QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
Dawnus Construction Holdings Limited |
Claimant |
|
- and - |
||
Marsh Life Limited |
Defendant |
____________________
Michael Curtis QC (instructed by Silver Shemmings LLP) for the Defendant
Hearing date: 4th May 2017
____________________
Crown Copyright ©
His Honour Judge McKenna:
Introduction
Factual background
"This we believe to be a slip. At no time did Marsh Life argue that Dawnus was not entitled to an extension of time. As in the Referral, within its Reply Marsh Life maintained that Dawnus was entitled to an extension of time for the SSE Delay Event, and that this was a relevant event being the carrying out by a Statutory Undertaker of Work Pursuance of its Statutory Obligations in relation to the Works. Marsh life argued, however, that there was no relevant matter entitling the recovery of loss and expense for such an event. Further, it was Dawnus who argued that the event was not a delay associated with the carrying out by a Statutory Undertaker of Work Pursuance of its Statutory Obligations in relation to the Works no doubt recognising that such event was not a relevant matter."
Similar comments apply to Delay Event 3 Winter Working Effect in that Marsh Life maintained that this was a relevant event being the carrying out by a Statutory Undertaker of Work Pursuance of its Statutory Obligations in relation to the Works.
In that you decided in favour of Marsh Life at paragraph 96.7 and that both the Delay Event 2 and Delay Event 3 were the carrying out by a Statutory Undertaker of Work Pursuance of its Statutory Obligations in relation to the Works we believe you have made slips in including sums for loss and expense in the Scott schedule whereas you had intended to include nil monies against both.
Further you have allowed for the recovery of O/H and Profit for such period whereas again we believe you intended to include nil monies for such periods.
We, therefore, ask that you correct these slips."
Approbation/Reprobation
"What the defendant could not do was to assert that the decision was a decision for the purposes of being the subject of a reference to arbitration but was not a decision for the purposes of being binding and enforceable pending any revision by the arbitrator…once the defendant elected to treat the decision as one being capable of being referred to arbitration, he was bound also to treat it as a decision which was binding and enforceable unless revised by the arbitrator."
"26. Although it is not strictly necessary to do so in the light of the conclusions which I have already expressed, I should like to comment on the alternative case put forward by Mr. Constable, that even if Mr. Haller had exceeded his jurisdiction in making the Award, any right which there would otherwise have been to raise objection on behalf of Automajor had been waived by making part payment of the sum awarded by Mr Haller and/or by inviting him to correct the Award…"
29. In my judgment it cannot be right that it is open to a party to an adjudication simultaneously to approbate and to reprobate a decision of the adjudicator. Assuming that good grounds exist on which a decision may be subject to objection, either the whole of the relevant decision must be accepted or the whole of it must be contested. It may, of course, be important correctly to characterise what constitutes a decision of the adjudicator. It is likely that, to be relevant for the purposes now under consideration, a decision will be the answer to a question referred to the adjudicator, rather than a conclusion reached on the way to providing such an answer…
30. In the present case Mr. Haller's error, if such it was, was committed in the cause of reaching a conclusion as to how much was due to Shimizu. It was not a decision on a separate question which had been referred to him. In my judgment by inviting Mr. Haller to correct the award under the slip rule Berwins on behalf of Automajor accepted that the award was valid. It is true that in its letter to Mr. Haller dated 6 November 2001 Berwins asserted that the Award contained an error which went to Mr. Haller's jurisdiction, but, if that were right, it would follow that the Award, or the relevant part of it, was a nullity. There will be nothing to correct. I accept the submission of Mr Constable that the invitation to Mr. Haller to correct the Award under the slip rule is only consistent with recognising it as valid. I also accept the submission of Mr. Constable that by paying part of the sum the subject to the Award Automajor elected to treat the Award as valid. Otherwise there was no need to pay Shimizu anything, and it was not appropriate to do so. Consequently, had it been necessary to do so, I should have held that Automajor had elected to forego any opportunity which it might otherwise have had to object to the Award."
The relevant principles
"The starting point, of course, is that, if the adjudicator has decided the issue that was referred to him, and he has broadly acted in accordance with the rules of natural justice, his decision will be enforced: see Macob Civil Engineering Limited v Morrison Construction Limited [1999] BLR 93. Adjudication decisions have been upheld on that basis, even where the adjudicator has been shown to have made an error: see Bouyques (UK) Limited v Dahl-Jensen (UK) Limited [2000] BLR 522. Chadwick LJ summarised the principal reason for this in Carillion Construction Limited v Devonport Royal Dockyard Limited [2006] BLR 15: "the need to have the 'right' answer has been subordinated to the need to have an answer quickly.""
