BUSINESS AND PROPERTY COURTS IN MANCHESTER
TECHNOLOGY AND CONSTRUCTION COURT (QBD)
B e f o r e :
sitting as a Judge of the High Court
____________________
SANDERSON LIMITED | Claimant | |
AND | ||
SIMTOM FOOD PRODUCTS LIMITED | Defendant |
____________________
Mr Jamie Jenkins (instructed by Direct Access) for the Defendant.
Hearing dates: 8th, 9th, 12th November and 20th December 2018
____________________
Crown Copyright ©
Judge Halliwell:
(1) Introduction
(2) Factual sequence
(3) Witnesses
14.1.1. The Claimant's witnesses included Mr Nicholas Bird (commercial director), Mr Michael Gallagher (sales director) and Mr Nicholas Slater (former client services manager), all of whom attended the February 2016 Meeting. Mr Slater also attended the meetings on 1st June and 21st July 2015, and Mr Gallagher attended the meeting on 17th June 2015.
14.1.2. Amongst the Claimant's other witnesses, Ms Janet Cartlidge and Mr James Rogers attended the Defendant's business premises for the business review on 20th and 21st January 2015. Ms Cartlidge and Mr Graeme Spencer-also called to give evidence-were involved in the preparation and delivery of the workshops.
14.1.3. In addition, the Claimant called Mr Richard Budd as a witness. Mr Budd was formerly employed by the Defendant as "Supply Chain Coordinator". He was given responsibility for the management of the project until September 2015, when he left the Defendant.
(4) The Contract
(5) Who was culpable for the lack of progress during late 2014-2015, what was agreed at the February 2016 Meeting and what happened in the aftermath?
(6) The correspondence leading up to the termination of the Contract.
(7) How, when and on what basis was the Contract brought to an end?
49.4.1. demanded written answers to a series of questions, many of which could more conveniently have been dealt with at the meeting itself;
49.4.2. sought to cast responsibility on the Claimant, rather than the Defendant, for the "numerous issues which arose in 2015";
49.4.3. stated that "we need to have our confidence fully in place before we can proceed"; and
49.4.4. asserted, baldly, that the Defendant had "never committed to any specific date" notwithstanding the discussions at the February 2016 Meeting and Mr Chandarana's confirmation, in answer to a question from Mr Gallagher, that the project would re-start on 1st February or sooner.
49.5.1. Contrary to the impression given by Mr Davies, the parties had agreed to suspend the project at the Defendant's request in order to meet its own lack of resources or, at least to accommodate the Defendant's unwillingness to commit such resources. The reasonable recipient would thus have been minded to look beyond the 21st February 2017 Email in considering the Defendant's want of co-operation.
49.5.2. The most obvious explanation for the Defendant's want of co-operation is that it was no longer ready, willing or able to proceed with the project, at least in accordance with its contractual commitments. From the time of his appointment, Mr Davies did nothing to conceal his hostility to the project. According to Mr Slater's oral testimony, Mr Davies advised him, as early as 1st June 2015, that he didn't want to see the incorporation of any new systems whilst he was still in work. His account of this was disputed by Mr Davies. However, on this point, I prefer the evidence of Mr Slater. It was based on his own specific recollection of a discussion on the occasion of their very first meeting. It is also consistent with a comment from Mr Slater at the end of the February 2016 Meeting ("I just thought about Andy who said, 'I've only just put one system in and I was hoping to retire before I put the next one in".) Moreover, the Claimant and any reasonable recipient with the same knowledge and information would have been mindful of the failure of the Defendant, from the outset, to accommodate the project properly or commit the resources it required.
(8) Disposal