BUSINESS AND PROPERTY COURTS
OF ENGLAND AND WALES
TECHNOLOGY & CONSTRUCTION COURT (KB)
Fetter Lane London, EC4A 1NL |
||
B e f o r e :
(Sitting as a Deputy Judge of the High Court)
____________________
ISG RETAIL LIMITED |
Claimant |
|
- and - |
||
FK CONSTRUCTION LIMITED |
Defendant |
Official Court Reporters and Audio Transcribers
5 New Street Square, London, EC4A 3BF
Tel: 020 7831 5627 Fax: 020 7831 7737
civil@opus2.digital
____________________
Crown Copyright ©
THE DEPUTY JUDGE:
"(4) Not later than 9 days before the dates for payment set out in the Schedule of Due Dates referred to in the Numbered Documents or in the Sub-Contract Particulars (as the case may be) (in each case the "Application Date"), the Sub-Contractor shall submit applications for payment to ISG's financial manager/surveyor…
(6) The due date for payment of any interim payment shall be the relevant date set out in the Schedule of Due Dates referred to in the Numbered Documents or in the Sub-Contract Particulars (as the case may be) or, if the relevant application for payment issued by the Sub-Contractor is submitted after the date required for its submission by clause 2(4), the relevant due date shall be postponed by the number of days by which the application is late. Provided always that the last due date for payment of any interim payment shall not fall after the expiry of a 3 month period following practical completion of the Works, and the Sub-Contractor shall not be entitled to submit any application for payment in respect of any interim payment after expiry of that period…
(8) ISG shall notify the Sub-Contractor in writing within 5 days of the relevant due date for any interim or final payment of the amount ISG considers to be, or to have been, due at the due date and the basis on which such amount is calculated. The payee shall submit a tax invoice to the payer for payment of the notified amount. Subject to any Pay Less Notice issued in accordance with clause 2(10), the payer shall pay the payee the amount so notified on or before the final date for payment…
(10) The payer shall, if it intends to pay less than the sum stated as due from it in the relevant payment notice issued by it in accordance with clause 2(8), issue notice of that intention (a "Pay Less Notice") not later than 2 days before the final date for payment of the relevant notification of the amount specifying both the amount the payer considers to be due to the payee at the date the notice is given and the basis on which that amount has been calculated. Where a Pay Less Notice is given, the payment to be made on or before the relevant final date for payment shall be not less than the amount stated as due in that notice…
(17) The Sub-Contractor and where applicable ISG shall submit any application for payment or invoice in accordance with clause 31. In relation to the requirements for giving notices under clauses 2(4), 2(8) or 2(10) it is immaterial that the amount then considered to be due may be zero. Payments shall be made by ISG to the Sub-Contractor if the relevant notice states that the amount is due to the Sub-Contractor, and by the Sub-Contractor to ISG if the relevant notice states that the amount is due to ISG."
"(1) This section applies in a case where, in relation to any payment provided for by a construction contract—
(a) the contract requires the payer or a specified person to give the payee a notice complying with section 110A(2) not later than five days after the payment due date, but
(b) notice is not given as so required.
(2) Subject to subsection (4), the payee may give to the payer a notice complying with section 110A(3) at any time after the date on which the notice referred to in subsection (1)(a) was required by the contract to be given.
(3) Where pursuant to subsection (2) the payee gives a notice complying with section 110A (3), the final date for payment of the sum specified in the notice shall for all purposes be regarded as postponed by the same number of days as the number of days after the date referred to in subsection (2) that the notice was given.
(4) If—
(a) the contract permits or requires the payee, before the date on which the notice referred to in subsection (1)(a) is required by the contract to be given, to notify the payer or a specified person of—
(i) the sum that the payee considers will become due on the payment due date in respect of the payment, and
(ii) the basis on which that sum is calculated, and
(b) the payee gives such notification in accordance with the contract, that notification is to be regarded as a notice complying with section 110A (3) given pursuant to subsection (2) (and the payee may not give another such notice pursuant to that subsection),"
"(3) A notice complies with this subsection if it specifies—
(a) the sum that the payee considers to be or to have been due at the payment due date in respect of the payment, and
(b) the basis on which that sum is calculated."
"The due date for payment of any interim payment shall be the relevant date set out in the Schedule of Due Dates referred to in the Numbered Documents or in the Sub-Contract Particulars (as the case may be) or, if the relevant application for payment issued by the Sub-Contractor is submitted after the date required for its submission by clause 2(4), the relevant due date shall be postponed by the number of days by which the application is late…"
(1) the application is still late and therefore not in accordance with the contract. Indeed, cl.2(6) refers in terms to lateness;
(2) the application is by definition "submitted after the date required for its submission," i.e., it is not in accordance with the contract.
"ISG shall notify the Sub-Contractor in writing within 5 days of the relevant due date for any interim or final payment of the amount ISG considers to be, or to have been, due at the due date and the basis on which such amount is calculated. The payee shall submit a tax invoice to the payer of payment of the notified amount. Subject to any pay less notice issued in accordance with clause 2(10), the payer shall pay the payee the amount so notified on or before the final date for payment."