"Finally, it is appropriate to stand back and to consider the ramifications of all this. The adjudicator's decision ran to 73 closely-typed paragraphs. It was the product of an adjudication which lasted from 11 October to 15 November 2016. I have only seen some of the documents relating to the adjudication but they fill more than one file. It cannot be right, absent any consent from the claimant, to let the defendant shoehorn into the time available at the enforcement hearing the entirety of that adjudication dispute. Such an approach would mean that, instead of being the 'de facto' dispute resolution regime in the construction industry, adjudication would simply become the first part of a two-stage process, with everything coming back to the court for review prior to enforcement. That is completely the opposite of the principles outlined in Macob, Bouyques and Carillion and cannot be permitted."
"From this and other cases, I conclude as follows in relation to breaches of natural justice in adjudication cases:a) It must first be established that the adjudicator failed to apply the rules of natural justice;b) Any breach of the rules must be more than peripheral; they must be material breaches;c) Breaches of the rules will be material in cases where the adjudicator has failed to bring the attention of the parties a point or issue which they ought to have given the opportunity to comment upon which it is one which is either decisive or of considerable potential importance to the outcome of the resolution of the dispute and is not peripheral or irrelevant.d) Whether the issue is decisive or of considerable potential importance or is peripheral or irrelevant obviously involves the question of degree which must be assessed by any judge in any case such as this.e) It is only if the adjudicator goes off on a frolic of his own, that is wishing to decide a case upon a factual or legal basis which has not been argued or put forward by either side, without giving the parties an opportunity to comment on or, where relevant put in further evidence, that the type of breach of the rules of natural justice with which the case of Balfour Beatty Construction Company Ltd v The Camden Borough of Lambeth was concerned comes into play. It follows that, if neither party has argued a particular point and the other party does not come back on the point, there is no breach of the rules of natural justice in relation thereto."
The challenge
The Decision
"For the same reasons as I decided the extension of time I decide that the Claimant have an entitlement to loss and expense."
Delay Event 2 SSE Cable Resequencing"96.1 The parties appear to have agreed that this caused a 15 week delay to the Works.96.2 However, in the Reply Marsh Life raised an argument that the event did not entitle Dawnus to any extension of time or loss and expense because SSE are not strictly statutory undertakers.
96.3 Before considering the argument, it is worth noting that even on Marsh Life's version of facts. A cable belonging to SSE was discovered to have encroached onto the site unbeknown to either party or SSE. The cable was actually located where excavation and piling was to occur. Marsh Life admit that this fact delayed the project by 15 weeks and caused delay and disruption. If Dawnus had not resequenced the Works to split the site to proceed on the part of the site that would not thereby be affected by the cables, the delay would have been 35 weeks. The facts are set out in a document dated 14 April 2016 by Mr Rowe to Marsh Life.
96.4 On that basis, an extension of time was agreed of 15 weeks and loss and expense applied for.
96.5 However, in the Reply in this adjudication Marsh Life seek to argue that SSE are not statutory undertakers and so as Dawnus cited work by Statutory Undertakers as the grounds for their entitlement no such entitlement arises.
96.6 Dawnus point out that Marsh Life accepted the delay was their responsibility and if this delay was not caused by Statutory Undertakers then the discovery of a cable preventing Dawnus from working as SSE banned them from working within three metres of the cable under statutory powers as an Electricity distributor under the Electricity Act 1989.
96.7 I reject Marsh Life's argument. SSE are an Electricity Distributor under the Electricity Act 1989 and as such are a Statutory Undertaker for the purposes of the Contract. If I am wrong about this I would have decided that Dawnus were entitled as the Employer had imposed obligations in relation to the specific order the Works had carried out per Clause 4.21.1 and 4.21.4.
96.8 Marsh Life agreed the extension of time and cannot now deny the extension. As such I decide that Dawnus are entitled to 15 weeks extension of time."
Discussion
"Dawnus claim loss and expense for the delays. Marsh Life do not dispute the entitlement but do dispute the proof of loss."
Disposal