[2004] EWLands LCA_38_1999 (14 April 2004)
LCA/38/1999
(consolidating LCA/34-38/1999)
LANDS TRIBUNAL ACT 1949
COMPENSATION – mining subsidence – damage to sewers – limitation – preliminary issue – knowledge of subsidence damage – whether facts from which claimant might reasonably have been expected to acquire knowledge were observable or ascertainable by it more than six years before damage notice given – Coal Mining Subsidence Act 1991 s 3 – burden of proof – approach of sewerage authority to identification of damage – claimant held to have failed to show that it could not reasonably have been expected to acquire requisite knowledge
IN THE MATTER of a NOTICE OF REFERENCE
BETWEEN
SEVERN TRENT WATER LIMITED
Claimant
and
THE COAL AUTHORITY
Compensating
Authority
Re:
Sewers at
(i) Waterfield Farm, Old Clipstone,
Nottinghamshire
(ii) Greenwood Drive, Kirkby in Ashfield,
(iii) Beauvale Road, Hucknall,
Before: The President and N J Rose FRICS
Sitting at 48/49 Chancery Lane, London WC2A 1JR
on 17-19 and 25-27 November and 4 December 2003
The following cases are referred to in this decision:
Crocker v British Coal Corpn (1995) 29 BMLR 159
Gascoine v Ian Sheridan & Co [1994] 5 Med LR 437 at 441
The following further cases were also cited:
Liddell v Middleton CA 7 July 1995, unreported.
Spencer-Ward and Another v Humberts [1995] 1 EGLR 123
Glaister v Greenwood [2001] PNLR 602
El Ajou v Dollar Land Holdings Plc and Another [1994] 2 All ER 685
Davie v Edinburgh Magistrates [1953] SC 34
Richard Harding, instructed by Kent, Jones and Done of Stoke-on-Trent for the Claimant
Paul Darling QC, instructed by DLA of Sheffield for the Compensating Authority
DECISION ON PRELIMINARY ISSUES
Introduction
(i) Waterfield Farm, Old Clipstone ("Waterfield Farm")
(ii) Greenwood Drive, Kirkby in Ashfield ("Greenwood Drive")
(iii) Beauvale Road, Hucknall ("Beauvale Road").
"For each of the references did the claimant have the knowledge, as defined by section 3(4) of the Coal Mining Subsidence Act 1991 ("the 1991 Act"), required for founding the claim made in that reference, more than six years before notice in respect of that claim was given to the Compensating Authority under section 3 of the Act?"
"(3) The period allowed by this section for giving a damage notice with respect to any subsidence damage is the period of six years beginning with the first date on which any person entitled to give the notice had the knowledge required for founding a claim in respect of the damage.
(4) For the purposes of subsection (3) above, the knowledge required for founding a claim in respect of any subsidence damage is knowledge –
(a) that the damage has occurred; and
(b) that the nature of the damage and the circumstances are such as to indicate that the damage may be subsidence damage;
and a person's knowledge includes knowledge which he might reasonably have been expected to acquire from the facts mentioned in subsection (5) below.
(5) Those facts are –
(a) any facts which were observable or ascertainable by him; and
(b) any facts which would have been ascertainable by him with the help of any expert advice which it was reasonable for him to seek."
Waterfield Farm | 8 February 1994 |
Beauvale Road | 7 August 1995 |
Greenwood Drive | 7 August 1995 |
Waterfield Farm | 1985/86 |
Beauvale Road | 1982/83 |
Greenwood Drive | 1976/77 |
Waterfield Farm | 8 February 1988 |
Beauvale Road | 7 August 1989 |
Greenwood Drive | 7 August 1989 |
The statutory provisions and the burden of proof
"The burden on the plaintiff is to show, on the balance of probabilities, that her cause of action came into existence on a day within the limitation period. Once that is demonstrated then the evidential burden moves to the defendants – they in turn must demonstrate that, in truth the cause of action arose at some earlier date by virtue, for example, of constructive knowledge on the part of the plaintiff: Nash v Eli Lilly & Co ((1992) 14 BMLR1 at 13, [1993] 1 WLR 782 at 796)."
