BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (QBD)
Rolls Building Fetter Lane, London, EC4Y 1NL |
||
B e f o r e :
____________________
STANDARD LIFE ASSURANCE LIMITED |
Claimant |
|
- and |
||
(1) GLEEDS (UK) (a firm) (2) BURO FOUR PROJECT SERVICES LIMITED (3) SHEARER PROPERTY ASSOCIATES LIMITED |
Defendants |
____________________
Claire Packman QC & Martyn Naylor (instructed by Clyde & Co LLP) for the First Defendant
Patrick Lawrence QC, Marion Smith QC and Nicholas Higgs (instructed by DAC Beachcroft LLP) for the Second Defendant
Graeme McPherson QC & Ian McDonald (instructed by Kennedys LLP) for the Third Defendant
Hearing dates: 25th and 26th May 2022
____________________
Crown Copyright ©
"This judgment was handed down by the judge remotely by circulation to the parties' representatives by email and release to The National Archives. The date and time for hand-down is deemed to be Friday 27th May 2022 at 10:30am"
Mrs Justice O'Farrell:
Background facts
Proceedings
The application
i) Paragraphs 86 and 87 and Annex 7 of the Particulars of Claim;
ii) Paragraph 2(9)(b) of the Reply to the First Defendant's Defence;
iii) Paragraph 2(11) of the Reply to the Second Defendant's Defence; and
iv) Paragraph 38(3) of the Reply to the Third Defendant's Defence
be struck out pursuant to CPR 3.4(2)(a) or (b) and/or summary judgment be given on those parts of the claim pursuant to CPR 24.2 on the grounds that (i) they disclose no reasonable grounds for bringing the claim; and/or (ii) the Claimant has no real prospect of succeeding on those parts of the claim.
The material pleadings
"8. Standard Life's Part A losses are particularised in Section G and Annex 7. Standard Life limits its Part A claim to £20,141,515 or such other sum the court shall determine. Namely: the difference between what ought to have been advised for outturn construction costs plus construction contingency (£105,872,515) less what was advised in fact (£85,731,000). This is an 'information case' for which the First to Third Defendants are jointly and severally liable for the consequences of their advice being wrong or their failure to advise as they ought.
86. Standard Life claims from the First to Third Defendants, jointly and severally, its losses on the Development from August 2008 to date. These losses are £128,417,518 or such other sum as the Court shall determine.
87. See Annex 7 for further particulars of the losses.
88. Standard Life limits its Part A claims to £20,141,515. Paragraph 8 is repeated."
"1. But for the breach of the Part A Defendants' obligations, Standard Life would not have proceeded with the Development. Standard Life would not have entered into the Building Contract on 26 August 2008. It would not have executed the Written Order to Commence Works on 16 September 2008.
2. Standard Life's losses are calculated by way of a basic comparison between:
(1) the position Standard Life would have been in had it not proceeded with the Development; and
(2) its actual position.
3. Standard Life's actual position is that it incurred £146,419,486 of construction costs.
4. The calculation of the position Standard Life would have been in had it decided not to proceed with the Development is set out below.
(1) Standard Life would not have incurred £146,419,486 in construction costs.
(2) Deducted from this figure are costs incurred by Standard Life for which the Part A Defendants were not responsible:
(a) the cost of Standard Life introducing John Lewis as an anchor tenant (£8,698,287);
(b) the cost of tenant variations (£2,423,681); and
(3) A further deduction is made to allow for certain irrecoverable sums incurred by Standard Life prior to August 2008. Prior to August 2008, Standard Life incurred total expenditure of approximately £15,000,000. Standard Life estimates that, of this sum, it would have been able to recover approximately £8,120,000 in proceeds from sale of land. The loss of the aborted Development would, therefore, have been approximately £6,880,000.
(4) Standard Life would not have incurred a loss elsewhere with the construction costs which would not in fact have been expended on the Development.
5. The basic comparison, therefore, is £146,419,486 less sums for which the Part A Defendants would not have been responsible in any event (£11,121,968) less irrecoverable costs of £6,880,000. That totals £128,417,518, or such other sum as the Court may find.
