BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (KBD)
Rolls Building London EC4A 1NL |
||
B e f o r e :
____________________
NORFOLK COUNTY COUNCIL |
Claimant |
|
- and – |
||
BLANMAR 2 LLP |
Defendant |
____________________
(instructed by nplaw) Solicitor for the Claimant
Mr Edward Peters KC (instructed by Hatton Solicitors Ltd) Solicitor for the Defendant
Remote Hearing date: 8 June 2023
Date draft circulated to the Parties: 26 July 2023
Date handed down: 17 August 2023
____________________
Crown Copyright ©
This judgment was handed down by the Judge remotely by circulation to the parties' representatives by email. The date and time for hand-down is deemed to be 10.30am on Thursday 17th August 2023.
Her Honour Judge Kelly
(1) the dispute was a "difference under any provision of the DCO"; and
(2) the dispute was not "otherwise provided for", so as to fall within Article 46.
(1) Ground 1: The court erred failing to take into account relevant considerations in the interpretative exercise.
(2) Ground 2: The court erred by taking into account irrelevant considerations in the interpretative exercise.
(3) Ground 3: The court erred in determining that a dispute as to "what the Claimant was permitted to do by the DCO" was "a difference under any provision" of the DCO.
(4) Ground 4: The court erred in determining that the difference it had identified was not "otherwise provided for" so as to come within Article 46.
The Test for Permission to Appeal.
"The threshold test for determining whether permission for an appeal should be given by the judge is the usual civil standard for an appeal, namely whether there was a reasonably arguable case. It was suggested by Jacob J in Macepark (Whittlebury) Limited v Sargeant that the test should be the same as for an appeal on an error of law under s 69, that the decision was at the very least open to serious doubt. Jacob J held that there was no basis for imposing a common standard, because s 67 was for the most part concerned with the proper construction of an agreement between the parties and was not subject to the same considerations applicable to error of law by the arbitrators".
"The public interest that arbitration should produce a high degree of finality compared with ordinary litigation led to Parliament proscribing strictly limited avenues of challenge and appeal. Though not identically worded, each provides that an appeal to this Court may only be made if the court appealed from gives permission".
The Grounds of Appeal
Ground 1
(1) the practical implications of the competing contentions;
(2) the context of the legislative scheme for compulsory purchase; and
(3) the law relating to the implication of terms or words into a statute.
"When considering, in relation to the facts of the instant case, which of the opposing constructions of the enactment corresponds to its legal meaning, the Court should assess the likely consequences of adopting each construction, both to the parties in the case (and where similar facts arise in future cases) for the law generally. If on balance the consequences of a particular construction are more likely to be adverse than beneficent this is a factor telling against that construction. "
"What is in issue is whether the arbitrator had jurisdiction in this particular case. It is not necessary or desirable to look at interpretation of Article 46 more generally. There may be a myriad of situations which may constitute "any difference under any provision of this Order"".
Ground 2
"The tendency now is very much to treat claims based on other causes of action as within the tribunal's jurisdiction, particularly if they relate to the same facts as other contractual claims falling within the arbitration agreement".
Ground 3
"the Arbitrator who the President of ICE appointed in this case had qualified as a barrister (unregistered) as well as a civil engineer, and is an adjudicator on the Royal Institution of Chartered Surveyor's panel; whilst the ICE dispute resolution service advertises itself as "a multidisciplinary service that includes lawyers, surveyors, architects, structural, mechanical and civil engineers.""
Ground 4
".. may not include provision the effect of which is to modify the application of a compensation provision, except to the extent necessary to the compulsory acquisition of land authorised by the order".