QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
The Rolls Building, Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
(sitting as a Deputy High Court Judge)
____________________
PETER BURGESS LYNN BURGESS |
Claimants |
|
- and – |
||
BASIA LEJONVARN |
Defendant |
____________________
Louis Flannery and David Sheard
(respectively of and instructed by Stephenson Harwood LLP) for the Defendant
Hearing dates: 17, 18, 19 November 2015
____________________
Crown Copyright ©
MR ALEXANDER NISSEN QC:
Introduction
General Background
The Preliminary Issues
(i) Was a contract concluded between the Claimants and the Defendant, as pleaded in paragraphs 21 to 23 of the Particulars of Claim or otherwise?(ii) If so, what were its terms?
(iii) On the assumption that the defects set out in Schedule 1 to the Particulars of Claim existed as at 9 July 2013, did the Defendant owe any duty of care in tort in light of the matters, and in the terms, pleaded in paragraphs 18 to 20 of the Particulars of Claim, or otherwise?
(iv) If so, what was the nature and extent of her duty?
(v) Was a budget of £130,000 for the Garden Project discussed between the Defendant and either or both of the Claimants as pleaded in paragraphs 10(1)(e), 11, 16(3), 21(2)-(3) and 29(3)(a)(b) of the Defence at any time before 5 July 2013, and if so, when?
Particulars of Claim
"D. The Garden Project: The Defendant's duty in tort
18. The Defendant well knew that the Claimants would rely on her professional skill and experience in carrying out the tasks set out in paragraphs 14 and 15 above. In particular, the Defendant well knew:
18.1. in light of the matters set out in paragraph 5, that the Claimants were relying on her to exercise the professional skills of an architect and project manager; in particular those that she had held herself out as having, and had in fact performed, in relation to the Bank Project, the earlier refurbishment of the Property, and the Office Project;
18.2. in light of the matters pleaded in paragraphs 9 to 11, that, had the Defendant been incapable of performing those tasks (namely, those set out in paragraphs 14 and 15 above) competently, so as to procure completion of the Garden Project at the Cost (allowing a reasonable margin for necessary changes in design, and events impacting on construction that were, in each case, unforeseen and unforeseeable), that the Claimants would instead have engaged Mark Enright;
18.3. that the Claimants were not intending to seek professional advice or assistance from any other person in relation to the performance of those tasks; and
18.4. that, if she were to perform those tasks without reasonable care and skill, it was a foreseeable consequence that the Claimants would suffer loss, expense and inconvenience.
19. The Defendant assumed responsibility for the tasks set out in paragraphs 14 and 15 above and thereby came under a duty of care to the Claimants to perform those tasks, and to give such advice, with due skill and care. In particular, the Defendant owed a duty to the Claimants, as architect and/or project manager on the Garden Project, to exercise reasonable care and skill in architectural design, budgeting, procurement, project management and supervision, and cost control, so as to complete the Garden Project at the Cost (allowing a reasonable margin as set out in paragraph 18.2).
20. Further or alternatively, the duty of care arose by reason of (a) the foreseeability of damage to the Claimants in the event of those tasks being performed, or that advice being given, negligently; and (b) the close proximity between the parties.
E. The Garden Project: The Defendant's contractual duty
21. The conduct and exchanges of the parties set out above in paragraphs 9 to 13 above, gave rise to a contract between the Claimants and the Defendant ("the Contract"). The Contract came into being on or around 15 May 2013, alternatively 28 April 2013, as a result of the matters pleaded in paragraphs 13 and 12 respectively.
22. By that Contract the Defendant agreed, in consideration of remuneration that she would draw out of the Cost (whether in the first phase or subsequent phases of the Garden Project), alternatively of the financial benefit that the Defendant would receive from her engagement on the Office Project:
22.1. to act as architect and/or project manager on the Garden Project, and to perform the services set out in paragraph 14 above; and
22.2. to procure the design and construction of the Enright Design at the Cost (allowing a reasonable margin as set out in paragraph 18.2).
23. It was an implied term of the Contract that the Defendant would exercise reasonable care and skill in the performance of those services, that term to be implied: by section 13 of the Supply of Goods and Services Act, because the Defendant was acting in the course of her business as Linia Studio; alternatively, because it was obvious, or necessary to give business efficacy to the contract."