"In summary, the approach to be taken by the court as gleaned from these authorities is as follows:
i) In considering the true construction of a contractual notice (including notices under the payment regime in the Act – see Grove Developments per Coulson J at [21]-[22] and S&T in the Court of Appeal at [58] per Sir Rupert Jackson), the question is not how its recipient in fact understood it. Instead "the construction of the notices must be approached objectively. The issue is how a reasonable recipient would have understood the notices", i.e. a reasonable recipient "circumstanced as the actual parties were" (see Mannai at 767 G-H and 768B-C per Lord Steyn).
ii) The notice must be construed taking into account the "relevant objective contextual scene", i.e. the court must consider "what meanings the language read against the contextual scene will let in" (see Mannai at 767H and 768A-B). This means that, amongst other things, the reasonable recipient will be credited with knowledge of the relevant contract (see Mannai at 768B-C).
iii) The purpose of the notice will be relevant to its construction and validity (Mannai at 768E).
iv) The court will be "unimpressed by nice points of textual analysis or arguments which seek to condemn the notice on an artificial or contrived basis" (Thomas Vale per HHJ Kirkham at [43]; Grove at [26]). Instead, as Sir Peter Coulson says in paragraph 3.36 of his book on Construction Adjudication (4th ed. 2018), focusing specifically on Pay Less Notices:
"The courts will take a commonsense, practical view of the contents of a payless notice and will not adopt an unnecessarily restrictive interpretation of such a notice…It is thought that, provided that the notice makes tolerably clear what is being held and why, the court will not strive to intervene or endeavour to find reasons that would render such a notice invalid or ineffective".
v) There is no principled reason for adopting a different approach to construction in respect of different kinds of payment notices (for example because some may give rise to more draconian consequences than others) as that would be contrary to the guidance in Mannai (see Grove at [27]). However:
"the particularly adverse consequences for an employer that follow from, say, a contractor's unanswered application/payment notice are relevant to the test of the reasonable recipient".
vi) To qualify as a valid notice, any payment notice must comply with the statutory (and, if more restrictive, the contractual) requirements in substance and form (Henia per Akenhead J at [17]). Payment notices and Pay Less Notices must clearly set out the sum which is due and/or to be deducted and the basis on which the sum is calculated. Beyond that, the question of whether a notice is or is not a valid notice is "a question of fact and degree" (Grove at [29] and S&T at [53]).
vii) Over and above the question of whether a notice has achieved the required degree of specificity, will be the additional question of whether the document that is alleged to constitute a valid notice was in fact intended to be such and whether it is "free from ambiguity" (Henia at [17] and Grove at [42]). The sender's intention is a matter to be assessed objectively taking into account the context. (Jawaby at [43], [59] and [63]).
viii) Although in Grove, Coulson J observed that payment notices must make plain what they are, there is no requirement for a particular type of notice, such as a Pay Less Notice, to have that title or to make specific reference to the contractual clause in order to be valid: "[t]he question is whether, viewed objectively, it had the requisite intention to fulfil that function" (Surrey & Sussex at [65]).
ix) One way of testing the validity or otherwise of a Pay Less Notice will be to see whether it "provided an adequate agenda for an adjudication as to the true value of the Works…" (Henia at [32] and Grove at [26]).
(1) The document is headed "Sub-Contractor Payment Notice," which suggests that it is concerned with what the Sub-Contractor is to be paid;
(2) In the second paragraph, it is stated that "Actual payment will follow in due course," which is an odd phrase to use if the main contractor, ISG, was expecting payment to it;
(3) As already noted, the bottom line of the document was that there is an "amount due to Sub-Contractor," albeit in a negative amount. If ISG had wanted to make clear to FK that they were now the payer, one would expect to see the phrase "amount due to contractor";
(4) The breakdown at bundle B, p.255 states that the payment terms are "As Sub-Contract Conditions, Subject to receipt of invoice from Subcontractor in accordance with the subcontract terms and conditions." Why would the Sub-Contractor be raising an invoice if he was the payer and not the payee? Mr Brannigan submits that this was an inadvertent carry over from previous payment notices, but the wording scarcely made clear to FK that they were now expected to pay over £3 million to ISG.
"The payee shall submit a tax invoice to the payer for a payment of the notified amount."
Both parties, for their own forensic reasons, submitted that such an invoice was not a condition precedent to payment, and I did not, therefore, hear full argument on this issue. In any event, my above conclusions are sufficient to dispose of the Part 8 claim. Now, as a matter of the impression, it seems to me that cl.2(8) envisages three distinct steps: firstly, notification of the amount given; secondly, submission of a tax invoice; and, thirdly, payment of the sum of the invoice. If that is right, then, in the absence of a tax invoice from ISG to FK, FK could not have become liable to pay any amount in any event.