BUSINESS AND PROPERTY COURTS IN BIRMINGHAM
TECHNOLOGY AND CONSTRUCTION COURT (KBD)
Priory Courts 33 Bull Street Birmingham B4 6DS |
||
B e f o r e :
____________________
Ubhi Construction Limited |
Claimant |
|
- and - |
||
Aspire Enterprises (UK) Limited |
Defendant |
____________________
Simon Clegg (instructed by Rutherfords LLP) for the Defendant
Hearing dates: 24, 25, 29 and 30 January
____________________
Crown Copyright ©
HER HONOUR JUDGE SARAH WATSON:
BACKGROUND
THE ISSUES
i) Did Mr Dhanda sign the JCT contract?
ii) If so, was the contract conditional on funding so that it did not bind the Defendant until it had obtained funding?
iii) If the contract was not conditional, is the Claimant entitled to payment of the invoices that it raised for the costs of the hire of plant and equipment and for standstill charges?
iv) If the was Contract was not conditional, what is the Claimant's recoverable loss? There is no issue between the parties that, if the Contract was not conditional, the Claimant is entitled to damages for the Defendant's beach of it by refusing to allow the Claimant carry it out.
THE EVIDENCE
DID MR DHANDA SIGN THE JCT CONTRACT?
"Bob
We have the whole site fenced off and all facilities are now on site.
We really need funds sending through now. I know you're on holiday, but you should be able to sort something out from there."
"Hi Bob
I appreciate your help and signing up the contract before I went away protects both parties.
The revised information was only sent to the finance company a few days before I left.
The finance still needs to be fully approved and then signed off at solicitor. This will hopefully be ready by the time I get back. Be assured I am on top of things even though I am away.
Regards
Bob"
"Hi Bob
Bob Dhanda has emailed the Google link for the JCT contract to me, however I am unable to open as I need permission on the Google account. I have sent a request via Google. Just in case you were unsure who the request was from, we are the bank's Monitoring Surveyors and will be required to make comment on the Contract within our initial development appraisal for the Bank."
"Contract- the executed contract we received did not incorporate the elements we would normally expect to see. We have advised that the contract is terminated and a new one drafted for our review."
"I have also spoken to the contractor UBHI Construction regarding the JCT contract. Bob will be emailing you with a few questions and I would appreciate if you could reply so we can have the JCT contractor signed in the format that would be appropriate to the Bank"
"I have seen a copy of the witness statement of my current co-director Bob Dhanda and I confirm that the contents of Bob's statement are true. To avoid repetition I do not repeat whet he has says (sic) but agrees(sic) with what he says.
There is a JCT contract dated 19 September (sic) which appears to have the signature of Mr Bob Dhanda, my current co-director. I was very surprised to see this document. Bob was not at that time a director of Aspire and Bob would not sign a document on behalf of Aspire as he was not a director and did not have authority to sign documents. Documents such as JCT contracts are always signed by the directors of Aspire which were myself and my co-director Kulwinder Bajwa (Karl). Bob has only become a director of Aspire in recent years."
i) Mr Dhanda was a 50% shareholder in the Defendant shortly after it was formed in 2014. At that time, he was company secretary.
ii) He resigned as company secretary on 1 July 2015. At that time Mrs Gill was appointed as a director. The directors were Mrs Gill and her brother, Mr Singh. The shareholders were Mr Dhanda, Mr Bajwa and Mrs Gill, who owned 34 shares each
iii) On 12 August 2016, Mr Dhanda transferred his shares to Mr Bajwa. Mr Bajwa then held 68 shares and Mrs Gill 34 shares.
iv) On 5 February 2019, a confirmation statement with updates was filed. It showed that Mr Dhanda, Mr Bajwa and Mrs Gill each owned 34 shares. It did not state when any shares had been transferred since the last statement with updates.
v) On 16 January 2024 (which I shall treat as 29 January 2024) Mr Bajwa and Mr Dhanda each transferred their 34 shares to Mrs Gill and Mr Bajwa resigned as a director. The sole director and shareholder is now Mrs Gill.
WAS THE CONTRACT CONDITIONAL ON FUNDING?
i) In an email from Mr Dhanda to Mrs Cooper copied to Mr Matharu and Mr Ubhi on 22 December 2016, Mr Dandha said " I have spoken to the contractor UBHI construction regarding the JCT contract. Bob will be emailing you with a few questions and I would appreciate if you could reply so we can have the JCT contractor signed in the format that would be appropriate to the Bank."
ii) In an email dated 17 January 2017 from Mr Dhanda to Mrs Cooper and copied to Mr Matharu and Mr Ubhi, he said "we have nearly completed all the outstanding work necessary and will be looking to have the JCT contract signed soon."
iii) In an e-mail dated 20 January 2017 from Mr Dhanda to Mr Sedgemore, Mr Matharu and Mr Ubhi, he said "just a quick e-mail to say we will have all the contract completed by this week and to you early next week."
IS THE CLAIMANT ENTITLED TO PAYMENT OF ITS INVOICES?
WHAT IS THE CLAIMANT'S RECOVERABLE LOSS?
CONCLUSION