BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (KBD)
Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
____________________
Município de Mariana & Others |
Claimants |
|
- and - |
||
BHP Group (UK) Ltd and BHP Group Limited |
Defendants |
____________________
Victoria Windle KC, Nicholas Sloboda and Oliver Butler (instructed by Slaughter and May) for the Defendants
Hearing dates: 28th July 2023
____________________
Crown Copyright ©
(1) service of the additional particulars of claim (the 'APOCs') to be extended until 8 September 2023;
(2) service of a revised new claim form by 8 September 2023 which includes the addresses of those new claimants for whom there is either no address or an incomplete address; and
(3) service of the updated version of the master schedule until 6 October 2023.
a. the outstanding APOCs in respect of any new claimants to be served by 16 June 2023;
b. the new claim form to be filed by 17 February 2023; and
c. the master schedule to be filed by 17 February 2023.
Claimants' submissions
Defendants' submissions
Applicable principles
a. ensuring that the parties are on an equal footing and can participate fully in proceedings and that parties and witnesses can give their best evidence;
b. saving expense;
c. dealing with the case in ways which are proportionate to the amount of money involved, the importance of case, the complexity of the issues and the financial position of each party;
d. ensuring it is dealt with expeditiously and fairly;
e. allotting it an appropriate share of the court's resources, while taking into account the need to allot resources to other cases; and
f. enforcing compliance with rules, practice directions and orders.
a. The court will grant a reasonable extension if it does not impact on hearing dates or other disrupt proceedings.
b. The fact that a refusal to extend time would in practice mean the end of a claim is a factor to be weighed in the balance but it cannot of itself warrant the grant of relief.
c. The need to comply with court orders is of paramount importance. A claimant's entitlement to sue a defendant is not an absolute right and does not permit that claimant to fail to comply with court orders or delay or disrupt the administration of justice.
"In general, the court should not refuse to grant a prospective application for a reasonable extension of time where the extension sought does not imperil any future hearing dates or otherwise disrupt the proceedings".
Extension of time for APOCs
Missing addresses from new claim form
"The claim form must include an address (including the postcode) at which the claimant lives or carries on business, even if the claimant's address for service is the business address of their solicitor."
"The claimants may, if so advised, and by 4 pm on 16 June 2023, serve an amended new claim form which gives an address for all claimants named on the new claim form. Thereafter, any claimant named on the new claim form for whom no address has been provided shall be removed from the master schedule pending any successful application for permission to include them."
a. Identify and assess the seriousness and significance of the failure to comply with any rule, practice direction or court order which engages CPR 3.9(1).
b. Consider any explanation for the default.
c. Evaluate all the circumstances of the case, so as to enable the court to deal justly with the application, including CPR 3.9(1)(a): the need for litigation to be conducted efficiently and at proportionate cost; and CPR 3.9(b): to enforce compliance with rules, practice directions and orders.
"Unless the claimants by 4 pm on 8 September 2023 serve an amended new claim which gives an address for all claimants named on the new claim form, any such claimant named on the new claim form for whom no address has been provided shall be removed from the master schedule and their names shall be struck through on the new claim form".
Master Schedule