"It is clear from the reference to the effect of constructive knowledge that Mitchell J is, as a matter of shorthand although not strictly accurately, speaking of knowledge under s 11 as if it were an element in the accrual of the cause of action. His first sentence therefore reaffirms the legal burden on a plaintiff to prove that knowledge (where material) only arose within the three years preceding the writ. His second recognises that an evidential burden may exist on a defendant to rebut the plaintiff's case, by, for example, adducing evidence to show (no doubt after pleading) constructive knowledge.
Taking this as the correct interpretation of Mitchell J's summary, there is in my judgment much to be said in favour of the analysis which it adopts. The legal burden rests throughout on the plaintiff, whether the issue is when the cause of action accrued or when the plaintiff first had knowledge of the facts in the sense identified in s 14. The concept which the authorities have called 'constructive knowledge' is by definition in s 14(3) one aspect of 'knowledge'. The date of first knowledge depends as much on knowledge which the plaintiff might reasonably have been expected to acquire from (a) facts observable or ascertainable by him or (b) ascertainable (subject to the proviso) by him with the help of medical or other appropriate expert advice as it does on actual knowledge. An issue arising under s 14(3) is, however, apt to involve an evidential burden on a defendant, at all events if there is nothing in the plaintiff's own case or evidence to raise the issue, although in some respects, for example in relation to the words 'so long as he had taken all reasonable steps to obtain (and, where appropriate, act on) that advice' in the proviso where they became material, it may be easy to envisage both the legal and an evidential burden on a plaintiff."
Evidence of witnesses
1984-1994 | 261 DASs covering strategic sewers in systems serving populations over 10,000 |
1990-1995 | 80 Rural Asset Management Plan Studies (RAMPS) covering strategic sewers in all areas not included in the DAS studies. |
1995-(2005) | 341 Drainage Area Maintenance Studies (DAMS) revisiting both the DAS and RAMPS studies. |
Waterfield Farm
a. Newlands Road claim.
The damage was 1.8 km from the closest part of the Waterfield Farm sewer, resulted from completely different mining and pre-dated the last mining to have undermined the Waterfield Farm sewer.
b. Mansfield Road claim.
The damage was 1.4 km from Waterfield Farm, resulted from completely different mining and pre-dated the last mining to have undermined Waterfield Farm.
c. Squires Lane claim.
The damage was 310 m from Waterfield Farm and resulted from completely different mining.
d. Forge Bridge claim
The damage was almost contiguous with Waterfield Farm, although the damaged lengths were over 1 km apart. It resulted from completely different mining and its discovery resulted from the DAS which failed to discover damage to Waterfield Farm. This claim led to the investigations which located damage at Waterfield Farm but was within 6 years of the Waterfield Farm damage notice.
e. 15 inch water main claim.
The damage was 375m from Waterfield Farm, resulted from completely different mining and was on a pressure main, which behaved differently from a sewer.
f. 3 inch water main claim
The damage occurred within six years of the Waterfield Farm damage notice, and was therefore irrelevant.
Beauvale Road
a. Tiverton Close claim.
The damage was 0.5 km from the closest part of the Beauvale Road sewer, resulted from completely different mining from that which caused the sewer damage at Beauvale Road and pre-dated the last mining to have undermined the Beauvale Road sewer.
b. Whyburn Lane No.4 reservoir claim
The damage was 0.4 km from the closest part of the Beauvale Road sewer, resulted from completely different mining and pre-dated the last mining to have undermined the Beauvale sewer.
c. Beauvale Estate claim
This was not a claim of which STW had any notice and British Coal at that time had concluded that the damage was not the result of coal mining subsidence.
Greenwood Drive
a. West Kirkby claim
The previous claim did not cover the sewers in Lawrence Avenue and Greenwood Drive, which formed the current claim. It related to part of a sewerage system flowing in the opposite direction to the sewers in the Greenwood Drive claim. The damage which caused the current claim was either present at the time of the West Kirkby scheme or it was not. If it was present, it had not "occurred" within the meaning of the contemporary 1957 Act and therefore no claim was possible under that Act. The earliest time that a claim could have been made under the 1991 Act was 7 August 1989. The current damage notice was served within six years of that date.
