[2003] EWLands LCA_37_2002 (16 May 2003)
LCA/37/2002
LANDS TRIBUNAL ACT 1949
COMPENSATION – preliminary issue – Land Compensation Act 1973 Part I – house affected by road traffic noise – whether claimant owner at relevant date – whether claim statute-barred – held claimant not entitled to make claim
IN THE MATTER of a NOTICE OF REFERENCE
BETWEEN HARRY PETER OWEN Claimant
and
HIGHWAYS AGENCY Compensating
Authority
Re: A2070 Sevington
Waterbrook Park to M20
Before: The President
Sitting at 48/49 Chancery Lane, London WC2A 1JR
on Wednesday 7 May 2003
Andrew Sharland instructed by the Treasury Solicitor for the compensating authority
The claimant did not appear and was not represented
The following case is referred to in this decision:
Bateman v Lancashire CC [1999] RVR 125
DECISION ON A PRELIMINARY ISSUE
"(1) Subject to the following provisions of this paragraph, the Secretary of State is the responsible authority for the purposes of Parts I and II of the Land Compensation Act 1973 (compensation for, and mitigation of, injurious effects of public works) as respects the Concessionaires' scheduled works and any other works of the Concessionaires authorised by this Act (including the construction or alteration of any highway).
(2) Where a claim under Part I of that Act relates to depreciation caused by use of the road forming Work No. 17–
(a) if and so far as it relates to depreciation that would not have been caused but for the opening to public traffic of Kent County Council’s scheduled works, that Council shall be the responsible authority in relation to it; and (b) if and so far as the Secretary of State is the responsible authority in relation to it, no account shall be taken in assessing compensation of any use or expected intensification of use of that road due to that opening.
(3) If and so far as the Kent County Council are the responsible authority in relation to a claim under that Part of that Act by virtue of sub-paragraph (2)(a) above, that Part of that Act shall have effect in relation to the claim as if—
(a) the relevant date were the date on which all of their scheduled works were first open to public traffic; (b) the increase in value to be taken into account under section 6 were any increase that would not have been caused but for the opening to public traffic of those works; and (c) subsection (1) of section 8 did not preclude the payment of compensation unless the previous claim was in respect of depreciation that would not have been caused but for that opening and subsection (2) of that section did not preclude the payment of compensation."
"I can now advise you that the following discussions between the Highways Agency based in Dorking and this Department, the Highways Agency has agreed to accept and process all the outstanding claims relating to the A2070 Junction 10/M20 to Waterbrook Park. This decision is without prejudice to any future decision as to whether or not any compensation should be settled on the claims in question.
Furthermore our legal advice is that there may be two responsible authorities, Kent County Council in relation to one element of the claim and the Secretary of State in respect of the remaining element. The Highways Agency will no doubt consider whether or not this is the position and will contact your Council in due course.
As to the number of claims involved, I understand that Mr Wood has forwarded 49 claims to the Highways Agency which refer to 'Alterations' to the A2070 Junction 10/M20 to Waterbrook Park and he will also forward the remaining claims which relate to the Stage 1 works. I believe that there are at least 19 outstanding claims in this last batch."
(a) The claimant did not have an interest qualifying him for compensation in relation to Work No 17, but he did have such an interest in relation to Work No 17A.
(b) The claim against the compensating authority in respect of these works is statute-barred.
The claimant was accordingly not entitled to make the reference, which must be dismissed.
16 May 2003
George Bartlett QC, President