BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (QBD)
Fetter Lane, London, WC2A 2LL |
||
B e f o r e :
____________________
C SPENCER LIMITED |
Claimant |
|
- and - |
||
MW HIGH TECH PROJECTS UK LIMITED |
Defendant |
____________________
Simon Hargreaves QC & Tom Owen (instructed by Clyde & Co LLP) for the Defendant
Hearing date: 1st July 2019
____________________
Crown Copyright ©
Mrs Justice O'Farrell:
Background to the dispute
"We enclose our interim application for payment No.32 in respect of the period ending 31st January 2019 in respect of the above Sub-Contract in the sum of £34,611,646.42 (includes 2.5% Retention deducted) excluding VAT.
As you are aware this is a "hybrid contract" where some of the works carried out by CSL are construction operations within the meaning of the Housing Grants, Construction and Regeneration Act 1996 (as amended) ("the Act") and some of the works are not construction operations within the meaning of the Act. The enclosed application therefore draws a distinction between construction operations that are subject to the Act (entitled "Inc Operations") and other operations which are not so subject (entitled "Exc Operations").
Until now, this is not a distinction which either party has previously made in respect of the payment process. However, following the abortive adjudication of last year, we now consider it to be appropriate given the acknowledgement of both parties that this is a hybrid contract.
Accordingly, we look forward to receiving your assessment of the sum due in respect of:
a) The sum applied for in respect of construction operations that are subject to the Act;
b) The sum applied for in respect of other operations which are not so subject.
Please forward your certification for payment to the undersigned "
"We refer to the Civils, Structural and Architectural Subcontract between you and us dated 20th November 2015 and your application for payment dated 4th February 2019 for the sum of £3,353,219.22 excluding VAT.
We hereby give you notice of the sum that we consider to be, or to have been due at the payment due date in respect of the above application being a Certificate that the Subcontractor owes the Contract £6,818,521.70 excluding VAT. [T]he basis on which that sum is calculated, is set out in the attached spreadsheet [CSL Application 32 M+W Assessment 35xlsx]."
The Claim
i) On a proper construction of the Act and clause 38.4 of the Subcontract, any certificate of payment issued by the Contract Manager must identify the sum assessed as due at the payment due date in respect of those works that comprise construction operations and the basis on which that sum is calculated.
ii) The certificate of payment was not a valid notice of payment for the purpose of section 110A(2) of the Act because it failed to identify that part of the amount assessed as due in respect of construction operations and the basis of that calculation. It simply assessed the overall sum due in respect of both construction and non-construction works.
iii) In the absence of a valid payment notice or any pay less notice, pursuant to section 111 of the Act, the "notified sum" to which CSL became entitled was the amount assessed as due in its application for payment.
i) The payment provisions in the Subcontract are compliant with the requirements of the Act. Payment notice 35 complies with the requirements of section 110A of the Act. The parties decided that all operations would be subject to the same payment regime. They were entitled to do so and it did not make an otherwise compliant scheme thereby non-compliant.
ii) If CSL's argument is correct, which is disputed, CSL must prove that all sums claimed in these proceedings are sums for construction operations.
iii) The Subcontract is a milestones contract and it is not possible to distinguish between included and excluded operations.
iv) CSL is estopped by convention from contending that the parties' agreement requires that applications for payment and payment notices distinguish between included and excluded operations.
v) MW is entitled to rely on the payment notice as notice of its cross-claims.
vi) MW is entitled to rely on the payment notice as a pay less notice.
vii) MW is entitled to raise a set-off in the sum of £6,818,521.70.
i) on a proper construction of the Subcontract and the Act, whether MW issued a valid payment notice in response to CSL's application no.32;
ii) whether CSL is estopped from relying on its construction argument;
iii) if MW failed to issue a valid payment notice, whether CSL is entitled to rely on its payment application as "the notified sum" for the purposes of the Act;
iv) whether MW is entitled to rely on its negative valuation as a pay less notice, cross-claim or set off;
v) whether this claim is suitable for determination by Part 8 proceedings.
