BUSINESS AND PROPERTY COURTS IN MANCHESTER
TECHNOLOGY AND CONSTRUCTION COURT (QB)
1 Bridge Street West Manchester M60 9DJ |
||
B e f o r e :
____________________
SHEPHERD CONSTRUCTION LIMITED |
Claimant |
|
- and - |
||
DRAX POWER LIMITED |
Defendant |
____________________
Crispin Winser QC (instructed by Pinsent Masons LLP) for the Defendant
Hearing date: 29th April 2021
____________________
Crown Copyright ©
COVID-19: This judgment was handed down remotely by circulation to the parties' representatives by email. It will also be released for publication on BAILII and other websites. The date and time of hand-down was 10.00am on 8th June 2021.
HH Judge Eyre QC :
The Issues.
The Relevant Terms of the Contract.
"14.9.1 The final Milestone Payment shall be paid to the Contractor in accordance with and subject to Clause 14 following the issue of the Taking-Over Certificate in respect of the whole of the Works and delivery of the Retention. Bond to the Employer in the form set out at Schedule 7 to the Contract Agreement (with such amendments as the Employer may agree (acting reasonably) and in an amount equal to 2.5% of the Contract Price in pounds sterling. No amount shall be due to the Contractor in respect of the final Milestone Payment until the Engineer has issued the Taking-Over Certificate in respect of the whole of the Works and received the Retention Bond. and any application for payment which seeks payment of the final Milestone Payment by the Contractor prior to such Taking-Over Certificate being issued and the Retention Bond being provided to the Employer as required by the Contract shall not be a valid Interim Statement and shall be deemed not to be submitted to the Engineer under the Contract.
14.9.2 Promptly after the latest of the expiry dates of the Defects Notification Periods, the Contractor shall be entitled to apply for payment of the outstanding balance of the Retention Money in the next Statement which amount shall, subject to Clause 14, be paid to the Contractor.
14.9.3 However, if any work remains to be executed under Clause 11 (Defects Liability) or Clause 12 (Tests after Completion), the Employer shall be entitled to withhold the estimated cost of this work until it has been executed and to deduct the same from amounts otherwise due to the Contractor until such time as the work is completed."
"the period for notifying defects in the Works or a Section (as the case may be) under Clause 11.1 (Completion of Outstanding Work and Remedying Defects). This shall be a period of twelve (12) months (with any extension under Clause 11.3 (Extension of Defects Notification Period)), calculated from the date on which the Works or Section is completed as certified under Clause 10.1 (Taking Over of the Works and Sections), except in relation to the Silo Bottoms (and in so far as they cannot sensibly be separated from the Silos, the Silos) where the period for notifying defects under Clause 11.1 shall be a period of twelve (12) months (with any extension under Clause 11.3 (Extension of Defects Notification Period)) calculated from the date on which Section 5 is completed as certified under Clause 10.1 (Taking Over of the Works and Sections)."
"(i) In relation to. the Works comprising and relating to Sections 1,1A and 2 only:
(a) 5%; until
(b) the Taking-Over Certificate has been issued in relation to Section 1, whereupon the percentage of retention shall be 3%; until
(c) the Taking-Over Certificate has been issued in relation to Sections 1,1A and 2,
whereupon the percentage of retention shall be 2.5%;
(ii) in relation to the Works comprising and relating to Sections 3,4 and 5:
(a) 5%; until
(b) the Taking-Over Certificate has been issued in relation to Section 3, whereupon the percentage of retention shall be 3%; until
(c) the Taking-Over Certificate. has been issued in relation to Sections 3, 4 and 5, whereupon the percentage of retention shall be 2,5%;
and the limit of Retention Money shall be 5% of the Contract Price."
"In relation to the Works comprising and relating to Sections 1, 1A, and 2:
14.9.1 Subject always to the Contractor's compliance with Clause 5.6.4 of the Contract in relation to Sections 1, 1A, and 2 the final Milestone Payment in relation to Sections 1, 1A, and 2 shall be paid to the Contractor in accordance with and subject to Clause 14 following the issue of the Taking-Over Certificate in respect ofthe whole of the WorksSections 1, 1A, and 2 and delivery of the Retention Bond to the Employer and in an amount equal to 2.5% of the part of the Contract Price relating to Sections 1, 1A, and 2 No amount shall be due to the Contractor in respect of the final Milestone Payment in relation to Sections 1, 1A, and 2 until the Engineer has issued the Taking Over Certificate in relation to Sections 1, 1A, and 2 and received the related Retention Bond, and any application for payment which seeks payment of the final Milestone Payment in relation to Sections 1, 1A, and 2 by the Contractor prior to such Taking-Over Certificate being issued and the related Retention Bond being provided to the Employer shall not be a valid Interim Statement
14.9.2 Promptly after the latest of the expiry dates of the Defects Notification Periods for Sections 1, 1A, and 2 the Contractor shall be entitled to apply for payment of theoutstanding balanceremaining part of the Retention Money referred to in limb (i)(c) of the definition `Retention Money' (taking into account any reduction in said amount by way of any claim or deduction by the Employer in relation to the Works) in the next Statement which amount shall, subject to Clause 14, be paid to the Contractor.
14.9.3 However, if any work remains to be executed under Clause 11 (Defects Liability) or Clause 12 ( Tests after Completion) the Employer shall be entitled to withhold the estimated cost of this work until it has been executed and to deduct the same from amounts otherwise due to the Contractor until such time as the work is completed.
In relation to the Works comprised and relating to Sections 3, 4, and 5:
14.9.4 Subject always to the Contractor's compliance with Clause 5.6.4 of the Contract in relation to Sections 3, 4, and 5, the final Milestone Payment in relation to Sections 3, 4, and 5 shall be paid to the Contractor in accordance with and subject to Clause 14 following the issue of the Taking-Over Certificate in respect of Sections 3, 4, and 5 and delivery of the Retention Bond to the Employer and in an amount equal to 2.5% of the part of the Contract Price relating to Sections 3, 4, and 5 No amount shall be due to the Contractor in respect of the final Milestone Payment in relation to Sections 3, 4, and 5 until the Engineer has issued the Taking Over Certificate in relation to Sections3, 4, and 5 and received the related Retention Bond and any application for payment which seeks payment of the final Milestone Payment in relation to Sections3, 4, and 5 by the Contractor prior to such Taking-Over Certificate being issued and the related Retention Bond being provided to the Employer shall not be a valid Interim Statement
14.9.5 Promptly after the latest of the expiry dates of the Defects Notification Periods for Sections 3, 4, and 5 the Contractor shall be entitled to apply for payment of the remaining part of the Retention Money referred to in limb (ii)(c) of the definition `Retention Money' (taking into account any reduction in said amount by way of any claim or deduction by the Employer in relation to the Works) in the next Statement which amount shall, subject to Clause 14, be paid to the Contractor.
14.9.6 However, if any work remains to be executed under Clause 11 (Defects Liability) or Clause 12 ( Tests after Completion) the Employer shall be entitled to withhold the estimated cost of this work until it has been executed and to deduct the same from amounts otherwise due to the Contractor until such time as the work is completed."
The Interpretation of Clause 14.9.6.
Was there Exclusion of the Defendant's Potential Claims by Way of Equitable Set-Off or Abatement?
The Validity of Interim Payment Application 35A.
"All your remaining purported `claims' or `deductions' in respect of the BDS Works remain unexplained and/or unsubstantiated and, as we have explained on a number of occasions, for the purposes of this application we refute (sic) the same".
Conclusion.
Note 1 In the varied Contract the additions are underlined. Other than showing the amendments the underlining is of no significance and is not repeated here. [Back]