QUEEN'S BENCH DIVISION
BUSINESS AND PROPERTY COURTS IN MANCHESTER
TECHNOLOGY AND CONSTRUCTION COURT
1 Bridge Street West Manchester M60 9DJ |
||
B e f o r e :
____________________
WILLIAMS TARR CONSTRUCTION LIMITED |
Claimant |
|
- and - |
||
1) ANTHONY ROYLANCE LIMITED 2) ANTHONY ROYLANCE |
Defendants |
____________________
Mr. Crispin Winser (instructed by Watson Burton LLP) for the Defendants
Hearing dates: 25th, 26th, 27th, 28th 29th June 2018
____________________
Crown Copyright ©
HH Judge Eyre QC:
Introduction.
The Factual Background.
The Competing Contentions in Outline.
The Approach to be taken in assessing the Evidence.
The Extent and Nature of the Defendants' Involvement in the Design of the Retaining Wall.
i) On 27th July 2010 Mr. Palgrave of Peak Associates (environmental consultants who had carried out ground investigations at the Site) said "I was also under the impression that Hy-Ten are the designers of the wall and are putting their PI against the design".
ii) In August 2010 Mr. Dawkin was in correspondence with Peter Warburton about professional indemnity insurance and said almost as an aside "but Hy-Ten have their PI cover in regards to the wall if this helps". On 16th July 2010 Mr. Dawkin had e-mailed the Claimant's Peter Aldred to say that he was going with Bill Quinn of CSS to meet with Hy-Ten. This was after the approach to Macaferri Ltd had been unsuccessful. Mr. Dawkin said "they [Hy-Ten] have a better product, they are designing the wall now".
i) First, Hy-Ten produced calculations and an initial drawing with the latter coming on 21st July 2010. The Second Defendant referred these to Mr. Palgrave for comment and forwarded those comments to Hy-Ten. Mr. Lisle confirmed that those comments had been forwarded to Hy-Ten's engineer. On 27th July 2010 Mr. Chandul sent revised calculations to Mr. Palgrave and to the Second Defendant saying that the revisions had taken account of discussions with Mr. Palgrave and of comments made in e-mails from the Second Defendant. There was then a similar exercise with the Second Defendant raising further queries with Hy-Ten in relation to the revised calculations. This elicited a response on 29th July 2010 in which Hy-Ten said that the revised calculations had been "generated by a dedicated software used for designing retaining wall (sic)" and that account had been taken of the points raised by the Second Defendant and by Mr. Palgrave. In my judgement these exchanges show Hy-Ten producing a design and then revising that design in response to comments. They also show Hy-Ten explaining that they were using software expressly created to design retaining walls.
ii) Next, Hy-Ten made a site visit on 15th September 2010. The next day Mr. Lisle sent an e-mail to Mr. Hazeleden of the Claimant and to Mr. Dawkin but not to the Second Defendant. The e-mail is headed "Gabion installation at Albany Mill Congleton". It refers to the site visit and Hy-Ten's "inspection of the gabion installation". It proceeds to say:
"we can confirm that installation thus far was to a good standard and was in accordance with our assembly guidance. It is important that as the build continues that the batter on the face is maintained as per our design and that the horizontal joints are laced with continuous lacing also any temporary ties should be removed."
In my judgement this e-mail is significant. That fact that it was sent to the Claimant and to Mr. Dawkin but not to the Second Defendant is noteworthy as an indication of the persons to whom Hy-Ten regarded itself as being responsible. Moreover, it demonstrates that Hy-Ten was addressing the system as a whole and not confining its concerns to the contents or design of the gabions albeit the main focus of its attention was on the gabions.
The Party engaged by the Claimant.
"ANTHONY ROYLANCE
Eur.Ing, A.Roylance, C Eng MICE
Chartered Civil Engineer"
i) The repeated use of the plural in the documents coming from the Second Defendant. Thus the letterhead referred to "Chartered Civil Engineers & Construction Consultants". The report of 9th November 2010 begins "we were appointed as civil engineering consultants for the above project …" and the report repeatedly uses "we" to refer to the work done by the Second Defendant. Similarly, the e-mail of 19th October 2010 from the Second Defendant to Mr. Parker sets out "our findings" and recites the opinion "we" have and the recommendation "we" make. However, this usage is not consistent throughout the correspondence and it is of note that the fee proposal of 18th November 2010 is said to contain "my breakdown of additional costs".
ii) The descriptions of attendees given in the minutes of the Progress Meetings repeatedly (although not invariably) describe the Second Defendant as "Anthony Roylance (AR) – Anthony Roylance Structural (ARS)".
iii) Mr. Winser placed considerable emphasis on the fact that on 14th March 2011 Peter Warburton of the Claimant sent the Second Defendant and other contractors a collateral warranty for completion. The warranty in respect of the civil engineering work described the covenantor as "Anthony Roylance company number 05477424 [the First Defendant's correct registration number] whose registered office is at 5 Old Street, Ashton under Lyne … [being the correct address of the registered office]". Mr. Winser said that this was a powerful indication that the Claimant knew it was dealing with a limited company. The point has some force although the document goes on to say "The covenantor carries on business as a firm of Chartered Civil Engineers and Construction Consultants" so there is a degree of ambiguity as to the corporate status of the covenantor. The document does demonstrate that at March 2011 the Claimant was aware of the First Defendant. There is no evidence of when the Claimant first acquired that knowledge and in particular no indication that it knew of the First Defendant's existence at the time of the engagement in November 2010. On 16th February 2011 the Claimant wrote to "Anthony Roylance" but the letter was addressed to the First Defendant's registered office and began "Dear Sirs". However, the Collateral Warranties Execution Progress Schedule attached to Mr. Warburton's e-mail of 25th January 2011 had referred simply to "Anthony Roylance" and had given the business address rather than the registered office of the First Defendant.
iv) Mr. Winser also made reference to the Drawing Issue and Register disclosed by the Defendants. This bore the heading "Anthony Roylance Chartered Civil Engineers" but at the foot of the page there appear the following words "File: Anthony Roylane (sic) Ltd". In my judgement this internal document does not advance matters materially and it has to be seen in the light of the drawings issued by the Second Defendant which bore the legend "Anthony Roylance Chartered Civil Engineer".
The Scope of the November 2010 Engagement and the Obligations arising from it.
"By a contract made partly orally and partly in writing, and to the extent in writing contained in email messages passing between the Claimant and First Defendant commencing in November 2010, the First Defendant in the course of its business agreed to carry out some of the structural engineering design works directly for the Claimant ("Contract"). As part of those works it carried out a redesign of the Gabion Retaining Wall it had previously commenced designing for Renew. It did so because the original design it had produced was not suitable for the actual site conditions. Its contract with the Claimant was to amend the design of the wall and associated features including drainage to produce a functioning retaining wall that was fit for purpose for the site."
Was there a Breach of the Second Defendant's Obligations?
Quantum.