6. Standard Life limits its Part A claim, as pleaded in paragraph 8 of the POC. That is £20,141,515 or such other sum as the Court may find, calculated as follows:
(1) the sum which ought to have been advised for outturn construction costs £100,591,463 (as calculated in Annex 6); plus
(2) the sum which ought to have been allowed for construction contingency at 5.25% £5,281,052; namely £105,872,515 less
(3) £85,731,000. On 29 July 2008, Gleeds advised in Financial Report No.7 £83,640,000 for outturn construction costs, not including construction contingency, and excluding fees and VAT. This advice was repeated by Gleeds on 4 September 2008 in Financial Report No.8. In its Appraisal of 14 August 2008, Shearer included a construction contingency of 2.5%. £83.64m plus 2.5% construction contingency, excluding fees, was £85,731,000."
"If, contrary to this Defence, Standard Life suffered loss as a result of breach of duty by Gleeds, Standard Life's recoverable loss is limited to the lesser of (a) and (b) below:
(a) Standard Life's actual loss on the Development to the extent reasonably foreseeable by Gleeds, but reduced for Standard Life's contributory negligence. Calculation of Standard Life's actual loss requires the following to be deducted from Costain's agreed final account:
(i) all costs caused by matters for which Gleeds was not responsible and which Gleeds could not reasonably foresee, such as the matters which in POC, Parts B and C, Standard Life alleges were caused by breach of duty on the part of other consultants and scope changes which Standard Life instructed;
(ii) the value of the completed Development;
(b) the difference between the sum(s) which Gleeds estimated as the cost of the Development before the Building Contract was made and the 'correct' estimate at that time."
"No deduction in the basic comparison is required for the value of the completed Development.
(a) Gleeds pleads no particularised case in law or in fact for the assertion.
(b) There is no benefit to deduct. Even if there were, it was not caused in fact and in law by Gleeds' breaches of duty. Even if it were, or in any event, it is collateral to the losses sustained by reason of the information, advice and performance particularly as to outturn construction cost for which Gleeds is liable being negligently wrong. In any event, the value of the Development has decreased. On Gleeds' logic, that increases the losses. Standard Life does not seek recovery of the same, for the same reasons above."
"If Standard Life establishes breach and causation against B4 (which is denied) the quantum of the claim is ill-conceived. Standard Life's claim has been calculated by applying a cap to its alleged total losses on the Development. However, Standard Life has not (as it should): (a) excluded losses with other causes, including the Part B claim; and (b) accounted for the benefits it has derived from the Development, including continued beneficial ownership."
"Paragraph 12(g) asserts that Standard Life's losses should deduct: (a) "losses with other cases", including Part B; and (b) account for "the benefits it has derived".
(a) As to any deductions to sums it in fact recovers pursuant to its claims in Part B and Section E2 of Part C POC, see Response 3(c) to Gleeds' RFI of 23 February 2020.
(b) No deduction in the basic comparison is required for the value of the completed Development.
(c) Buro 4 pleads no particularised case in law or in fact for the assertion.
(d) There is no benefit to deduct. Even if there were, it was not caused in fact and in law by Buro 4's breaches of duty. Even if it were, or in any event, it is collateral to the losses sustained by reason of the information, advice and performance particularly as to outturn construction cost, for which Buro 4 is liable, being negligently wrong. In any event, the value of the Development has decreased. On Buro 4's logic, that increases the losses. Standard Life does not seek recovery of the same, for the same reasons above."
"Shearer asserts in paragraph 3(b) of its Appendix 2 that Standard Life "must give credit for the value of the completed Development". That is denied.
(1) No deduction in the basic comparison is required for the value of the completed Development.
(2) Shearer pleads no particularised case in law or in fact for the assertion.
(3) There is no benefit to deduct. Even if there were, it was not caused in fact and in law by Shearer's breaches of duty. Even if it were, or in any event, it is collateral to the losses sustained by reason of the information, advice and performance particularly as to outturn construction cost for which Shearer is liable being negligently wrong. In any event, the value of the Development has decreased. On Shearer's logic, that increases the losses. Standard Life does not seek recovery of the same, for the same reasons above."