"Further to our meeting held on 2 July 1997, as agreed please find the reason why the authority considers this claim statute barred. As explained in the meeting, the reason for rejection was that the authority consider Severn Trent Water to have reasonable knowledge of the mining six years prior to the submission of the damage notice. In reaching this conclusion consideration was given to the following facts:
The last mining to affect the upstream end of the sewer was in 1986 and the downstream end in 1982, some 8 and 12 years before submission of the damage notice. Investigations revealed that other claims in close proximity to this one had been submitted at various times between 1982 to 1990, one claim for Squires Lane sewer was surveyed up to the manhole where this claim joins that run. Accordingly it is considered that Severn Trent Water were aware of mining in this area and, under the 1991 Act, as a person who would have had reasonable knowledge, should have investigated the sewers at that time, when any subsidence damage would have been evident."
"The area of Greenwood Drive was subject to a claim under the provisions of the Coal Mining (Subsidence) Act 1957 and dated 04/07/1979. It was submitted by Ashfield District Council as agents to Severn Trent Water.
The claim was discharged by the National Coal Board by payment for repairs which were incorporated in the West Kirkby Subsidence Remedial Works Scheme.
The Mining Reports Office have indicated that no mine workings have affected the area of the claims since 1976.
The Coal Authority is of the opinion that a reasonable body such as Severn Trent Water were aware of mine workings in the Greenwood Drive area in 1979 and any damage evident resultant from those workings would now be statute barred and therefore I am unable to recommend that any liability is accepted."
"The investigations have confirmed that there is no evidence that any coal mining subsidence damage has occurred within the relevant limitation period for making claims. All mining activity in the vicinity of the sewer ceased in 1984."
a. Newlands Road.
Claim on 10 April 1984. This related to the trunk sewer along Newlands Road, upstream of the current claim. British Coal paid £38,395.73 in about March 1993. STW accepted this sum in settlement in February 1994.
b. Mansfield Road
Claim on 12 July 1984. A supporting drawing showed details of a survey which extended towards the trunk sewer and the current claim. Settled in February 1994 for £56,156.
c. Squires Lane
Claim on 14 October 1987. The sewer from Squires Lane connected with the trunk sewer at manhole 490 and the sewer length between manhole ("MH") 490 and MH 690 was surveyed for both claims. Settled in June 1994 at £52,020.10
d. Trunk Sewer between River Maun and Railway
Claim on 18 October 1990. Immediately downstream of the current claim and along the same trunk sewer. Settled in December 1993 at £68,086.43
e. 3 inch public water main between Clipstone Pumping Station and Waterfield Farm.
Claim on 5 May 1988. Settled in September 1989 for £193.82.
f. 15 inch public water main opposite Clipstone Pumping Station.
Claim on 20 April 1987. Settled in August 1987 at £4,098.02.
a. No.4 Reservoir, Whyburn Lane, Hucknall
Claim in 1982. Immediately adjacent to that part of current claim relating to Whyburn Lane. Claim accepted and damage to reservoir repaired.
b. Tiverton Close
Claims in March 1978, July 1980 and June 1981.
c. Beauvale Estate
Claim by ADC on 11 May 1987. An STW hydrologist attended a meeting with representatives of ADC at which mining subsidence was discussed as a possible cause.
d. ADC housing claims
A number of claims submitted. Limited information available, but repairs undertaken included drains.
e. Other claims to damaged kerbs and 4 inch water main at Common Lane. No detailed information available.
a. Greenwood Drive
Claim on 4 July 1979. This related to sewers for Greenwood Drive, Berry Avenue, Highfield Avenue and the rear of Willow Street. The damage notice did not exclude any specific lengths of sewer within the streets named.
b. Sewers in the Kirkby area. A letter dated 17 January 1979 from NCB to Ashfield DC accepted liability for a number of lengths of sewers in the Kirkby area. This related to the sewers on Berry Avenue/Greenwood Drive and Highfield Avenue/Greenwood Drive and also Station Road/Copeland Road, Banks Avenue, The Hill/Victoria Road, Lime Tree Avenue and Chestnut Avenue.
c. West Kirkby Subsidence Remedial Work. A letter dated 5 April 1982 from Ashfield DC to NCB identified that works had commenced in relation to Berry Avenue, Greenwood Drive, Highfield Avenue and Lime Tree Avenue.
d. Main Drainage System to west of Kirkby. An NCB expenditure sheet dated November 1980 indicated that the main drainage system to the west of Kirkby had been investigated by the local authority as agent for STW.
e. Frederick Avenue. Damage notice dated 23 December 1976, relating also to Copeland Road and Sutton Road.