Defence
Paragraph 10(1)(e)
"Thereafter, on 28th April 2013 the Defendant met with the First Claimant at the Property to discuss the likely budget for completing a garden in line with the Enright plan in circumstances in which the 2nd phase decorative features and finishes were yet to be designed. The First Claimant was unwilling to incur the costs of a complete design at that stage. At the meeting, it was discussed that an overall budget in the region of £130,000 should be set aside, as was itemised in the Defendant's handwritten notes for the meeting, which are appended hereto as Appendix 1."
Paragraph 16(3)
"Whilst it is admitted that the Defendant told the Second Claimant that the overall budget for the garden was £130,000, it is denied that this was raised for the first time at this meeting. Subparagraph 10(1)(e) above is repeated."
Paragraph 21(2)(3)
"(2) Whilst following the Defendant's meeting with the Second Claimant on 5th July 2013 the First Claimant purported to be surprised by the £130,000 budget figure that the Defendant had mentioned to the Second Claimant, and purported to maintain that this represented an escalation in cost when compared against Hardcore's cost estimate, in fact this figure had already been clearly set out and discussed at the 28th April 2013 meeting as a likely overall budget for the project as a whole. The figure of £130,000 was also discussed at the meeting on 17th May 2013 between the Claimants, the Defendant and Mr Kodyl of Hardcore. Paragraph 10(1)(e) is repeated. For unknown reasons, the First Claimant appeared to assume that the sum that he was going to have to pay for groundworks only had increased to £130,000, which was not the case.
(3) Whilst the completed project would not and was never going to cost £78,500, it is denied if the same be alleged that, as at 9th July 2013, the project could not have been completed within or close to an overall budget of £130,000."
Paragraph 29(3)(a)(b)
"(a) Paragraphs 10 and 21(2) and (3) above are repeated. The First Claimant chose to proceed with the project on the basis of a likely budgeted cost of £130,000. It is denied, if the same be alleged, that the Defendant assumed any responsibility towards the Claimants in suggesting this budget, or that the same was negligent.
(b) If, which is denied, the Defendant ought to have informed the Claimants that the Garden Project would cost in excess of £130,000, no admissions are made as to what the Claimants would have done had they been so informed."
The Witnesses
Expert Evidence
The Facts
Friendly Relationships
Mrs Lejonvarn's Qualifications and Experience
"Overview: Past: Project Architect/Manager at Richard Mitzman Architects. Senior Architect at PAPA Architects."
"Lynn certainly felt that a Canadian architect would be as good as a British one (she being Canadian herself), so this was not an issue for us."
Other Projects
The Bank Project
"Normally our fees are divided into 3 stages and reflect the 3 stages of work that traditionally comprise a full architectural service…However, this project is small enough not to warrant a main contractor and therefore merits a slightly different fee structure. Instead of tendering out to a main contractor, we would be hired to project manage the works ourselves. We would hire the subcontractors, manage them and be involved on a day to day basis on site. This would guarantee you that the works would be carried out to our specifications ensuring a higher quality than what you would get from a main contractor. This is far more than what we would normally do using a standard form of contract. When you enter into a contract with a main contractor the assumption is that he project manages it himself with us as the administrator of the contract. With us acting as project managers you get a much higher quality job and a project manager who acts in your interest. Our fee structure for the project management stage of the job is 15% of the overall building cost. (of which we don't know the cost of yet, but probably around £100,000)"
"Originally we thought we would cut the cheques to the builder every Friday after receiving their weekly invoice. However, because we are technically your builders (and the builders, in effect, our subcontractors) it makes us liable for their tax if they don't pay etc etc. If we filter their invoices and you cut them the cheques, then they remain as simply your builders without any tax implications to you. Adam will give us an invoice Friday morning and we will scrutinize it, approve it and then pass the invoice to Rak (your accounting person yes?). If he could then write out a cheque the same day, then they will have their money…"
"We have been really cranking things on your project. I go at least twice a day and the boys are moving quickly. I am working on designing and drawing up everything with hopes to have it in building control in 2 weeks….Am pleased with their progress."
"I have also gone over the bills to date in order to keep close watch on costs. I have prepared a spread sheet and itemized it so we can see where we are. I have attached it here. It is good to keep it all under close scrutiny now that we have so many quotes coming in…"
"I am attaching an updated spread sheet for the project estimate…We have two more months of labour costs which we anticipate to be around £18,000. Included in this labour cost will be some of the items listed in the project estimate…We have therefore gone slightly over our budget but not more than £5,000 to £10,000. It is always good to account for a contingency."