Parties' submissions
"Typically in the case of a negligent valuation of an intended loan security, the basic comparison called for is between (a) the amount of money lent by the plaintiff, which he would still have had in the absence of the loan transaction, plus interest at a proper rate, and (b) the value of the rights acquired, namely the borrowers covenant and the true value of the overvalued property."
Fourth, having carried out the basic comparison in order to ascertain the loss sustained as a matter of fact, it is then necessary to carry out a SAAMCo / MBS analysis in order to identify what if any part of the loss falls within the scope of the duty that has been breached by the defendant.
The applicable test
"The court may strike out a statement of case if it appears to the court:
(a) that the statement of case discloses no reasonable grounds for bringing or defending the claim "
i) If the pleaded facts do not disclose any legally recognisable claim against a defendant, it is liable to be struck out. However, the application must assume that the facts alleged in the pleaded case are true.
ii) It is not appropriate to strike out a claim in an area of developing jurisprudence, since in such areas, decisions as to novel points of law should be based on actual findings of fact: Barratt v Enfield BC [2001] 2 AC 550 per Lord Browne-Wilkinson at p.557.
iii) The court must be certain that the claim is bound to fail; unless it is certain, the case is inappropriate for striking out: Hughes v Colin Richards & Co [2004] EWCA Civ 266 per Peter Gibson LJ [22]-[23]; Rushbond v JS Design Partnership [2021] EWCA Civ 1889 per Coulson LJ at [41]-[42].
"The court may give summary judgment against a claimant on the whole of a claim or on a particular issue if
(a) it considers that
(i) that claimant has no real prospect of succeeding on the claim or issue; and
(b) there is no other compelling reason why the case or issue should be disposed of at a trial."
i) The court must consider whether the claimant has a "realistic" as opposed to a "fanciful" prospect of success: Swain v Hillman [2001] 1 All ER 91.
ii) A "realistic" claim is one that carries some degree of conviction. This means a claim that is more than merely arguable: ED & F Man Liquid Products v Patel [2003] EWCA Civ 472 at [8].
iii) In reaching its conclusion the court must not conduct a "mini-trial": Swain v Hillman.
iv) The court must take into account not only the evidence actually placed before it on the application for summary judgment, but also the evidence that can reasonably be expected to be available at trial: Royal Brompton Hospital NHS Trust v Hammond (No 5) [2001] EWCA Civ 550.
v) The court should hesitate about making a final decision without a trial, even where there is no obvious conflict of fact at the time of the application, where reasonable grounds exist for believing that a fuller investigation into the facts of the case would add to or alter the evidence available to a trial judge and so affect the outcome of the case: Doncaster Pharmaceuticals Group Ltd v Bolton Pharmaceutical Co 100 Ltd [2007] FSR 63.
vi) If the court is satisfied that it has before it all the evidence necessary for the proper determination of a short point of law or construction and the parties have had an adequate opportunity to address the question in argument, it should grasp the nettle and decide it. It is not enough to argue that the case should be allowed to go to trial because something may turn up which would have a bearing on the question of construction: ICI Chemicals & Polymers Ltd v TTE Training Ltd [2007] EWCA Civ 725.
vii) The burden of proof remains on the defendants to establish that the claimants have no real prospect of success and that there is no other reason for a trial.
Discussion and disposal
Conclusion
i) By 4.00pm on 24 June 2022:
a) The Claimant shall file and serve its draft amended particulars of quantum on Part A.
b) The Claimant shall file and serve Amended Particulars of Claim on Part C.
ii) By 4.00pm on 1 July 2022 the Defendants shall notify whether they consent or object to the amendments, and the basis of any objections. If objection is taken, the Claimant shall apply for permission to amend by 4.00pm on 8 July 2022. If no objection is taken, the draft served on 24 June 2022 shall stand as the Amended Particulars of Claim on Part A and Part C without need for re-service.
iii) By 4.00pm on 5 August 2022:
a) The Part A Defendants shall file and serve amended defences in response to the amended particulars of quantum.
b) The Second Defendant shall file and serve an Amended Defence in Part C, if so advised.
iv) By 4.00pm on 30 September 2022 the Claimant shall file and serve its amended Reply on the Part A and Part C claims, if so advised.