BUSINESS AND PROPERTY COURTS IN BIRMINGHAM
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Priory Courts 33 Bull Street Birmingham B4 6DS |
||
B e f o r e :
____________________
Mrs Gurpreet Kang Mr Avtar Singh |
Claimants |
|
- and - |
||
Mr Kultarn Singh Pattar |
Defendant |
____________________
Mr William Knapman (instructed by Aspect Law) for the Defendant
Hearing dates: 11 January 2021 to 14 January 2021 and 27 January 2021
____________________
Crown Copyright ©
Her Honour Judge Sarah Watson:
Introduction and background
The issues
The evidence
The contracting parties and agency
" (5) The terms of the contract may, expressly or by implication, exclude the principal's right to sue, and his liability to be sued. The contract itself, or the circumstances surrounding the contract, may show that the agent is the true and only principal."
"If he tells a lie relating to any part of the contract or its subject-matter, which induces another person to contract to deal with his property in a way which he would not do if he knew the truth, the man who tells the lie cannot enforce his contract."
"Where personal considerations enter into a contract, error as to the person with whom the contract is made annuls the contract; not so where the person sought to be bound would have been equally willing to make the same contract with any other person …
Whenever the consideration of the person with whom I am willing to contract enters as an element into the contract which I am willing to make, error with regard to the person destroys my consent and consequently annuls the contract. .... On the contrary, when the consideration of the person with whom I thought I was contracting does not enter at all into the contract, and I should have been equally willing to make the contract with any person whatever as with him with whom I thought I was contracting, the contract ought to stand."
The terms of the Varied Contract and incorporation of construction drawings
"The plans were approved by the Walsall Council (sic) on 11th January 2018. Following approval, the Clients requested further works and updated cost was agreed at £118,810."
"16 On 11 January 2018, the architectural plans were approved by Walsall Council. In view of this approval, the Claimant requested that the Defendant undertake certain further works not originally specified.
17 That same month, in January 2018, Mr Singh, acting on behalf of the Claimants, made payment of £10,000 to the Defendant…"
"In March 2018, the Defendant was provided with a number of documents, which together set out the scope and specification of the varied works…
19 Thereafter, in March 2018, the Defendant…agreed with Mr Singh…. that he would undertake the Varied Works"
"Following the approval from Walsall Council, Mr Pattar continued with the build and we continue to pay him as agreed. He promised us he would complete his work (i.e. the more extensive works that we had obtained permission to do) in April/May 2018 and the house would be met ready to move into."
Termination and repudiatory breach
The Claimants' claims for damages for delay
Valuation of work completed and remedial work
The expert evidence
Mr Singh's involvement on site
Staircase
Wiring
Piping to radiators
Overheads and profit
Remedial works
Drains
"New plumbing and drainage throughout whole property with it all being tested and inspected thoroughly with accessible manholes and rodding access for all the house".
Dormer cheeks
Flooring sheets
Wallplate
Timber purlins
Roof and floor timbers
Timber packing
Stairs and landing
Blockwork and brickwork
Ducting
Site conditions and security
"What your plans for moving the sand in front of the house? The lads will have all the other rubbish removed by Wednesday, we have an old bath and all double glazing units to remove?"
Living room joists
Dormer oversized
End bedroom unsupported
Rear roof canopy
The Defendant's claim for lost profit
Item |
Decision |
Value of work completed |
|
Value of completed work agreed between the experts |
£71,552 |
Staircase |
Nil |
Wiring |
£3,500 |
PVC push fit piping to radiators |
£3,400 |
Difference between agreed profit of 15% and profit allowed at 20% on the value of works agreed between the experts |
£3,111 |
Profit of 20% on the disputed items awarded (totalling £6,900) |
£1,380 |
Subtotal: value of completed work before allowance for remedials |
£82,943 |
Remedial work |
|
Drainage |
Nil |
Dormer cheeks |
£50 |
Flooring sheets |
Nil |
Wallplate |
Nil |
Timber purlins |
£400 |
Roof and floor timbers |
£270 |
Timber packing |
£225 |
Stairs and landing |
Nil |
Blockwork/brickwork |
£400 |
Ducting |
Nil |
Site condition/security |
Nil |
Living room joists |
Nil |
Dormer oversized |
Nil |
End bedroom unsupported |
Nil |
Rear roof canopy |
Nil |
Subtotal remedial works allowed |
£1,345 |
Balance payable to the Defendant for the Varied Contract works completed, net of remedial costs allowed |
£81,598 |
Less: paid on account |
£69,300 |
Balance due to the Defendant after payment already received |
£12,298 |
Defendant's lost profit on balance of the contract price of £38,069 |
£ 6,344 |
Total due to the Defendant |
£18,642 |