"The reason for speaking to Socrates is not "to go over your head". We consider you to be a good friend as well as a talented architect. But I do have issues with your employer and I do not want to spoil our relationship by arguing these points with you. I feel it would be much better to deal with contentious issues with Socrates or someone else at Papa. I really do admire your work."
"I do however stand by the work we have done and after working in this profession for many years I know that we have given you not only very good design and project management service not least because I consider you a friend and gave you much more care and attention."
"However, on the subject of cost you feel that PAPA is responsible for costs exceeding your initial budget. That discussion I feel you should indeed take up with Socrates as I am not responsible for fees. I am however always working with a budget estimate and I feel I did everything I could do to control those cost (sic) in my control."
The Kitchen Project
"Peter, I have been thinking about that kitchen quote. If you feel uncertain about it, please speak to me again about it because as your architect, I feel I should tell you that I can get you the same kitchen for much less."
"As you know we are a design practice and as such the work we do is first and foremost design. The labour we employ work only from our designs and thus are not building contractors of the regular sort. This is why we have such a long standing history with them. We are, in effect, a team. Adam and his guys are really Interior Fit Out Specialists and they work to our designs exclusively. So I am afraid we are unable to simply act as contractors in this instance. …I hope that we can have other opportunities to be your architects and designers but I completely understand that for Highfields it is not appropriate."
The Little Venice Office Project
"I will prepare what I believe to be your brief, and then you can let me know if you agree, and then you can give me a budget that we can agree on."
"Peter, leave the builders to me! Although Small Restorations aren't even builders! I use Small Restorations for simple windows and I don't think that they would be capable of doing anything without having their hand held! And I mean held!!!"
"You have me! Don't go near them! The thing is that they need to be given drawings, specifications, constant supervision you see! They don't think on their own!"
Archway Road
"I have the drawings for the First Floor Flat printed and I wanted to ask you if you would like me to schedule in some design and procurement time in order to get the refurbishments going. I don't want the boys on site and not have materials ordered as it would not be an efficient method of working. I thought I would present to you the new bathroom layouts, some fitting suggestions, samples of materials etc. Then I can go to my sources and start procurement once you are happy with the choices. What I do need however is a budget to work with."
Concluding Comments
The Garden Project – Primary Facts
"Also, do you think your guys could do our garden? I will send you the plans."
"I will have a look now. Please send me the design of the garden and definitely our guys will be great."
"I spoke with the boys and once you send the plans I can meet with them to go over the job so that they can price it."
"This would be for Peter Burgess. This is his house. It is all outside work, and I think you can do it without a doubt. The gardeners will do all the planting etc, but the main works are the terracing, stairs etc. A lot of it is already there. It is quite a complicated garden built on a steep slope, so you would have to incorporate some drainage but I have someone that can help with that. A nice job I think."
"All right, I let you know. It's a lot of work and you'll need to think it over. I think that you cannot give the total price until more design is specified. I also would like to speak with the drainage specialist. It is like it is more or less but it's true that you need to drain well."
"I met with Peter and Lynn yesterday regarding the works to the garden. It looks like they will have approval from their residents association shortly which means you could get started anytime. It is basically a lot of earth moving around and levelling. You will have to get a digger/earth mover. The design they like includes using railway ties and decking. We will need some replacement fencing and then we can call in Matt to do the planting. At the ground level next to the house, we would like to repave the terrace with porcelain tiles. The underground drainage needs to be rodded and checked and that will be a good opportunity to do that."
"We have done the leg work on what needs to be done in preparation for works and we can be ready very soon at minimum getting things lined up. Do you have a start date or thereabouts in mind…Ideally I would not want to be away the week they start, but actually, that week is a short week due to Easter Monday. Hardcore will prepare the first phase for costing which will relate to all the ground preparation, ground works, etc. to get the levelling done. I would also like to instruct a drains survey as quickly as possible. This is the opportune time to confirm that all the below ground drainage is sound and where exactly we can connect to etc, for additional drainage…I use 2 companies who are both very good and very reasonable."
