QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
ABB AB HVDC |
Claimant |
|
- and - |
||
MCLAREN CONSTRUCTION (MIDLANDS AND NORTH) LTD |
Defendant |
____________________
Jonathan Selby QC (instructed by Pinsent Masons) for the Defendant
Hearing dates: 15th May 2019
____________________
Crown Copyright ©
Mr Justice Stuart-Smith:
i) If ABB's reliance on Clause 18.1 was well founded, Clause 18.5 required McLaren to assign all of its agreements with its sub-suppliers, which would include McLaren's sub-contracts with its sub-contractors;
ii) In any event, Clause 18.9 (18.10 in the conformed version) provided that, on termination of the Contract, McLaren "shall immediately deliver to [ABB] all specifications, programs and other information, data and [McLaren] documentation regarding the Works which exist in any form whatsoever at the date of such termination, whether or not then complete". On its face this provision survived termination for whatever reason and is at least arguably broad enough to include McLaren's sub-contracts with its sub-contractors, though this is not accepted by McLaren.
i) McLaren did not assign the sub-contracts until after ABB had issued these proceedings with its application for interim relief;
ii) In correspondence McLaren adopted the position that it was not obliged to assist ABB by the provision of assignments or documentation. Whether because of confusion on its part or for some other reason, McLaren appeared to offer to novate subcontract agreements, which is materially different because it would require all McLaren's pre-novation obligations and liabilities to be assumed by or imposed on ABB.
i) About 50% of the agreements, as provided, were unsigned and others had only one signature; and
ii) It was immediately apparent that not all sub-contractors were covered by the disclosure.
i) Compelling McLaren to provide the final signed and executed versions of all of its sub-contracts for the project and, in the case of any sub-contracts that were not signed, an assurance that those sub-contracts were in fact agreed in the form already provided to ABB; and
ii) Compelling McLaren to inform all its sub-contractors that ABB and not McLaren now had the right to require performance of their sub-contract works.
i) McLaren provided 31 new or replacement agreements;
ii) Of those 31, 8 were in respect of sub-contractors for whom no agreements had previously been provided and who had not been included on McLaren's previous lists of sub-contractors. Accordingly, these sub-contracts could not be and had not been included in McLaren's statement on 10 May that it would assign its subcontracts or the assignments that took place on 11 May 2019;
iii) The visit to site enabled McLaren to retrieve 26 signed documents and;
iv) It emerged that one sub-contractor's agreement (HIL) incorporated a term requiring HIL's consent to any assignment, which had not previously been sought by McLaren.