Type of failure | Cause | Prevention |
Beam fractures | Uneven resistance of foundations or soil movement, or differential settlement. Caused by mining in extreme cases of shallow workings. | Flexible joints and uniform hardness of foundation. |
Pull fractures | Thermal or drying shrinkage of pipe, or site concrete, drying shrinkage or clay soil. Extension of ground through mining. | Flexible telescopic joints and gaps in site concrete and pipe joints. |
Shear fractures | Differential settlement of wall relative to pipe or vice versa. Can be caused by fissuring in subsided ground. | Flexible joints at a and b and making ab not more than 1m. |
Thrust fractures | Restrained thermal or moisture expansion of pipe or compression due to subsidence. | Flexible telescopic joints. Spigot End not laid hard up in socket |
Leverage fractures | Excessive angular displacements. Extreme cases of differential subsidence. | Flexible joints. Avoidance of excessive slew when laying. |
"(a) Identify panels which had been worked during the preceding year;
a. identify the zone of influence around that year's mining in respect of each panel (based on 0.7 x depth);
b. identify one or more sewers within each panel most likely to be adversely affected by subsidence (generally those crossing the downstream rib side of the panel);
c. determine the pre-and post-subsidence profile of the sewer by reference to the SEH;
d. estimate the maximum anticipated ground strain induced by each panel by reference to the SEH."
Conclusions
The general approach to the identification of damage
Complaints and the absence of complaints
"The public will complain to the local authority, saying: 'There is a terrible smell of the drains round here. Can you come and inspect?' What has generally happened is that the sewage is not flowing through the sewer any more and that may be because there is a lack of gradient or back fall or the sewer has been damaged, and that could be by mining or it could be by other causes, tree roots or other works or simply the age of the sewer, or it could be blocked by some material that has got into the pipe.
So there might be smells resulting from that or alternatively that can also lead to flooding of property, because if the sewer is blocked and more sewerage is coming down, ultimately, particularly if there is heavy rain, then the sewer can back up either in houses or on to land, and then that will be again reported to the local authority.
The local authority will come out to investigate. What they will do is clear the blockage. They will jet out what is there, because it is usually a blockage that they will find. If they see there is damage or there is obviously a hydraulic problem, then they will report that and come back and carry out surveys, but what generally happens is that they clear the incident and leave it and wait to see what happens, because the majority of incidents will be isolated ones and will not run on, or if they do, it will not be for a number of years, but if they encounter a number of complaints about a particular area, then they will go and carry out more detailed investigations as to what is the cause of those problems, and that will involve them carrying out a CCTV and levelling surveys."
"Q. Now can we then, please, go forward to Beauvale and Greenwood? Now, I wonder if I can just try to cut matters short. We know that both of these areas of problem were discovered from a pilot CCTV survey.
A. Yes.
Q. Is there any reason, so far as you are concerned, technically why such a survey could not have been carried out years earlier?
A. Technically, no.
Q. Now you nevertheless think that it was not reasonable, or nor reasonably necessary, to carry out such an investigation?
A. We are dealing with Greenwood Drive and Beauvale Road together, are we?
Q. They were dealt with by the same pilot CCTV survey.
A. Precisely, so we are dealing with them. The answer to the question is no, because there is no evidence of complaints.
Q. Essentially the debate between you and I comes down, does it not, to the presence of or absence of complaints?
A. Precisely."
Waterfield Farm
"When deciding when the various sewers were to be the subject of a DAS, we gave priority to areas where we knew mining was taking or had taken place, as these were more likely to be in need of work."
Beauvale Road and Greenwood Drive
Dated 14 April 2004
George Bartlett QC, President
N J Rose, FRICS
Addendum on costs
Dated 16 June 2004
George Bartlett QC, President
N J Rose FRICS