"We can cost out the first phase of works to achieve the necessary levels. We have unit costs for the railway ties but we really need to have a more detailed design developed in order to cost out how many ties are needed. What can be achieved is a conservative estimate at the very least. In order to determine full costs for the steps and decking, I will generate areas and number of steps from Mark Enright's design but I would actually like to make my own drawings to develop the design to a realistic quantifiable level. In the meantime, the first phase of the works would include protection and site preparation, initial removal of existing decking…then the initial ground works to achieve the new levels. That can be priced up now….we need to cost up as much as is known of the works"
"By no means am I suggesting a re-design. Mark gave you a very good general concept and his design should work but he hasn't taken it to a level that is necessary both for costing and for building. He gave you a budget estimate but he didn't give you a breakdown of costs, and once you would have started costs might just have accumulated. I wouldn't be charging you to work through the initial costing anyway. The only design charges I anticipate are for the exact layout of the deck areas, the paving area (it has to be laid out even for ordering of the tiles) and any design features such as the screens to the hedge, the fencing above and how you want it to be. A drawing helps you visualise the final result and it helps work out how much of each item one needs to order. Effectively, you have a general design, but it is not something anyone (other than Mark Enright of course) can implement without working out some further details. For example the fencing, what type, ready made panels or not, will it need some support members etc. The railway ties all come in different sizes and we need to make sure we get ones that are adequate for the job and keep consistency throughout the garden. It is premature for some of these decisions, but those are the kinds of things I mean when I refer to design. I don't mean I want to re-design the general layout. Mark has done that and from there you can move forward, but it isn't quite ready for a meaningful pricing exercise. Remember that Mark Enright does this over and over again, so he will have a good idea of what he needs to charge. From my builder's perspective, they need to go through the job with a fine tooth comb in order to arrive at a price that is realistic."
"So you would prefer for me to get Hardcore to give you another budget estimate for the whole job just like Mark Enright did?...I am not suggesting a re-design, I am suggesting the next step of the initial concept design for the purposes of pricing. I see the project team as follows:
1. Labour: Hardcore (Przemek and Adam)
2. Project Management and detail design (to include layout and procurement of hard materials such as paving, decking, possibly balustrades and design features (possibly a water feature), consideration of technical aspects such as drainage and building of raised beds and or supports, fences, barriers and or other built items such as storage cupboard and all related finishes.) ME.
3. Lighting: Mark DAVIS
4. Trees: Richard Wassels
5. Planting and any pots or decorative features: Matt
6. Misc. items: underground drainage and irrigation.
My guys are prepared to do all of the "building work", the ground works, the raised beds and terraces, the deck areas and stairs, and storage and the paved areas at the ground level and they can have it all ready to receive planting."
"The best option for us, if we don't take price into account is to let Mark Enright do it since its his design and daftly the fact that he has done it has value. Of course I would love your guys to do it but I certainly don't want to be in a position where it costs even more than Mark Enright. I was thinking it would be substantially less expensive. I will need a fairly firm price."
"Ok so we get a firm price from them. I doubt their price would come even close to Mark's but the only way to find out is to test it. So that is how I will proceed. I will do what is necessary for them to price it out accurately and I will ask Matt to come and have a look at the garden so that he can get us a price too. I will work on finding the tiles so I can get a price for that too. Mark's design is good and you can always still say it is a Mark Enright designed garden as I am assuming you paid for his design so I don't see how you would lose that value by using Hardcore to carry it out. …Agreed for Hardcore to price out with my input?"
"…Also when you refer to piling: how do you know it will need to be piled and that implies we need to involve an engineer as the piling has to be designed. Again, if this is the case the price cannot be adequate until we have an engineer's design how can you price for it. So this item still needs work. I could speak to Martin Redston about this in order to get his take on it."
"Here is the Cost Estimate for the Ground works and first phase works to be carried out according to the design furnished by yourself. Hardcore have given you a price for the 1st phase of works and as such have itemised what this comprises of. The subsequent stages are only budget estimates. If you are happy to accept this first stage pricing (the subsequent prices listed are done so as budget prices but as discussed earlier, we will have to first decide what exactly you will want (ie what kind of decking etc) and then the price can be precise. At present the first stage of works have a final price as shown but once accepted, the full price breakdown will be sent to you. We are just coordinating a start date with the labour team and once you are ready, we can confirm."
"As far as the decking goes, your choices are less exciting but as long as you don't want the very expensive teak decking, you can still keep costs to the budget."
"Firstly, are we on budget. I can't remember how much we've paid so far but I think we must be half way through the quote and yet it doesn't look like they are anywhere near half way through. Also we do not have unlimited time with the fence being down. Has something gone wrong with the workforce?"