The Subcontract
"The Subcontract constitutes the entire agreement between the Contractor and the Subcontractor with respect to the performance of the Subcontract Works and supersedes any prior negotiation, representation or agreement relating thereto, whether written or oral, except to the extent that they are expressly incorporated in the Subcontract. No change, alteration or modification to the Subcontract shall be effective unless the same shall be in writing and signed by both parties. The Contractor and the Subcontractor agree that they shall not be entitled to enforce or otherwise rely on any term or condition (including but not limited to any term or condition, standard or otherwise, contained in a Quotation, acceptance of Quotation, Purchase order or any Standard Terms and Conditions of either party) which is not contained or incorporated expressly in the Subcontract."
Clause 38.1
"The Contractor shall pay the Subcontractor the Subcontract Price in instalments against completed Milestone Events as set out in table [14.5] of Schedule 14 (Subcontract Price and payment), subject to:
(a) Sub-clause 38.1A and clause A2 (Retention Bond); and
(b) the aggregate of the amounts having been paid and which are due to be paid to the Subcontractor as at the relevant payment date not exceeding the amount stated in the "Cumulative" column of table [14.5] of Schedule 14 (save where amounts payable to the Subcontractor are adjusted in accordance with Clause 18 or 19, or approved for early payment under 38.2A)."
Clause 38.2
"If any instalment is to be paid upon the completion of a specified task or milestone, the Subcontractor shall only be entitled to apply for payment for that instalment when he can provide evidence of completion of the task or milestone as stated in Schedule 14.
The Subcontractor may not include in any request for payment the value of any work that has not been carried out on or before the date of the application or for a Milestone Event which has not been completed "
Clause 38.3
"The Subcontractor shall submit a request for payment to the Contract Manager at intervals of not less than one calendar month showing:
(a) the Subcontractor's assessment of the amount to be paid for Subcontract Works carried out up to the end of the period for which it is submitted, together with any other scheduled payment as may have become payable;
plus
(b) the amounts to which the Subcontractor considers himself entitled in connection with all other matters for which provision is made under the Subcontract;
less
(c) the total of all sums previously certified by the Contract Manager for payment.
The Subcontractor's requests for payment shall each state the sum that the Subcontractor considers is to be paid and the basis upon which the amount applied for is calculated and shall be supported by all relevant documentary evidence appropriately itemised."
Clause 38.3A
"Each instalment of the Subcontract Price shall become due on the date which is:
(a) 16 days after the date of the Subcontractor's request for payment of that instalment in accordance with clause 38.3; or
(b) 56 days after the date of the Subcontractor's request for payment in accordance with clause 38.3, in the case of the final request for payment.
The Subcontractor's final request for payment shall state that it is his final request for payment."
Clause 38.4
"Sixteen days after the date of the Subcontractor's request for payment in accordance with clause 38.3, or in the case of the final request for payment fifty-six days after that date, the Contract Manager shall issue a certificate to the Subcontractor and the Contractor for the instalment to which the request for payment relates. The certificate shall show the sum which the Contract Manager considers to be due at the payment due date determined in accordance with Sub-clause 38.5, and the basis on which it has been calculated. The total certified shall comprise all sums listed in the Subcontractor's statement which, in the opinion of the Contract Manager, are properly payable under the Subcontract and shall show separately any elements within the sums certified in respect of nominated Sub-subcontractors. The Contract Manager may in any certificate delete, correct or modify any sum previously certified by him as he shall consider proper. If in respect of any Subcontractor's request for payment, the contractor, or the Contract Manager on his behalf, considers that nothing is due to the Subcontractor he shall issue a certificate for zero."
Clause 38.5
"In respect of each instalment of the Subcontract Price the Contractor shall pay the Subcontractor the amount specified in clause 38.6 (or, if applicable, the amount specified in a notice under clause 38.7) on a date 19 days after the payment due date of that instalment (Final Date for Payment)."
