[2001] EWLands ACQ_161_2000 (15 August 2001)
ACQ/161/2000
LANDS TRIBUNAL ACT 1949
COMPENSATION – compulsory acquisition of derelict property in Bradford – comparables Council's valuer's comparables rejected in favour of settlement on adjoining property – compensation determined at £16,000
IN THE MATTER of a NOTICE OF REFERENCE
BETWEEN MOHAMMED ABDUL KHALIQUE
and
NATIONAL WESTMINSTER BANK PLC Claimants
and
CITY OF BRADFORD METROPOLITAN Acquiring
DISTRICT COUNCIL Authority
Re: 242 Manningham Lane,
Bradford
Tribunal Member: P H Clarke FRICS
Sitting at Huddersfield
on 28 and 29 June 2001
The claimants did not appear and were not represented.
Vincent Fraser QC, instructed by Department of Legal and Democratic Services, City of Bradford MDC, for the acquiring authority.
DECISION
FACTS
"Exterior
The roof had been re-covered with tiles but about 50% of this covering was missing as a result of a fire in the attic storey. The extension roof could not be seen although internal evidence in the form of collapsed ceilings suggested that it was in poor condition. The chimney stack leaned slightly.
The front wall was generally plumb and straight. Pointing was in poor condition and a mullion in one of the first floor windows was splitting apart at the base; the lintel to this window sloped. The woodwork over the shop front sagged and the attached gutter was rotten. A straight joint had been formed in the masonry at the junction with the neighbouring property and this had been newly pointed above first floor level; below this the pointing had fallen out leaving an open joint. The shop front was fully boarded over and could not be inspected.
Interior
Internally the property seemed to have been empty for some time and fire damage and subsequent water penetration had caused deterioration in the upper floors and staircases; consequently certain area were not entered for safety reasons.
The fire had occurred in the attic and much of this level was open to the sky. The staircase to this level had virtually collapsed and no entry was attempted. On the first floor the ceilings had collapsed in virtually every room. There were vertical cracks at the front and cross wall junctions and also at the junction of the back wall and the extension wall. On the ground floor the back room ceiling was sagging and there were vertical cracks in the party wall near its junction with the back wall and also at the side of the door between the back room and the hallway. The extension walls leaned outwards. The stairs between the ground and first floors were in a precarious condition although just usable; entry beneath them to the basement, however, was not attempted.
Conclusions
Consideration of the defects observed in this property shows three main structural problems:-
(i) Subsidence of the rear of the house and particularly movement of the two storey extension rotating downwards at the rear and away from the main house building;
(ii) Separation of the front wall and , to a lesser extent, the back wall from the main cross walls;
(iii) Virtual dereliction of the property following its abandonment and fire damage."
Repairs to prevent further subsidence which would have been expected were the installation of piling and ground beams to support the walls off the quarry base and the installation of steel straps to tie the walls to the cross walls and floors. The approximate costs of structural repairs was £40,000 for piling and ground beams and £500 for the stabilisation of walls.
COUNCIL'S CASE
DECISION
Rent | £ 3,000 | |
YP 5 years @ 20% | 2.99 | £ 8,970 |
Reversion to value of land & | ||
Uneconomic building | £15,000 | |
PV of £1 in 5 years @ 20% | 0.402 | £ 6,030 |
£15,000 |
By an arithmetical coincidence the present value of the land plus an uneconomic building (before deferment) is the same as the settlement figure of £15,000.
DATED: 15 August 2001
(Signed) P H Clarke
ADDENDUM
"Where … -
(a) …
(b) the Lands Tribunal is satisfied that a claimant has failed to deliver to the acquiring authority, in time to enable them to make a proper offer, a notice in writing of the amount claimed by him, containing the particulars mentioned in subsection (2) of this section;
the Lands Tribunal shall, unless for special reasons it thinks proper not to do so, order the claimant to bear his own costs and to pay the costs of the acquiring authority so far as they were incurred …., after the time when in the opinion of the Lands Tribunal the notice should have been delivered."
DATED: 13 September 2001
(Signed) P H Clarke