"I can only say that I have no reason to doubt the efficiency or effort of the guys at present. Given the nature of the work, they have actually made very good progress. The sheer volume of clay that needs to be removed from site in order to create the lawns is in of itself very time consuming. Especially as it is removed skip by skip. I am not concerned with the budget yet as we have a very close eye on where we are. The land works are the greatest proportion of the budget by far. Once Joe and his men leave, you are effectively left with light building work, decoration and gardening."
"As long as you are happy and we are not going to go massively over budget or timings, that's fine."
"All the lawn related stuff Peter will be done professionally and all rubbish will be removed with spoil. Any builder working with me and Hardcore as a subcontractor is held accountable and works to our standards or he doesn't get paid."
"I think there she may have got confused because she seems to think that the cost for the ground works is going to be £130k. I have been working on the premise that this would be 78k as per your quote attached. I know that this quote does not include planting, or the tiling of the patio area. Lynn says you want another £30k this week which is fine but can I assume this is the final payment for the earthworks? If you're about this weekend can we discuss. If Lynn has understood you correctly then it appears that you are more expensive than Mark Enright and we cannot have his plan anyway. I am sure that there are some lines crossed somewhere."
"We have made all efforts to keep to the 130 we agreed for doing the project (Linia Design Studio (myself) and Hardcore) and given the adjustments that had to be made which I have described above, we are very close. Have a look at the spreadsheet attached and if you want to discuss it in further detail just let me know. I have discussed with Joe an estimated 2 weeks to finish up this groundworks phase….I hope this will help reassure you that we haven't gone far from our agreed price which is a very positive given the site constraints at Highfields."
"So in fact you are saying that your cost will be more than Mark Enright and we cannot have half the features of that plan. Basia I think we need to stop work now and get Mark Enright in to do the work. This is a disaster. At no point did we agree £130k and Friday was the first time you mentioned this. If you had told me at the beginning that you would be charging more than Mark Enright and couldn't implement the plan I would clearly have not gone ahead. I am quite shocked by this. We need to meet to work out how to get out of this mess."
"I am shocked by your email. You and I agreed 130k at your house when you also told me Mark Enright had wanted 178k. You told me that not once but twice. I have written down as such and if you believed that the cost estimate of 78k is what you believe you should be paying then you are saying that you never had any intention to pay for my project management and development of Mark Enright's "design" which was hardly something anyone can build from. Are you saying you wanted it at cost and managed as a friendly favour on my part? Perhaps then it is I who has wholly misunderstood our Professional relationship….I am very upset by this."
"You are being very defensive and this isn't helping. Nor is it a good idea to have an email war. The central issue at the moment appears to be that you feel you had told me that the earth works and sleepers are now going to be £130k and in your quote you stated £57k. That is more than double and will bring your price to much higher than Mark Enright's. I accept that you genuinely believe that you did tell me this. However, I hope you will accept that I genuinely believe that you did not. One of us has this wrong….Mark Enright's quote of £178k included planting. The quote without planting was £155k. I will show you the quotes….We are not getting the job we asked for and we are having to pay much more for it…This is a disaster and I simply cannot afford to spend £200k on a garden. Add to that your guys are being paid in cash! ... As for your fee, I have never asked you for a friendly favour. I would have thought that your project management fee should have been included in the quote and I was assuming that this was included. …I am clearly not now expecting you to come in at the price quoted. But we do need absolute clarity going forward. Muddling through with me paying you shed loads of cash is not an option."
"I am sorry to say that you have not managed the costs of this project at all and you have not actually supervised the work."
"I think the truth is here that you were not qualified to take on a job such as this and have just muddled through hoping we wouldn't notice or wouldn't mind."
"Unfortunately you were working to a budget of £78,000 pounds based on a budget estimate early April well before you and I agreed the weekend of the 26th of April to a budget of £130,000. I did not put it in an email because you wanted to pay in cash and for that reason I wrote it down in my notes and have been working to that budget since that agreement and not via email for obvious reasons….It is my responsibility to work in the best interests of my clients and as such I make great efforts to make clients aware of any potential problems, issues or shortcomings that may affect the success of a project. I am not a Quantity Surveyor and as such I do not price jobs. I have also assembled an experienced team and offered to you their services which I have managed. I promised to work to a budget price that we agreed, and that is exactly what I have done. The budget was £130,000 and we have come in at 132,000 plus change….The work thus far is of a very high standard and the retaining walls are in place according to the design despite you thinking otherwise….Unfortunately I don't believe we will come to a mutually agreeable conclusion. I am sorry that this has ended our relationship but I cannot work under these circumstances."
