KING'S BENCH DIVISION
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT
Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
(sitting as a Deputy High Court Judge)
____________________
BELL BUILDING LIMITED |
Claimant |
|
- and - |
||
TCLARKE CONTRACTING LIMITED |
Defendant |
____________________
Mr Andrew Singer KC (instructed by Howard Kennedy LLP) for the Defendant
Hearing date: 12th July 2024
____________________
Crown Copyright ©
The Deputy Judge:
(i) The sum of £2,129,672.69 plus VAT as a debt due under Payment Application No. 18 in the absence of a valid Pay Less Notice;
(ii) Contractual interest on that sum to the date of the Decision of £37,487.84 plus £437.60 per day thereafter which at the date of the Hearing was £170,080.64 in total;
(iii) The Adjudicator's costs in the sum of £21, 000.00 plus VAT.
(i) Bell issued the instant enforcement proceedings on 24th May 2024;
(ii) TCL acknowledged service indicating that it intended to defend these proceedings on 5th June 2024;
(iii) TCL served a statement from John Lewis (TCL's Divisional Commercial Manager) in response to Bell's application for summary judgment on 19th June 2024;
(iv) In the parallel Part 7 proceedings:-
(a) TCL filed and served its Particulars of Claim on 7th June 2024; and
(b) Bell filed and served its Defence and Counterclaim in the Part 7 proceedings on 5th July 2024. The final timetable to a trial of the issues in the Part 7 proceedings is yet to be determined.
Background Facts
"It is common ground that [TCL] has paid Bell the sum of £710,120.62 received on 21st June 2023 and £685,591.18 received on 17th July 2023. It is also common ground that amounts totalling £18,084,322.36 (excluding VAT and inclusive of the two amounts separately described) have been received as at the date of this Notice."
Paragraph 5.2 states:
"For the avoidance of doubt, Bell does not give the Adjudicator jurisdiction to decide the "true value" of the Payment Claim and reserves the right to bring such a claim in any subsequent adjudication."
Paragraph 6.1 under the heading "Remedy and Redress sought by Bell" provided at sub-paragraph 6.14:
"[TCL] should pay Bell the Payment Claim in the outstanding sum of £1,443,981.51 plus applicable VAT as a debt"
"5.49 Bell is therefore entitled to be paid the outstanding sum of £1,443,981.51 (excluding VAT) as a result of (TCL's) breach of the sub-contract payment provisions.
5.50 For the avoidance of doubt, Bell does not give the Adjudicator jurisdiction to decide the "true value" of the Payment Claim and reserves the right to bring such a claim in any subsequent adjudication.
5.51 For the avoidance of doubt, Bell does not give the Adjudicator jurisdiction to decide the value, true or otherwise in respect of any other Payment Claim and reserves the right to bring such a claim in any subsequent adjudication."
Paragraph 7.14 under the heading "Remedy and Redress Sought by Bell" provides "(TCL) should pay Bell the Payment Claim in the sum of £1,443,981.51 plus applicable VAT as a debt."
"This is a technical adjudication concerning an Application for a Payment and the associated service of any Pay Less Notice leading to the payment of any Notified Sum colloquially known as a "smash and grab" adjudication and does not concern the true value of the works at the relevant time."
He decided at paragraph 189 that "the document issued by email by the Respondent on 6th June 2023 is not considered a valid Pay Less Notice and has no standing".
He decided "the Respondent should pay the Payment Claim in the sum of £1443,981.51 plus applicable VAT as a debt". He said at paragraphs 228 and 229:
"228. The Respondent has challenged the Claimant's calculation of the amount to be paid on the basis that it includes the Respondent's payment regarding Application No. 19. I understand this challenge to mean that I am only dealing with the Claimant's Application No. 18 in this adjudication. It is the Respondent 's position that I cannot take into account a payment made under Application No. 19 as that will be outside my jurisdiction.