Clause 38.6
"Subject to clauses 38.7 and 41.1A (Subcontractor's Insolvency) the amount to be paid by the Contractor under clause 41.5 in respect of each instalment of the Subcontract Price is:
(a) the amount certified for payment in the relevant Contract Manager's certificate issued under clause 38.4; or
(b) if the Contractor, or the Contract Manager on his behalf, omits to issue such certificate, the amount applied for in the relevant Subcontractor's application under clause 38.3."
Clause 38.7
"If the Contractor intends to pay less than the sum due in accordance with Sub-clause 38.4 or 38.6 for any reason including any sum that may be due from the Subcontractor to the Contractor under the Subcontract or any sum not payable in accordance with Sub-clause 41.5, the Contractor shall notify the Subcontractor not later than one day before the Final Date for Payment, specifying the amount he considers to be due on the date the notice is given and the basis on which that sum is calculated."
Clause 38.8
"For the purposes of the Late Payment of Commercial Debts (Interest) act 1998, the rate of interest payable on any sum withheld contrary to any requirement of the Subcontract Conditions is 3% (simple) over the Agreed Rate."
Clause 38.11
"If the amount of a payment which is:
(a) notified in accordance with Sub-clause 38.4 (and no notice is given by the Contractor under Sub-clause 38.7 in respect of such payment); or
(b) stated in a notice given by the Contractor under Sub-clause 38.7;
is referred to an adjudicator appointed in accordance with Clause 44 (Adjudication) and if the decision of the adjudicator as to the amount which is to be paid by the Contractor is that more shall be paid than the amount stated as in (a) or (b) as applicable, the additional amount shall be paid not later than:
(i) seven days from the date of the adjudicator's decision; or
(ii) the Final Date of Payment;
whichever is the later."
Clause 42.5
"Nothing in the Subcontract Conditions (other than provisions for the giving of notices) shall exclude or limit any right of set-off in law or equity."
" either party shall have the right to refer any dispute or difference (including any matter not referred to the Contract Manager in accordance with Sub-clause 43.3) as to a matter under or in connection with the Subcontract to adjudication and either party may, at any time, issue a Notice (a 'Notice of Adjudication') to the other stating his intention to do so "
"This clause 44 applies only to the extent (if any) required by [the Act]."
The Act
"(1) In this Part a "construction contract" means an agreement with a person for any of the following
(a) the carrying out of construction operations
(5) Where an agreement relates to construction operations and other matters, this Part applies to it only so far as it relates to construction operations."
"(1) In this Part "construction operations" means, subject as follows, operations of any of the following descriptions
(2) The following operations are not construction operations within the meaning of this Part
(c) assembly, installation or demolition of plant or machinery, or erection or demolition of steelwork for the purposes of supporting or providing access to plant or machinery, on a site where the primary activity is
(i) power generation "
"(1) A party to a construction contract has the right to refer a dispute arising under the contract for adjudication under a procedure complying with this section.
(5) If the contract does not comply with the requirements of subsections (1) to (4), the adjudication provisions of the Scheme for Construction Contracts apply."
"(1) A party to a construction contract is entitled to payment by instalments, stage payments or other periodic payments for any work under the contract
(2) The parties are free to agree the amounts of the payments and the intervals at which, or circumstances in which, they become due.
(3) In the absence of such agreement, the relevant provisions of the Scheme for Construction Contracts apply.
"(1) Every construction contract shall
(a) provide an adequate mechanism for determining what payments become due under the contract, and when, and
(b) provide for a final date for payment in relation to any sum which becomes due.
The parties are free to agree how long the period is to be between the date on which a sum becomes due and the final date for payment.
(3) If or to the extent that a contract does not contain such provision as is mentioned in subsection (1), the relevant provisions of the Scheme for Construction Contracts apply."
