QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Rolls Building, Fetter Lane, London, EC4a1NL |
||
B e f o r e :
____________________
(1) The Governors and Company of the Bank of Ireland (2) Bank of Ireland (UK) PLC |
Claimants |
|
- and - |
||
Watts Group PLC |
Defendant |
____________________
Ms Jessica Stephens (instructed by RPC) for the Defendant
Hearing date: 3 October 2017
____________________
Crown Copyright ©
The Hon. Mr Justice Coulson :
1. INTRODUCTION
(a) The Bank's claim failed for a variety of reasons. I found that the allegations of negligence had not been made out but that, even if they had been, it was difficult to say that they had caused any loss to the Bank. Separately, I found that the cause of the Bank's loss was its own decision to lend the money to the developer in the first place, and the failure of its employees to adhere to its lending rules.
(b) I was particularly critical of Mr Vosser, the expert quantity surveyor who gave evidence on behalf of the Bank. My grave concerns about his evidence were summarised at paragraphs 58-70 of the original Judgment.
(c) Before the trial, Watts made three offers to the Bank. The first was a Part 36 offer in the sum of £75,000, made on 2 October 2015. The second was in the sum of £150,000, made on 1 August 2016, also in accordance with Part 36. The third offer, dated 6 March 2017, was inclusive of costs and was for just under £545,000.
2. ASSESSMENT ON AN INDEMNITY OR A STANDARD BASIS?
"16. …
(a) Indemnity costs are appropriate only where the conduct of a paying party is unreasonable "to a high degree. 'Unreasonable' in this context does not mean merely wrong or misguided in hindsight": see Simon Brown LJ (as he then was) in Kiam v MGN Ltd [2002] 1 WLR 2810.
(b) The court must therefore decide whether there is something in the conduct of the action, or the circumstances of the case in general, which takes it out of the norm in a way which justifies an order for indemnity costs: see Waller LJ in Excelsior Commercial and Industrial Holdings Ltd v Salisbury Hammer Aspden and Johnson [2002] EWCA (Civ) 879.
(c) The pursuit of a weak claim will not usually, on its own, justify an order for indemnity costs, provided that the claim was at least arguable. But the pursuit of a hopeless claim (or a claim which the party pursuing it should have realised was hopeless) may well lead to such an order: see, for example, Wates Construction Ltd v HGP Greentree Alchurch Evans Ltd [2006] BLR 45.
(d) If a claimant casts its claim disproportionately wide, and requires the defendant to meet such a claim, there was no injustice in denying the claimant the benefit of an assessment on a proportionate basis given that, in such circumstances, the claimant had forfeited its rights to the benefit of the doubt on reasonableness: see Digicel (St Lucia) Ltd v Cable and Wireless PLC [2010] EWHC 888 (Ch).
17. These principles have recently been restated in the judgment of Gloster J (as she then was) in Euroption Strategic Fund Ltd v Skandinaviska Enskilda Banken AB [2012] EWHC 749 (Comm)."
3. REDUCTIONS OR ALLOWANCE IN FAVOUR OF THE BANK
4. THE INTERIM PAYMENT ON ACCOUNT OF COSTS
"3.18. Assessing costs on the standard basis where a costs management order has been made
In any case where a costs management order has been made, when assessing costs on the standard basis, the court will—
(a) have regard to the receiving party's last approved or agreed budgeted costs for each phase of the proceedings;
(b) not depart from such approved or agreed budgeted costs unless satisfied that there is good reason to do so; and
(c) take into account any comments made pursuant to rule 3.15(4) or paragraph 7.4 of Practice Direction 3E and recorded on the face of the order."
"Such a conclusion also accords with authority (albeit none binding on this court): not only in the form of the decisions in Merrix and Collins but also in the form of the remarks of Coulson J in McInnes v Gross [2017] EWHC 127 (QB). In that case, in the context of considering an interim payment on account of costs, Coulson J in terms said, at paragraph 25, that the significance of CPR 3.18 "cannot be understated" and meant that, where costs are assessed, the costs judge "will start with the figure in the approved costs budget." He roundly rejected the argument of the paying party that detailed assessment "will start from scratch." I agree with those observations of Coulson J."
"…this would provide the benefits of both consistency and certainty. There is a concern that, if an order for indemnity costs allows a receiving party to ignore the costs management order, then that will encourage successful parties to argue for indemnity costs every time. That would be unfortunate, and would leave an unacceptable doubt hanging over even approved costs budgets, all the way through to judgment and beyond. A paying party will have fought the trial assuming that, even if it loses, its opponent will be unlikely to recover more than the amount recorded in the costs management order, unless there is good reason for any departure. That is the certainty that the new regime provides. Even if the paying party has to pay costs on an indemnity basis, that does not seem to me automatically to justify an abandonment of that certainty, and the encouragement of a costs free-for-all."