BUSINESS AND PROPERTY WORK
TECHNOLOGY AND CONSTRUCTION COURT
Bridge Street, Manchester M60 9DJ |
||
B e f o r e :
____________________
OPTIMUS BUILD LIMITED |
Claimant |
|
- and - |
||
(1) MATTHEW SOUTHALL (2) JADE McMANUS |
Defendants |
____________________
Simon Arnold (instructed by JMW Solicitors LLP, Manchester) for the defendants
Hearing dates: 24, 25 November, 2 December 2020
Draft judgment circulated on 4 December 2020
____________________
HTML VERSION OF JUDGMENT
Crown Copyright ©
His Honour Judge Stephen Davies :
Legal principles
"When interpreting a written contract, the court's task is to ascertain the objective meaning of the language which the parties have chosen to express their agreement. It does so, having regard to the meaning of the relevant words in their documentary, factual and commercial context. That meaning has to be assessed in the light of:
(i) the natural and ordinary meaning of the clause;
(ii) any other relevant provisions of the contract;
(iii) the overall purpose of the clause and the contract;
(iv) the facts and circumstances known or assumed by the parties at the time that the document was executed; and
(v) commercial common sense; but
(vi) disregarding subjective evidence of any party's intentions.
See: Arnold v Britton [2015] UKSC 36 per Lord Neuberger at paras. [15] to [23]; Wood v Capita Insurance Services Ltd [2017] UKSC 24 per Lord Hodge at paras. [8] to [15]."
"Secondly, I am amply persuaded that the estimate did not give rise to a fixed price contract. In this connection, I do not think that there is any "magic" in the label "estimate"; certainly in the present case, I do not regard that label as a term of art. However, I do regard both the context and language of the estimate as pointing decisively against this being a fixed price contract "
The witnesses and their credibility
Relevant events
Contract formation
Works commencement
Interim valuations 1 and 2
The falling out over the third interim valuation
The email of 5 October 2018
"The meeting on Wednesday was extremely concerning and left us feeling like you were trying to reduce our price retrospectively without foundation. Our Valuation 3 remains our assessment of the value of works up to the end of September 2018. We have subsequently carried out a further weeks work since then and see no reason why the Valuation cannot be payed (sic) in full subject to the reduction mentioned above. We genuinely wish to complete our works on this project but due to our uneasy feeling following the meeting on Wednesday we believe the way to move forward on this project should be under the following circumstances:
(a) Valuation 3 is paid as described above.
(b) The full scope of our remaining works is established.
(c) A payment plan is put in place to cover the remaining works that is mutually acceptable.
We would suggest a meeting as soon as possible to try and agree a way forward and will be happy to meet to try and come to an acceptable resolution. Until we feel comfortable with the situation we will not be carrying out any further works on the project. We hope this adequately clarifies our position."
The defendants' response and the termination of the contract
"Hi Matt and Jade, It is sad that matters got heated but without payment I feared I would be unable to pay the suppliers and subcontractors but I have now got over that hurdle. Where we are is that I think we need to meet up to discuss matters with a view to working together to complete the project that we agreed. The roof trusses are still available and we will schedule those shortly, but in the meantime the scaffolders will be on site before the end of the week and our steel man will come to site to measure as planned. So please let me know when you are free to meet?"
Valuation of the claimant's claims
The claim for the value of the works undertaken by the claimant pre-termination
The claim for loss of profit
Summary
The counterclaim
"This delay lead to us incurring significant costs. While we were awaiting completion of the works at the Property were living in a rental accommodation, at a cost of £2,500 per month, and paying finance of 1% on a loan of £250,000. This loan expired in April 2019 and, with the Property unmortgageable due to its incomplete state, we had to take out a bridging loan that incurred included 6 months interest at £20,377.50, £10,725 in broker fees and £1,560 in legal fees."
Note 1 Construction contracts with a residential occupier are excluded from the ambit of Housing Grants, Construction and Regeneration Act 1996. [Back] Note 2 It is common ground that this was intended to and understood as a reference to tranches. [Back] Note 3 This is taken from the final account claim and I assume is gross of VAT. [Back]