies that, in its opinion, on the basis of the facts
in its possession, the non-exclusive licence agreement and supplementary
Construction and Maintenance agreements dated 31 July 1998 between CIÉ,
Iarnród Éireann and Esat Telecom, notified under
Section 7 of the
Competition Act on 20 August 1998 (notification no. CA/8/98) does not
contravene
Section 4(1) of the
Competition Act, 1991, as amended.
For
the Competition Authority,
Isolde
Goggin,
Member
28
January 2000