"(1) A construction contract shall, in relation to every payment provided for by the contract
(a) require the payer or a specified person to give a notice complying with subsection (2) to the payee not later than five days after the payment due date, or
(b) require the payee to give a notice complying with subsection (3) to the payer or a specified person not later than five days after the payment due date.
(2) A notice complies with this subsection if it specifies
(a) in a case where the notice is given by the payer
(i) the sum that the payer considers to be or to have been due at the payment due date in respect of the payment, and
(ii) the basis on which that sum is calculated
(3) A notice complies with this subsection if it specifies
(a) in a case where the notice is given by the payer
(i) the sum that the payee considers to be or to have been due at the payment due date in respect of the payment, and
(ii) the basis on which that sum is calculated
(4) For the purposes of this section, it is immaterial that the sum referred to in subsection (2)(a) or (b) or (3)(a) may be zero
(5) If or to the extent that a contract does not comply with subsection (1), the relevant provisions of the Scheme for Construction Contracts apply."
"(1) This section applies in a case where, in relation to any payment provided for by a construction contract
(a) the contract requires the payer or a specified person to give the payee a notice complying with section 110A(2) not later than five days after the payment due date, but
(b) notice is not given as so required.
(2) Subject to subsection (4), the payee may give to the payer a notice complying with section 110A(3) at any time after the date on which the notice referred to in subsection (1)(a) was required by the contract to be given.
(3) Where pursuant to subsection (2) the payee gives a notice complying with section 110A(3), the final date for payment of the sum specified in the notice shall for all purposes be regarded as postponed by the same number of days as the number of days after the date referred to in subsection (2) that the notice was given.
(4) If
(a) the contract permits or requires the payee, before the date on which the notice referred to in subsection (1)(a) is required by the contract to be given, to notify the payer or a specified person of
(i) the sum that the payee considers will become due on the payment due date in respect of the payment, and
(ii) the basis on which that sum is calculated, and
(b) the payee gives such notification in accordance with the contract,
that notification is to be regarded as a notice complying with section 110A(3) given pursuant to subsection (2) (and the payee may not give another such notice pursuant to that subsection)."
"(1) Subject as follows, where a payment is provided for by a construction contract, the payer must pay the notified sum (to the extent not already paid) on or before the final date for payment.
(2) For the purposes of this section, the "notified sum" in relation to any payment provided for by a construction contract means
(a) in a case where a notice complying with section 110A(2) has been given pursuant to and in accordance with a requirement of the contract, the amount specified in that notice;
(b) in a case where a notice complying with section 110A(3) has been given pursuant to and in accordance with a requirement of the contract, the amount specified in that notice;
(c) in a case where a notice complying with section 110A(3) has been given pursuant to and in accordance with section 110B(2), the amount specified in that notice.
(3) The payer or a specified person may in accordance with this section give to the payee a notice of the payer's intention to pay less than the notified sum.
(4) A notice under subsection (3) must specify
(a) the sum that the payer considers to be due on the date the notice is served, and
(b) the basis on which that sum is calculated.
It is immaterial for the purposes of this subsection that the sum referred to in paragraph (a) or (b) may be zero.
(5) a notice under subsection (3)
(a) must be given not later than the prescribed period before the final date for payment, and
(b) in a case referred to in subsection (2)(b) or (c), may not be given before the notice by reference to which the notified sum is determined.
(6) Where a notice is given under subsection (3), subsection (1) applies only in respect of the sum specified pursuant to subsection (4)(a)."
"Where any provisions of the Scheme for Construction Contracts apply by virtue of this Part in default of contractual provision agreed by the parties, they have effect as implied terms of the contract concerned."
Construction of the Subcontract
"[63] It follows that the statute contemplated a position where one agreement related to both construction operations under section 105(1) and operations which were excluded by section 105(2).
