[2001] EWLands ACQ_165_2000 (15 August 2001)
ACQ/162-5/2000
(heard together)
LANDS TRIBUNAL ACT 1949
COMPENSATION – compulsory acquisition of derelict properties in Bradford – ownership – rights of way – comparables – inadmissibility of Tribunal's decision on value of adjoining property – claimants' valuer's figures accepted
IN THE MATTER of a NOTICE OF REFERENCE
BETWEEN REHMAN & OTHERS Claimants
and
CITY OF BRADFORD METROPOLITAN Acquiring
DISTRICT COUNCIL Authority
Re: 234, 236, 238 & 240
Manningham Lane,
Bradford
Tribunal Member: P H Clarke FRICS
Sitting at Huddersfield
on 28 and 29 June 2001
The following cases are referred to in this decision:
Montgarret v Claro Water Board (1963) 15 P & CR 53
Khan(S) v Bradford Metropolitan District Council (2000) (unreported) (ACQ/132/2000)
Land Securities plc v Westminster City Council [1992] 44 EG 153
John Collins instructed by William Hicks & Partners, solicitors, for the claimants
Vincent Fraser QC instructed by Department of Legal and Democratic Services, City of Bradford MDC, for the acquiring authority
DECISION
FACTS
"Exteriors
The front slope of the roof of the terrace had originally been clad in slate but Nos.236 and 238 had been reclad in modern tiling, leaving open holes where the roof lights were intended to go. Nos.234 and 240 were completely unclad, with the roofing felt and tiling battens exposed. On the rear slope some of the original tiles were still in place but roughly 90% of the roof was unclad. The felt and battens were in place but there were extensive holes in them, not only at roof light positions but also where the felt had torn and ripped. Vegetation growth was common along the gutter line and also at the bases of the chimney stacks. The line of the roof was reasonably straight with slight sags between supporting walls.
The front wall of the terrace was reasonably plumb but with a slight tendency to bulge outwards at first floor level. Much of the masonry was smoke stained. There appeared to be a distinct hinge point in the terrace at the side of the door to no.240; a full height vertical crack was evident and, from the slope of the sills and lintels, subsidence had clearly taken place to the right of this crack. Elsewhere along the front wall, the first floor string course undulated somewhat indicating further, lesser subsidence. Vertical cracks were also evidence at the sides of the front doors and the bay window to No.238, indicating an outward movement of the more ornate masonry at these locations. There was also an opening up of the masonry joints at the front gable eaves corner of No.234.
The back wall of the terrace was similarly distorted with sloping sills and lintels. No.240 appeared to have had it's back wall built in it's entirety at some stage, leaving a toothed joint at the junction with No.238: the latter was now some 50-75 mm proud of No.240, indicating the amount of outward movement that had taken place in the original back wall. The hinge point on the front wall was also reflected on the back with a series of vertical cracks and fractured sills and lintels running down the wall close to the junction between Nos.238 and 240.
Interiors
Internally, access to the four properties was hampered by the condition of the structure. Horizontally, entry to virtually all of the houses could be gained via holes or roughly formed doorways in the separating walls. Vertically however, access was limited by the difficulty of finding a staircase in a safe condition. Safe staircases were found in one or other property to all but the attic level where the staircases had virtually collapsed, and this level could be inspected in one house only and then only from the half landing between the first and second floors.
Generally the interiors of these properties were derelict. Ceilings were in a state of collapse virtually everywhere, with plaster and ceiling laths either missing or hanging down, and with the plaster covings dropping, fallen or badly cracked. Floor joints thus exposed were seen to be badly damp stained throughout and extensively fire damaged in places. Wall plaster was frequently missing, leaving the studwork or brick work exposed. Severe vertical or diagonal cracks were evident in much of the internal brickwork. Floorboards were frequently missing. An extensive series of holes of the order of 1m diameter had been deliberately punched in virtually all internal walls and suspended timber floors.
Conclusions
Consideration of the defects observed in these properties shows four main structural problems:
1. Subsidence of all of these houses,
2. Outward movement of the front and particularly of the back walls, and their separation from the main cross walls;
3. General instability of the walls caused by the formation of large holes in the internal walls and floors.
4. Virtual dereliction of the properties following their abandonment and the fire damage."
Repairs to prevent further subsidence which would have been expected were the installation of piling and ground beams to support the walls off the quarry base, the installation of steel straps to tie the walls to the cross walls and floors and the rebuilding of the rear walls incorporating steel straps. The approximate costs of structural repairs was £125,000 for piling and ground beams and £52,000 for the stabilisation of walls. Temporary works to maintain the stability of the properties during these repairs would have been £10,000. All costs relate to the four subject properties.
CLAIMANTS' CASE
COUNCIL'S CASE
DECISION
"An arbitration award on the other hand is an arbitrator's opinion, after hearing the evidence before him of the rent at which the premises could reasonably have been let. The letting is hypothetical, not real. It is therefore not direct evidence of what was happening in the market. It is the arbitrator's opinion of what would have happened."
He concluded that the award was inadmissible because it had in itself insufficient weight to justify the exploration of otherwise irrelevant issues which its admissibility would require (see page 158).
In my judgment the same principle applies to the determination of value by another decision of this Tribunal. There are other reasons in this reference why I should have no regard to the decision in Khan. First, it is subject to appeal. The Council have been granted permission to appeal by this Tribunal. This appeal has not yet been heard by the Court of Appeal. Secondly, the comparable evidence before the member in Khan, on which he based his decision, is before me in these references and can be given direct consideration.
Rent | £ 3,000 | |
YP 5 years @ 20% | 2.99 | £ 8,970 |
Reversion to value of land & | ||
uneconomic building | £15,000 | |
PV of £1 in 5 years @ 20% | 0.402 | £ 6,030 |
£15,000 |
By an arithmetical coincidence the present value of the land plus an uneconomic building (before deferment) is the same as the settlement figure of £15,000.
No.234 (Khan (P) and Khan (N)) | £19,500 | (ACQ/165/2000) |
No.236 (Khan Mirza & Mirza) | £17,500 | (ACQ/164/200) |
No.238 (Khan (D)) | £17,500 | (ACQ/163/2000) |
No.240 (Rehman) | £22,500 | (ACQ/162/2000) |
A surveyor's fee under Rydes scale is payable to each claimant.
DATED: 15 August 2001
(Signed) P H Clarke
ADDENDUM
"Where … -
(a) …
(b) the Lands Tribunal is satisfied that a claimant has failed to deliver to the acquiring authority, in time to enable them to make a proper offer, a notice in writing of the amount claimed by him, containing the particulars mentioned in subsection (2) of this section;
the Lands Tribunal shall, unless for special reasons it thinks proper not to do so, order the claimant to bear his own costs and to pay the costs of the acquiring authority so far as they were incurred …., after the time when in the opinion of the Lands Tribunal the notice should have been delivered."
DATED: 11 September 2001
(Signed) P H Clarke