"I don't want to leave you with an unfinished project so I will ask my contractors if they would be willing to continue with you directly. There are risks associated with this. Problems may arise on site that require someone to manage them with a knowledge of technical, logistical and design solutions You will be exposed and vulnerable to cost increases, or unacceptable results in terms of how it is finished off or detailed. The fact that you do not have any technical design drawings for the stairs leaves them open to the interpretation of the builders."
"You have also overstepped the professional boundaries. Moreover, you have overstepped the boundaries between friends."
The Preliminary Issues
Preliminary Issue (i)
"89 The applicable general principles were not in dispute. They are set out in Chapter 2 of Chitty on Contracts (31st edition) and conveniently summarised by Lord Clarke in RTS Flexible Systems Ltd v Molkerei Alois Müller GmbH & Co KG (UK Production) [2010] UKSC 14, [2010] 1WLR 753.
90 The test for determining whether a contract exists is objective. It depends not on the parties' actual intentions but on what those intentions would reasonably be understood to be from the parties' communications (by words or conduct) with each other.
91 An offer is "an expression of willingness to contract on specified terms made with the intention…that it is to become binding as soon as it is accepted by the person to whom it is addressed" – Chitty para. 2-083.
92 A bilateral contact is formed through an exchange of promises under which both parties undertake obligations – Chitty para. 1-099.
93 A unilateral contact is formed through the promise of a party to perform if the other party does (or forbears from doing) a particular act – Chitty para. 1-099; 2–078.
94 For an agreement to be legally binding it must be supported by consideration; be made with the intention to create legal relations; be sufficiently certain and complete, and comply with any requirements as to form.
95 As stated by Lord Clarke in the RTS case:
"The general principles are not in doubt. Whether there is a binding contract between the parties and, if so, upon what terms depends upon what they have agreed. It depends not upon their subjective state of mind, but upon a consideration of what was communicated between them by words or conduct, and whether that leads objectively to a conclusion that they intended to create legal relations and had agreed upon all the terms which they regarded or the law requires as essential for the formation of legally binding relations. Even if certain terms of economic or other significance to the parties have not been finalised, an objective appraisal of their words and conduct may lead to the conclusion that they did not intend agreement of such terms to be a precondition to a concluded and legally binding agreement."
"Agreement is not a mental state but an act and, as an act, is a matter of inference from conduct. The parties are to be judged, not by what is in their minds, but by what they have said or written or done."
"Where an offer or an acceptance or both are alleged to have been made by conduct, the terms of the agreement may be more difficult to ascertain than where the agreement was negotiated by express words. The difficulty may be so great as to force the court to conclude that no agreement was reached at all."
"Another factor relevant to the issue of contractual intention is the degree of precision with which the agreement is expressed…Vagueness may also be a ground for concluding that the parties had never reached agreement at all…While the issues of contractual intention and vagueness are conceptually distinct, they may overlap in borderline cases; the question whether an agreement exists will depend on the degree of vagueness or on whether the vagueness can be resolved, e.g. by applying the standards of reasonableness."
"The doctrine of consideration is based on the idea of reciprocity: that "something of value in the eye of the law" must be given for a promise in order to make it enforceable as a contract. It follows that an informal gratuitous promise does not amount to a contract."
"Consideration would again be illusory where it was alleged to consist of a promise the terms of which left performance entirely to the discretion of the promisor. A person does not provide consideration by promising to do something "if I feel like it" or "unless I change my mind"."
Preliminary Issue (ii)
Preliminary Issue (iii)
"Contractual and tortious duties have different origins and different functions. Contractual obligations spring from the consent of the parties and the common law principle that contracts should be enforced. Tortious duties are imposed by law, as a matter of policy, in specific situations."
"Contractual obligations are negotiated by the parties and then enforced by law because the performance of contracts is vital to the functioning of society. Tortious duties are imposed by law (without any need for agreement by the parties) because society demands certain standards of conduct."
The Law
"Both Lord Oliver in D&F Estates and Lords Bridge and Keith in Murphy drew attention to the possibility that economic loss would be recoverable by application of the decision of the House of Lords in Hedley Byrne v Heller & Partners. Although that decision is typically associated with the giving of information or advice, Lord Goff in Henderson made clear that it extends to a broad range of circumstances in which "special skill" is exercised."