[64] It also follows that the right to refer disputes to adjudication under section 108, the entitlement to stage payments under section 109, the provisions as to dates of payment under section 110, the provisions as to notice of intention to withhold payment under section 111, the right to suspend performance for non-payment under section 112 and the prohibition of conditional payment provisions under section 113 will only apply to the subcontract in this case, insofar as the subcontract relates to construction operations
[91] It is clear that the legislation could have dealt with agreements which related both to construction operations and to "other matters" being operations which were not construction operations, in a number of ways. It would have been possible to treat them either as being agreements for construction operations or as not being agreements for construction operations. It would also have been possible for that question to depend on the relative values of the construction operations and of the "other matters". It is clear that Parliament decided that, just because an agreement related, in part, to operations which were not construction operations, this did not prevent the implied terms under section 114(4) of the Act from applying to the construction operations. It follows that a party can refer a dispute arising under the agreement, insofar as it relates to construction operations, to adjudication under a procedure complying with section 108 of the Act. In this case the contract contained no provision for adjudication and it is common ground that any adjudication would have to be carried out in accordance with the Scheme for Construction Contracts ("the Scheme")."
"[21] At one point, it was apparent that Mr Hickey was itching to submit that the provisions in the 1996 Act ought to be incorporated wholesale, even in a hybrid contract, to apply to all the works. But it seems to me that, first, that submission would have run counter to s 104(5), which expressly provides that the provisions in the Act apply 'only so far as' they relate to construction operations; and secondly, ignores the fact that the parties have expressly agreed a different payment regime In my view, the court must uphold that different regime in respect of all claims to payment in respect of works which are excluded by the 1996 Act.
[22] This means that, under a hybrid contract such as this, there are two very different payment regimes. That is what Ramsey J indicated in Cleveland Bridge. Although I find that uncommercial, unsatisfactory and a recipe for confusion, it is the inevitable result of Parliament's desire to exclude what would otherwise have been obvious construction operations from the ambit of the 1996 Act."
"[32] The whole point of the default provisions in the 1996 Act, by which an employer becomes liable for the sum notified, is to encourage simplicity and clarity. If x notifies y of a claim for £1,000, and y does not respond in the prescribed time to challenge that claim, £1,000 becomes due because it is the notified sum. Introducing the possibility of a partial claim for £675, by reference to a gloss put on an accompanying spreadsheet, would be to confuse the simple system of notification envisaged by the 1996 Act.
[33] That interpretation is reinforced by a consideration of the next statutory requirement, that in order to be payment notice, the notice has to set out the basis on which the sum claimed has been calculated interim payment claim 15 was for everything. There was therefore no explanation in the payment notice of the calculation of £1.4m as being the minimum due in respect of construction operations within the 1996 Act
[34] Because this was a hybrid contract, it was imperative that the claimant spell out the fact that, regardless of the position in relation to excluded operations, this was a payment notice (with all that that entailed) in respect of the claim for construction operations.
[36] In those circumstances it seems to me inequitable now to penalise the defendant for failing to respond within the limited time prescribed by the 1996 Act, in circumstances where the parties had been operating the contract in a different way, and when interim application 15 did not give any indication that it was a payment notice in respect of a specific part of the claim. If the claimant wanted to take advantage of the right that it has under the 1996 Act, then it had to do so in an open way. The least that the claimant could have done was to spell out in the December 2014 notice how the claim was split and why it was that in respect of the claim for construction operations, a very truncated timetable applied."
Estoppel by convention
Proof of sums claimed
Reliance on negative valuation
Suitability of Part 8 proceedings
Conclusion
i) on a proper construction of the Subcontract and the Act, MW issued a valid payment notice in response to CSL's application no.32;
ii) CSL is not estopped from relying on its construction argument;
iii) if, contrary to the finding in (i), MW failed to issue a valid payment notice, CSL would be entitled to rely on its payment application as the notified sum for the purposes of the Act;
iv) MW would not be entitled to rely on its negative valuation as a pay less notice, cross-claim or set off;
v) this claim was suitable for determination by Part 8 proceedings.