[2001] EWLands LCA_44_1997 (7 June 2001)
LCA/44/1997
LANDS TRIBUNAL ACT 1949
COMPENSATION – Damage caused to bungalow close to new sewer and trees – whether damage caused by works connected with sewer or by trees acting on clay beneath foundations – Held sewer works to blame – Public Health Act 1936, s.278.
IN THE MATTER of a NOTICE OF REFERENCE
BETWEEN JACK LUMB Claimant
and
UNITED UTILITIES WATER LIMITED Respondent
(formerly NORTH WEST WATER LIMITED)
Re: "Dunwood",
Smallbrook Road,
Shaw, Nr Oldham,
Lancs.
Before: N J Rose FRICS
Sitting at: Manchester Combined Tax Tribunal,
9th Floor, West Point, 501 Chester Road, Old Trafford, Manchester M16 9HU
on 15 May 2001
Ruth Stockley, instructed by Jackson Brierley Hudson Stoney, solicitors of Rochdale for the Claimant.
Alan Evans, instructed by Mr T J Warn, solicitor with United Utilities Water Limited for the Respondent.
DECISION
"(1) Whether damage was caused to Dunwood by the laying of the Shaw Main Outfall Sewer; and
(2) If so, the extent of that damage."
"The external face of the brickwork to the right hand bay window (when viewed from the front) shows signs of fracturing and forward rotation away from the main structure. Separation between the right hand edge of the bay window frame and the adjacent brickwork has occurred and slight distortion to the front section of the right hand elevation brickwork is apparent. The brick courses on the front elevation are slightly out of level and dip towards the front outer corner adjacent to the bay window in question.
Internally, a ¼ " wide fracture has occurred at the top left hand corner of the bay window aperture in the bedroom and separation of the decorative wall and ceiling papers has occurred along the side wall of the bedroom. A vertical fracture was noted from the right hand edge of the bedroom window cill extending down to floor level. The bottom left hand pane of glass in the bay window was noted to be cracked.
A cracking pattern co-incident with the edges of the plasterboard sheets has developed to the bedroom ceiling with a gap now apparent of about 2mm in the centre of the bedroom ceiling."
"the construction of the tunnel in close proximity to the bungalow could have been the cause of the structural damage sustained."
"fissure in the clay surface appears to have been caused by settlement of the ground above the line of the tunnel and in my opinion this general earth movement is the cause of the structural damage now being sustained by your bungalow."
"There is therefore no evidence of any previous damage and consequently we cannot comment on whether that damage was as a result of the sewer works or not.
You will, however, observe from the photographs that the property, and particularly the right hand side of the property, is in very close proximity to the mature poplar and other trees and that area of the property could therefore have been affected by clay shrinkage, aggravated by tree root damage following the summer of 1989.
It must be said, however, that the line of the sewer when judging from the manhole in one of the photographs does run in very close proximity to the property and may, in fact, have been the cause of or a contributing factor in some if not all of the damage as alleged by the property owner.
… it may be that there was previous damage within the property resulting from tree root action and clay shrinkage, although it may be clutching at straws to suggest such a thing and in any event such damage would have been covered under general household insurance policies.
We note from a memo of 25 September 1992 that it is conceded that some settlement could have taken place around shaft number 9 shown in the car park in the enclosed photographs near the bungalow, due to loss of ground water while sinking the shaft.
… however, at the time of our visit all damage has now been remedied and with extensions at both the front and right hand elevations, the history of any damage has long since been covered up.
It is therefore impossible for us to say with any degree of certainty that the damage was or was not caused by tunnelling works.
It seems likely that the tunnelling could have contributed towards any damage which previously existed and this is certainly suggested in the memo of 25 September where it is conceded that some settlement could have taken place.
This may have aggravated a previously existing situation as Mr Stott from Oldham Borough Council has suggested at the time of his own visit that the cracks did not appear to be recent when examined in November 1989, immediately after the tunnelling which occurred during August/November.
This is all pure conjecture, however, as no damage was available for inspection at the time of our visit. Our report, therefore, is necessarily vague and unless we can have sight of any photographs which were previously taken of the damage we cannot comment further on the matter."
"I think the cracks were started by the action of the trees. When the building weakened, further vibration from the tunnel exacerbated the position. It is not possible to divide the damage between the two causes because I did not see it at the time."
Dated: 7 June 2001
(Signed): N J Rose
ADDENDUM
Dated: 7 June 2001
(Signed): N J Rose