BUSINESS AND PROPERTY COURTS
OF ENGLAND AND WALES
TECHNOLOGY & CONSTRUCTION COURT (KBD)
London EC4A 1NL |
||
B e f o r e :
(Sitting as a Deputy High Court Judge)
____________________
PROVIDENCE BUILDING SERVICES LIMITED |
Claimant |
|
- and - |
||
HEXAGON HOUSING ASSOCIATION LIMITED |
Defendant |
____________________
MR J LEWIS KC and MR N KAPLAN (instructed by Devonshires Solicitors) appeared on behalf of the Defendant.
____________________
Crown Copyright ©
Mr Adrian Williamson KC:
".3 If a specified default or a specified suspension event continues for 28 days from the receipt of notice under clause 8.9.1 or 8.9.2, the Contractor may on, or within 21 days from, the expiry of that 28-day period by a further notice to the Employer terminate the Contractor's employment under this Contract.
".4 If the Contractor for any reason does not give the further notice referred to in clause 8.9.3 but (whether previously repeated or not):
".1 the Employer repeats a specified default; . . . ".2 . . .
then, upon or within 28 days after such repetition, the Contractor may by notice to the Employer terminate the Contractor's employment under this Contract.'
"If the employer does not give the further notice referred to in clause 8. 4.2 (whether as a result of the ending of any specified default or otherwise) but the Contractor repeats a specified default, whether previously repeated or not then upon or within a reasonable time after such repetition the Employer may, by notice to the Contractor, terminate that employment."