BUSINESS AND PROPERTY COURTS IN LEEDS
TECHNOLOGY AND CONSTRUCTION COURT (KBD)
Oxford Row Leeds LS1 3BG |
||
B e f o r e :
sitting as a Judge of the High Court
____________________
BEXHILL CONSTRUCTION LTD |
Claimant |
|
- and |
||
KINGSMEAD HOMES LTD |
Defendants |
____________________
Mr Harry East (instructed by Hill Dickinson LLP) for the Defendant
Hearing date: 17 May 2023
Date draft circulated to the Parties: 22 September 2023
Date handed down: 3 October 2023
____________________
Crown Copyright ©
Her Honour Judge Kelly
Background
17.09.21 |
The Claimant entered into a subcontract with the Defendant to undertake labour only brickwork at the site for the sum of £174,128.50. |
|
The subcontract contained the following relevant provisions: Clause 6.2: "Form of Subcontract Conditions JCT" Clause 6.9.1: "Daywork shall only be carried out on the written instruction of the Contractor and Daywork sheets shall be submitted at the end of the day following the day the work was executed for signing by the Site Manager. Any sheets submitted after this dated will be rejected. Such signature shall not imply that the charge in reasonable or that the work is to be valued and paid for on a Daywork basis."
Clause 6.9.2: Variations: Any works that are considered to be a variation by the Subcontractor shall be notified to the Contractor at least 7 working days prior to the date that the works are due to be carried out. The notification shall include full details of the works involved and include the Subcontractor's fully detailed quotation for carrying out the works. The Contractor will issue a notice stating whether the notified works constitute a variation. If the works are deemed to be a variation the Contractor will issue an instruction which will include details of the agreed cost for the works. Any notifications that are not issued in accordance with the above procedure will be rejected. Any variation works notified after the works have been carried out will also be rejected"
Clause 6.10: "Valuation Periods: Applications for interim payments is one month. Valuations are to be submitted on the 1st of each month. Sub contact valuations are to be submitted in writing.
Sub contract valuations are to be submitted in accordance with the following:
Interim Valuation claims, for works executed to Valuation Date, to be submitted to head office by the 17th of the month
1. Interim Applications received after the Interim Application Date will be put forward to the following Valuation period 2. Claims for additional works must be accompanied with written approval from Kingsmead Homes Limited. Lack of approval will mean that such claims will be disallowed until approval in writing by Kingsmead Homes limited. 3. Additional works will be included in the Valuation period following issue of written approval by Kingsmead Homes Limited."
|
|
After work began, the Claimant issued a number of interim applications for payment pursuant to the subcontract.
|
16.05.22 |
The Claimant issued its interim application for payment number 8 in the sum of £49,664.80. |
23.05.22 |
The Defendant sent an email to the Claimant which it asserted was a pay less notice for application 8. The email asserted that the application was not in line with the subcontract. The reason for refusal was either because the day works had not been accepted in accordance with paragraph 6.9.1 of the subcontract or alternatively the works were included within the scope of work included within the subcontract. In respect of the balance of work, the email asserted that a previous pay less notice had been issued and so nothing was due.
The email also asserted that the subcontract was terminated as of 16 May 2022. |
18.01.23 |
The Claimant instructed consultants to refer the dispute between the parties concerning application number 8 to adjudication. The Claimant asserted amongst other things that the JCT Short Form of Subcontract (ShortSub) 2016 Conditions ("the JCT terms") were incorporated into the subcontract, that the Defendant had not served a valid interim certificate nor a pay less notice and that the consultants were going to apply to the RICS to nominate an adjudicator.
The Referral accompanied that letter and set out the nature of the dispute including: (1) The Dispute was "the Respondent's failure to pay the sum due of £49,664.80" and sought a decision that the Claimant was to be paid that sum or such other sum as the adjudicator deemed proper; (2) the subcontract agreement was subject to the JCT terms; (3) the Defendants did not serve an effective pay less notice because it was served to early and in any event did not state the sum considered to be due by the Defendant, nor the basis upon which that sum had been calculated.
|
19.01.23 |
The adjudicator was appointed by the RICS.
|
26.01.23 |
The Defendant provided a Response to the adjudicator including assertions that: (1) The Claimant had not established any contractual basis for its claim and was thus "restricted by Bexhill to only concern enforcing payment purely on the terms/rules of the contract rather than the valuation of the underlying works. Consequently, Kingsmead will not address the value of the underlying works within its Response". (2) The JCT terms did not apply because the parties had not agreed which form of JCT terms should apply. The agreement was therefore only the terms are set out in the subcontract agreement. (3) "To the extent that these terms do not fully comply with the Housing Grants Construction and Regeneration Act 1996 as amended ("the Act") then the Scheme applies". (4) There was no contractual basis for making a claim for payment under the subcontract agreement or under the JCT terms.
|
30.01.23 |
The Claimant provided a Reply to the Response (the Reply"). The Reply argued that: (1) Either the JCT terms applied or in the alternative the Act and the Scheme applied. (2) If the Act and the Scheme applied, the Defendant had not served an effective payment notice or pay less notice.
|
01.02.23 |
The Defendant provided its Rejoinder. The Defendant asserted: (1) The use of the letters "JCT" was insufficient to demonstrate the parties agreed the incorporation of particular JCT terms. (2) The application for payment was not issued in accordance with section 110B(4)(b) of the Act; (3) The application for payment was not valid as it did not conform with clause 6.10 of the subcontract agreement because the sums claimed were for additional work which had not been approved by the Defendant.
|
02.02.23 |
The Claimant sought permission by email from the adjudicator to respond to paragraphs 22 to 25 of the Defendant's Rejoinder, namely the Defendant relying on an "agreement to agree" in respect of additional works.
