BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (QBD)
7 Rolls Building, Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
____________________
AMEY LG LIMITED |
Claimant |
|
- and - |
||
AGGREGATE INDUSTRIES UK LIMITED |
Defendant |
____________________
James Howells QC (instructed by Macfarlanes LLP) for the Defendant
Hearing dates: 7th – 9th October 2019.
____________________
Crown Copyright ©
HH Judge Eyre QC:
Introduction.
The Parties' Dealings.
"The Subcontractor shall issue its final statement to the Contractor within one month following the completion of the Services".
"Notwithstanding clause 17 (b) the Subcontractor shall submit his final statement for each Works Order together with full substantiation as required by the Contractor to the Contractor within one month of completion of the Works Order."
i) "Actual Costs" were defined as being:
"Labour, plant, and material expense incurred in carrying out the works (excludes overheads and profit). Actual Costs will be established through transparent open book audit on an initial basis and thereafter on an annual basis".
ii) The proposed clause 17.1.4 (e) provided that:
"If the actual cumulative cost of treatment and disposal of the above stated material varies positively or negatively from the forecast total … then a pain/gain share shall apply on a 50/50 basis between the parties subject to substantiation and agreement of quantities and Actual Costs."
iii) The proposed clause 17.1.4 (g) provided that:
"Audits of Actual Cost will be on a sample basis. Such audits to be carried out at the Contractor's discretion without notice. If in the Contractor's opinion there is a significant variation in a sample audit a further detailed audit may be invoked. The findings of such audit may vary the allocation within the pain gain mechanism. …."
The Earlier Judgments and their Effect.
i) The final statement was then due to be submitted by the Defendant; and
ii) The Defendant's entitlement to any further payment or any correction of any payment entitlement under the Subcontract post-termination would arise exclusively through the final statement mechanism of the Subcontract
were to continue as if they had been begun under Part 7. As will be seen there has been some variation and expansion of the declarations being sought.
"… by varying the payment regime from the outset of the contract, the parties must have necessarily intended that the final payment regime would be varied in like manner. The consequence of this was that, instead of having individual final accounts for each Works Order, with a separate statement required within one month of completion of that Works Order, the parties must have intended to provide for a single final account process within one month of completion of all the Services ordered pursuant to the Subcontract."
"…Whatever legal or equitable consequences may flow from what the parties did and said, what seems plain to me is that they intended those arrangements to apply to and impact upon the Subcontract itself. The terms of the draft Tar Agreement and, indeed, the way the parties conducted themselves both involved the making of payments within and as an intrinsic part of the interim payment regime of the Subcontract…."
"That having been said, if "now" means November 2018, the tar instalments (if due) have come to an end. It seems to me that, thereafter, a reasonable period should be allowed for any residual ascertainment of actual cost (with any audit in respect thereof) and implementation of the pain-gain provisions. In that context, I bear in mind that such costs will have been expended before July 2017 and should, by now, be capable of ascertainment. There was no argument about timescale but I can do no more than say that there must come a time (or have come a time) by which the implementation of those provisions must come to an end and be replaced with the requirement for [the Defendant] to provide the final statement."
"the Defendant is not entitled to claim further payment adjustments to previous interim payments by way of adjudication but will be able to adjudicate any dispute as to its final payment entitlement upon crystallisation of the dispute following the submittal of a final statement."
The Parties' Contentions in Outline.
The Declarations Sought.
"Clarification of the issues underlying the declarations was by no means an easy undertaking. Both in his skeleton argument and orally at the hearing, Mr Hickey suggested that the Court should either give the declarations sought or "such declarations as it considered appropriate for the reasons set out in this Skeleton and as expounded at the oral hearing". During the hearing, as the argument ebbed and flowed, Mr Hickey suggested that the declarations that his client had sought could be modified as appropriate to address the real issues, as he saw them, between the parties…"
Did the Tar Agreement and the Parties' Actions give rise to an Estoppel or to a varied Contract?
When was the Defendant obliged provide a Final Statement?
Is the Defendant in breach of its Obligation?
The Declarations to be granted.
"the Defendant is not entitled to claim further payment adjustments to previous interim payments by way of adjudication but will be able to adjudicate any dispute as to its final payment entitlement upon crystallisation of the dispute following the submittal of a final statement."
"…pending resolution of the final payment, [the Defendant] is entitled to bring a claim through adjudication in respect of adjustments to amounts notified in respect of previous interim payments. Once (and if) it is accepted that [the Defendant] had a right to apply for such interim payments, both before and even after termination (whether pursuant to an agreement or on a convention basis) it must follow that the amounts so notified could be challenged by way of review."
"Insofar as the Court might, contrary to [Mr. Hickey's] case, see it as permissible for [the Defendant] to seek certain adjustments to interim payments in adjudication, involving an opening up, review and revision of a given Payment Notice so as to assess the true value of the sum due, he invited the Court to say [the Defendant] could not do so in a piecemeal fashion. Complaint was made that [the Defendant]'s claims had sought further sums, not on the basis of true value, but on the (disputed) basis that [the Claimant]'s own valuation methodology was accepted."
"If those sorts of granular or contingent claims are made to the adjudicator in respect of a given application, it will be for him or her to determine the permissibility of that approach in the first instance. If it becomes appropriate to revisit that question in Court, whether on enforcement or by way of a separate Part 8 claim, then the issues about that can be properly ventilated in those proceedings at that time."