"The case has always been regarded as important in that it established that, in certain circumstances, a duty of care may exist in respect of words as well as deeds, and further that liability may arise in negligence in respect of pure economic loss which is not parasitic upon physical damage. But, perhaps more important for the future development of the law, and certainly more relevant for the purposes of the present case, is the principle upon which the decision was founded. The governing principles are perhaps now perceived to be most clearly stated in the speeches of Lord Morris of Borth-y-Gest (with whom Lord Hodson agreed) and of Lord Devlin. Lord Morris said, at pp. 502-503:
"My Lords, I consider that it follows and that it should now be regarded as settled that if someone possessed of a special skill undertakes, quite irrespective of contract, to apply that skill for the assistance of another person who relies upon such skill, a duty of care will arise. The fact that the service is to be given by means of or by the instrumentality of words can make no difference. Furthermore, if in a sphere in which a person is so placed that others could reasonably rely upon his judgment or his skill or upon his ability to make careful inquiry, a person takes it upon himself to give information or advice to, or allows his information or advice to be passed on to, another person who, as he knows or should know, will place reliance upon it, then a duty of care will arise.""
"He then cited a number of authorities, and continued, at pp. 528-529:
"I think, therefore, that there is ample authority to justify your Lordships in saying now that the categories of special relationships which may give rise to a duty to take care in word as well as in deed are not limited to contractual relationships or to relationships of fiduciary duty, but include also relationships which in the words of Lord Shaw in Nocton v. Lord Ashburton [1914] AC 932, 972 are 'equivalent to contract,' that is, where there is an assumption of responsibility in circumstances in which, but for the absence of consideration, there would be a contract. Where there is an express undertaking, an express warranty as distinct from mere representation, there can be little difficulty. The difficulty arises in discerning those cases in which the undertaking is to be implied. In this respect the absence of consideration is not irrelevant. Payment for information or advice is very good evidence that it is being relied upon and that the informer or adviser knows that it is. Where there is no consideration, it will be necessary to exercise greater care in distinguishing between social and professional relationships and between those which are of a contractual character and those which are not. It may often be material to consider whether the adviser is acting purely out of good nature or whether he is getting his reward in some indirect form…."
"He said, at pp. 531-532:
"Since the essence of the matter in the present case and in others of the same type is the acceptance of responsibility, I should like to guard against the imposition of restrictive terms notwithstanding that the essential condition is fulfilled. If a defendant says to a plaintiff: 'Let me do this for you; do not waste your money in employing a professional, I will do it for nothing and you can rely on me;' I do not think he could escape liability simply because he belonged to no profession or calling, had no qualifications or special skill and did not hold himself out as having any. The relevance of these factors is to show the unlikelihood of a defendant in such circumstances assuming a legal responsibility, and as such they may often be decisive. But they are not theoretically conclusive and so cannot be the subject of definition. It would be unfortunate if they were. For it would mean that plaintiffs would seek to avoid the rigidity of the definition by bringing the action in contract as in De la Bere v. Pearson Ltd. [1908] 1 KB 280 and setting up something that would do for consideration. That, to my mind, would be an undesirable development in the law; and the best way of avoiding it is to settle the law so that the presence or absence of consideration makes no difference."
From these statements, and from their application in Hedley Byrne, we can derive some understanding of the breadth of the principle underlying the case. We can see that it rests upon a relationship between the parties, which may be general or specific to the particular transaction, and which may or may not be contractual in nature. All of their Lordships spoke in terms of one party having assumed or undertaken a responsibility towards the other. On this point, Lord Devlin spoke in particularly clear terms in both passages from his speech which I have quoted above. Further, Lord Morris spoke of that party being possessed of a "special skill" which he undertakes to "apply for the assistance of another who relies upon such skill." But the facts of Hedley Byrne itself, which was concerned with the liability of a banker to the recipient for negligence in the provision of a reference gratuitously supplied, show that the concept of a "special skill" must be understood broadly, certainly broadly enough to include special knowledge. Again, though Hedley Byrne was concerned with the provision of information and advice, the example given by Lord Devlin of the relationship between solicitor and client, and his and Lord Morris's statements of principle, show that the principle extends beyond the provision of information and advice to include the performance of other services. It follows, of course, that although, in the case of the provision of information and advice, reliance upon it by the other party will be necessary to establish a cause of action (because otherwise the negligence will have no causative effect), nevertheless there may be other circumstances in which there will be the necessary reliance to give rise to the application of the principle. In particular, as cases concerned with solicitor and client demonstrate, where the plaintiff entrusts the defendant with the conduct of his affairs, in general or in particular, he may be held to have relied on the defendant to exercise due skill and care in such conduct."