The adjudicator gave permission for either or both parties to briefly address that issue further.
The Claimant made brief further submissions on the point. The Defendant did not provide any further submissions. |
15.02.23 |
The adjudicator provided his decision. Although neither party asked the adjudicator to provide reasons for his decision, he did so.
The decision set out the following: (1) The broad nature of the dispute referred to adjudication, is the claimed Responding Party's failure to pay the sum due of £49,664.80, including later a more detailed summary of the dispute referred; (2) The "principal submissions" received from the parties including the Referral, Response, Reply and Rejoinder. He did not set out the further brief email exchanges after the Rejoinder. (3) It was agreed between the parties that the subcontract agreement dated 17 September 2021 was agreed. It was also agreed that to the extent that the subcontract did not fully comply with the Act, the Scheme applied. (4) This adjudication was only concerned with enforcing payment purely on the terms and rules of the contract rather than the valuation of any underlying works. (5) What the parties disagreed about was the applicable terms and conditions of the subcontract between the parties and the entitlement of the Claimant to payments in respect of its application number 8. (6) The adjudicator had read and considered both parties submissions but not all of those submissions were relevant to the matters he had to decide. (7) The JCT short form terms did not apply to the subcontract. (8) The Claimant succeeded on its alternative argument that the Scheme applied. The adjudicator noted that the Defendant had agreed that was the position in its Response. The adjudicator then went on to consider whether the Claimant was entitled to payment on the basis of the Scheme applying. (9) The Defendant's pay less notice email of 23 May 2022 was not compliant as a payment notice under the Scheme because the Defendant did not state the amounts due at the payment due date and the basis on which that sum was calculated. (10) The Defendant's pay less notice email of 23 May 2022 was also not compliant as a pay less notice under the Act because it did not state the amounts due at the payment due date on the basis on which that sum was calculated. (11) The adjudicator noted the Defendant's assertions that the Claimant had not provided any contractual basis for the claim. However, he stated that although the Claimant's arguments had evolved, in his view "it was essentially still the same dispute". (12) For technical reasons only therefore the adjudicator found that the Claimant was entitled to payment of the sum claimed of £49,664.80.
|
|
After receipt of the decision, the Defendant's consultants emailed the adjudicator asserting that the decision "does not address the content of Kingsmead's Rejoinder" where a defence was raised that the interim application had not been issued in accordance with the subcontract agreement and as a result, interim application number 8 could not be the notification under section 110B(4)(b) of the Act and so was not a notified sum required to be paid by the Defendant under section 111. The email asked how this defence had been addressed in the decision.
|
16.02.23 |
The adjudicator replied the next day by email stating "I confirm that all submissions were reviewed during the adjudication. Those that have not been expressly referred to in my Decision, did not impact my Decision".
|
15.03.23 |
The Claimant issued the claim to enforce the adjudicator's decision.
|
21.04.23 |
The Defendant filed a defence to the claim. In it, the Defendant denied that the Claimant had issued a valid payment application because all of the claim was in respect of additional work which had not been approved by the Defendant.
The Defendant asserted that the validity of the payment notice had been raised by the Defendant to the adjudicator and the adjudicator had not considered that argument in his decision.
The Defendant therefore denied that the decision of the adjudicator was enforceable because it was made in breach of natural justice.
|
The Law
(1) An adjudicator's decision will normally be enforced by the court by way of summary judgment. The court is not concerned with the merits of the decision. There are limited bases on which a Defendant may resist enforcement which include a material breach of natural justice.
(2) The court must decide if the breach is material and is more than peripheral. The issue of whether an issue is material or peripheral involves a question of degree which must be assessed by the judge. Once a defence has been raised, it is the adjudicator's job to consider any defence properly put forward by the defending party (see Cantillon Limited v Urvasco Limited [2008] EWHC 282 (TCC), Quarterzelec Ltd v Honeywell Control Systems Limited [2008] EWHC 3315 (TCC) and C & E Jacques Partnership v Ensign Contractors Limited [2009] EWHC 3383 (TCC)).
(3) A breach can be material if there is a failure to consider and address a substantive defence put forward by the responding party. It will not be a material breach if the adjudicator simply fails to address some particular aspect of the evidence or elements of one party's submissions (see NAP Anglia Ltd v Sun-Land Development Co Ltd [2011] EWHC 2846 (TCC)).