229. Following this logic taking into account the payment made by the Respondent to the Claimant in relation to Application No. 18 the outstanding amount remaining to be paid is in the sum of £2,839,793.31 less £710,120.62 being the amount of £2,129,672.69."
The decision at paragraph 262 is that:
"The Respondent shall pay the Claimant the Payment Claim in the sum of £2,129,672.69 plus applicable VAT as a debt"
(i) The Adjudicator noted that Application No. 18 was for a payment of £1,058, 248.92 and not £1,443,981.51 as claimed. He asked for an explanation of the difference;
(ii) Bell explained that it was because the sum applied for under Application No. 18 reflected the increase in value of the completed work since the last application. It did not take into account the sums previously due as interim payments and/or sums paid by TCL to date;
(iii) In contrast, Bell's claim in the adjudication was based on its contractual entitlement to the value of the completed work less sums previously due as interim payments, sums paid to date and retention;
(iv) Bell's figure of £1,443,981.51 plus VAT claimed in the adjudication was therefore the result of deducting the sums paid by TCL at the date of the Referral from Bells's gross valuation under Application No. 18, less 3% retention;
(v) However, as recorded in the Decision at paragraphs 211 - 216, TCL challenged Bell's calculation on the basis that it included payments made by TCL under Application No. 18 and Application No. 19. At paragraph 228 of the Decision, the Adjudicator accepted TCL's submissions and concluded that he had no jurisdiction to consider payments made under Application No. 19;
(vi) He therefore concluded that his assessment of the sum due under Application No. 18 in the absence of a valid Pay Less Notice should exclude the sum of £679.592.78 that Bell claimed it had received under Application No. 19. This increased the sum due under Application No.18 from the sum claimed of £1,443,981.51 to £2,129,672.69 plus VAT. That is the sum he ordered was due as a debt (paragraphs 229 - 230 of the Decision).
"There has been substantial authority based in arbitration and in adjudication about what the meaning of the expression "dispute is" and what disputes or differences may arise on the facts of any given case… I draw from such cases as those the following proposition:
(a) Courts (and indeed Adjudicators and Arbitrators) should not adopt an over legalistic analysis of what the dispute between the parties is;
(b) One does need to determine in broad terms what the disputed claim or assertion (being referred to adjudication or arbitration as the case may be) is;
(c) One cannot say that the disputed claim or assertion is necessarily defined or limited by the evidence or arguments submitted by either party to each other before the referral to adjudication or arbitration;
(d) The ambit of the reference to arbitration or adjudication may unavoidably be widened by the nature of the defence or defences put forward by the defending party in adjudication or arbitration."
(a) "It must first be established that the Adjudicator failed to apply the rules of natural justice;
(b) Any breach of the rules must be more than peripheral; there must be material breaches;
(c) Breaches of the rules will be material in cases where the Adjudicator has failed to bring to the attention of the Parties a point or issue which they ought to be given the opportunity to comment upon if it is one which is either decisive or of considerable potential importance to the outcome of the resolution of the dispute and is not peripheral or irrelevant;
(d) Whether the issue is decisive or of considerable potential importance or is peripheral or irrelevant obviously involves a question of degree which must be assessed by any Judge in a case such as this;
(e) It is only if the Adjudicator goes off on a frolic of his own, that is wishing to decide a case upon a factual or legal basis which has not been argued or put forward by either side without giving the parties an opportunity to comment or, where relevant put in further evidence, that the type of breach of the rules of natural justice with which the case of Balfour Beatty Construction Company Limited v. The Camden Borough of Lambeth was concerned comes into play. It follows that, if either party has argued a particular point and the other party does not come back on the point there is no breach of the rules of natural justice in relation thereto".
"23. If an Adjudicator has it in mind to determine a point wholly or partly on the basis of material that has not been put before him by the parties, he must give them an opportunity to make submissions on it. For example, he should not arrive at a rate for particular work using a pricing guide to which no reference has been made during the course of the referral without giving the parties an opportunity to comment on it.
Natural Justice
Jurisdiction