"I have already expressed the opinion that the fundamental importance of this case rests in the establishment of the principle upon which liability may arise in tortious negligence in respect of services (including advice) which are rendered for another, gratuitously or otherwise, but are negligently performed - viz., an assumption of responsibility coupled with reliance by the plaintiff which, in all the circumstances, makes it appropriate that a remedy in law should be available for such negligence. For immediate purposes, the relevance of the principle lies in the fact that, as a matter of logic, it is capable of application not only where the services are rendered gratuitously, but also where they are rendered under a contract."
"Just as in the case of fiduciary duties, the assumption of responsibility referred to is the defendant's assumption of responsibility for the task not the assumption of legal liability. Even in cases of ad hoc relationships, it is the undertaking to answer the question posed which creates the relationship. If the responsibility for the task is assumed by the defendant he thereby creates a special relationship between himself and the plaintiff in relation to which the law (not the defendant) attaches a duty to carry out carefully the task so assumed."
"I can draw all these eminent authorities together in the following summary in the context of this case: (a) There are in effect two types or manifestations of duties of care which may arise in relation to economic loss, firstly, out of a negligent misstatement or misrepresentation and, secondly, where there is a relationship akin to contract or the non-contractual provision of services. There is no simple formula or common denominator to determine whether a duty of care, in relation at least to economic loss cases, arises or not. (b) The Courts have traditionally observed some caution and conservatism in economic loss cases. Attempts to open the floodgates, such as in Anns v Merton LBC, have ultimately been rejected. An incremental approach is favoured. (c) It is always necessary to consider the circumstances and context, commercial, contractual and factual, including the contractual structure, in which the inter-relationship between the parties to and by whom tortious duties are said to be owed arises. Thus, it is not every careless misstatement which is actionable or gives rise to a duty of care. Foreseeability of loss is not enough. (d) It is necessary for the party seeking to establish a duty of care to establish that the duty relates to the kind of loss which it has suffered. One must determine the scope of any duty of care…. (f) In considering the second type of duty of care, it is material to consider whether the relationship between the parties is akin to contract or whether the party alleged to owe the duty was asked by the person to whom the duty is said to be owed to provide services to or for the benefit of that person. Reliance is important also in this type of negligence to link the damage suffered to the breach of duty. (g) Although the voluntary assumption of responsibility test is not mandatory, it is a useful guide in determining if a duty of care of either sort arises. It is an objective test. The threefold test (of reasonable foreseeability of the economic loss, proximity and fairness, justice and reasonableness) provides no simple answer where, in a new situation, a duty of care is said to arise. These tests are all helpful but are not always determinative."
"In the light of this decision, it is clear that a builder who does no more than build pursuant to a "normal" construction contract does not owe a duty to avoid causing economic loss to a person with whom it is in contract or any other person. A professional, such as an engineer, does owe a duty to avoid causing economic loss to a person with whom he is in contract and may owe such a duty to others to whom he has assumed responsibility for such loss."
"The question "what does the concurrent duty of care in tort require?" begs the response "duty of care in doing what?"
Discussion
Preliminary Issue (iv)
Preliminary Issue (v)
Summary and Conclusions
(i) No.(ii) Not applicable.
(iii) Yes. Mrs Lejonvarn owed a duty of care to Mr and Mrs Burgess to exercise reasonable skill and care in the provision by her of professional services acting as an architect and project manager on the Garden Project.
(iv) The duty was to provide those services pleaded in paragraphs 14 and 15 of the Particulars of Claim with the exception of paragraph 14.2 and subject to the additional limitations and qualifications identified in the body of this judgment.
(vi) Yes, on both 28 April and 17 May 2013.
Further Steps
Note 1 See paragraph 14-003 of Keating on Construction Contracts, 9th edition. A false statement that a person is an architect is an offence under the Trade Descriptions Act 1968: see paragraph 14-009. [Back] Note 2 With no disrespect to him, I have corrected his spelling for clarity. [Back] Note 3 See the discussion in Jackson & Powell on Professional Liability 7th edition at paragraph 9-241. [Back]