(4) The objective of adjudication and of the Act is to respect and enforce an adjudicator's decision unless it is plain that the question which he has decided was not the question referred or the manner in which he has gone about his task is obviously unfair. There will only be rare circumstances where the court will interfere with the decision of an adjudicator (see Carillion Construction Ltd v Devonport Royal Dockyard [2005] EWCA Civ 1358 at paragraphs 85 and 86).
(5) The starting point for any application to enforce the decision of an adjudicator is that the court will always endeavour to enforce such decisions. The adjudicator is not obliged to set out the matters raised by each party nor give detailed reasons for every part of his conclusion, unless commentary and findings are necessary to provide reasons and explanations for the decision (see Balfour Beatty Construction v Modus Corovest (Blackpool) Ltd [2008] EWHC 3029 (TCC) and HS Works Limited v Enterprise Managed Services Limited [2009] EWHC 729 (TCC))).
(6) There is a distinction between a case where an adjudicator deliberately decides not to consider a defence or a legitimate counterclaim and a case where there is an inadvertent failure to consider one of a number of issues embraced by the single dispute that the adjudicator has to decide. The former may make the decision unenforceable whereas an inadvertent failure ordinarily will not (see Pilon Limited v Breyer Group PLC [2010] EWHC 837 (TCC)).
(7) In considering whether there has been a material breach, if an adjudicator disregards all of one party's Response both as to argument and evidence, that will be material. It is not necessary for the court to investigate the facts to decide if the adjudicator would have reached a different decision if he had considered that argument and evidence. All that is necessary is that there would be a real (as opposed to fanciful) possibility that the adjudicator could have reached a different decision (see CJP Builders Limited v William Verry Limited [2008] BLR 545).
(8) An adjudicator can act wholly honestly and transparently and still be in breach of natural justice if they fail to deal with matters which are properly before them or if they deal with a matter without giving the parties the opportunity to be heard on that point. There is no need for the court to consider whether the decision would have been different had the issue been properly considered (see PC Harrington Contractors v Tyroddy Construction [2011] EWHC 813 (TCC)).
(1) if a Claimant will probably be unable to repay a judgment sum awarded by an adjudicator and enforced by summary judgment at the end of the substantive trial or arbitration, that may constitute special circumstances such that it would be appropriate to grant a stay (see Wimbledon Construction Company 200 Limited v Derek Vago [2005] EWHC 1086 (TCC)).
(2) However, even if the receiving party's financial position suggested that it was probable it would be unable to repay the judgment sum, that would not justify the grant of a stay if either the receiving party's financial position was similar to its financial position at the time the contract was made, or the Claimant's financial position was due, in part, to the Defendants failure to pay those sums due (see Bexheat Limited v Essex Services Group Limited [2022] EWHC 936 (TCC)).
The Issues
(1) What was the dispute referred to the adjudicator?
(2) What was the defence, or defences, raised by the Defendant in Response to the dispute?
(3) In deciding the dispute, did the adjudicator consider the defence, or defences, raised by the Defendant?
(4) If not, was there a material breach of natural justice?
(5) If so, does the Defendant have a real prospect of successfully defending the claim?
(6) In the alternative to the above, has the Defendant sufficiently pleaded that enforcement should be stayed?
(7) If not, can the court consider the matter of stay of enforcement?
(8) Would any subsequent judgment requiring the Claimant to repay monies to the Defendant go unsatisfied?
(9) Is any such evidence sufficient to provide special circumstances which render it inexpedient to enforce the adjudicator's decision?
Submissions and Findings
(1) What was the dispute referred to the adjudicator?
(2) What was the defence, or defences, raised by the Defendant in Response to the dispute?
(3) In deciding the dispute, did the adjudicator consider the defence, or defences, raised by the Defendant?
28. I do not accept the assertion made by Mr Beer in his witness statement that the adjudicator made "erroneous findings of fact/agreements" when the adjudicator stated that the parties agreed that the Claimant's application for payment was made on 16 May 2022. It is correct that the adjudicator did not specifically set out the contents of paragraphs 22 to 25 of the Rejoinder and the emails of 2 February 2023 where the Defendant argues further why that notice was not a valid notice. However, in its Response at paragraph 20, the Defendant said "it accepts Bexhill served an interim application for payment on 16 May 2022" and later at paragraph 31 stated "However, as has already been agreed, Bexhill issued its interim application on 16 May 2022 ". Having made those submissions, I do not accept that there is a real prospect of successfully arguing that the finding of such an agreement was erroneous.
(4) If not, was there a material breach of natural justice?
(5) If so, does the Defendant have a real prospect of successfully defending the claim?
(6) In the alternative to the above, has the Defendant sufficiently pleaded that enforcement should be stayed?
(7) If not, can the court consider the matter of stay of enforcement?
(8) Would any subsequent judgment requiring the Claimant to repay monies to the Defendant go unsatisfied? and
(9) Is any such evidence sufficient to provide special circumstances which render it inexpedient to enforce the adjudicator's decision?
"Companies are in the weakest 20% in their size category and display risk factors that might include a deteriorating financial position, sub-optimal gearing or liquidity, and the possible presence of recent or significant legal notices. The risk is elevated, and suppliers should seek suitable assurances or guarantees."