QUEEN''S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
WALTER LILLY & CO LIMITED |
Claimant |
|
- and - |
||
JEAN FRANCOIS CLIN |
Defendant |
____________________
Mr Vincent Moran QC (instructed by DLA Piper) for the Defendant
Hearing date: 19th January 2016
____________________
Crown Copyright ©
Insert Judge title and name here :
The preliminary issues
1. Did RBKC’'s communication in its letter dated 17 July 2013:
1.1 mean that it required conservation area consent for the Works then ongoing to be obtained before it would allow those works to continue; and
1.2 amount to a requirement of a local authority or competent authority to halt the works within the meaning of the definition of “"Requisite Consents”" and/or “"Statutory Requirements”" set out at Clause 1.1 of the Building Contract?
2. If so, was Walter Lilly obliged and/or entitled pursuant to clause 2.1.1 and/or clause 2.3.7 of the Building Contract to halt the relevant works until either that consent had been obtained, or RBKC changed what it required?
3. If so did that obligation to halt the Works amount to:
3.1 an alteration or modification to the design, quality or quantity of the Works in accordance with clause 5.1.1 of the Building contract? And/or
3.2 the imposition by the Employer of any obligations or restriction in regard to (i) access to the site or use any specific parts of the site, (ii) limitations of working spaces, (iii) limitation of working hours or (iv) the execution of the work in any specific order in accordance with clause 5.1.2 of the Building Contract?
4. As between Walter Lilly and Mr Clin, did the risk and responsibility for ensuring that all planning consents in fact required by RBKC (whether lawfully necessary or not) were applied for and obtained prior to the Works being carried out lie solely with Mr Clin?
5. Was there an express or implied term of the Building Contract to the effect that Mr Clin was obliged:
5.1 to ensure that:
5.1.1 the Works had the required planning consents, including any consent subsequently required by RBKC (whether lawfully necessary or not) in relation to the proposed demolition works? And/or
5.1.2 RBKC was satisfied that all necessary consents and approvals for the Works (whether lawfully necessary or not) had been obtained prior to their commencement?
Or
5.2 Only to take due diligence (or, alternatively, reasonable skill and care) to obtain the planning consents necessary for the lawful completion of the Works?
6. Was Mr Clin obliged under the Building Contract:
6.1 prior to the Works commencing, to ensure that RBKC was satisfied that all necessary consents and approvals for the works had been obtained? And/or
6.2 following receipt of the 17 July Letter, to make a prompt and compliant application for the necessary conservation area consent (prior to 1 October 2013) and/or planning consent (post 1 October 2013)? And/or
6.3 to apply to RBKC for a Lawful Development Certificate and, if such a certificate was not granted, to seek to appeal that decision and/or their failure to apply for declaratory relief?
7. Note: The Claimant may apply to reinstate paragraph 3.3 of its proposed Preliminary Issues at the Hearing of 19 January 2016, provided that notice of such application is given not later than 7 days before the Hearing.”"
The terms of the contract
Employer’'s Persons:
“"…all persons employed, engaged or authorised by the Employer, excluding the Contractor, Contractor’'s Persons, the Architect/Contract Administrator, the Quantity Surveyor and any Statutory Undertaker but including any such third party as is referred to in clause 3.22.2”"
Statutory Undertaker:
“"Statutory Undertaker: any local authority or statutory undertaker where executing work solely in pursuance of its statutory obligations, including any persons employed, engaged or authorised by it upon or in connection with that work.”"
Pre-Construction Services:
“"the services set out in Annexure 4 and those referred to in clause 2A”"
Requisite Consent (added by the Schedule of Amendments):
“"Those permissions, consents, approvals, licences, certificates and permits as may be necessary to carry out and complete the works, including without limitation any approval of reserved matters in respect of the planning permission granted for the Development, Building Regulation consent and bye-law approvals and requirements of all competent authorities regarding the Development.”"
Statutory Requirements (amended by the Schedule of Amendments):
“"any directly applicable provisions of the EU Treaty or any EU Regulation, any statute, statutory instrument, regulation, rule or order made under any statute or directive having the force of law which affects the Works or performance of any obligation under this Contract and any approvals, requirements, codes of practice, regulation or bye-law of any local authority, competent authority or statutory undertaker which has any jurisdiction with regard to the Works or with whose systems the Works are, or are to be, connected.”"
(Words in italics added by amendment)
(Mr Brannigan added the emphasis to the concluding words)
“"Upon execution of this Contract and for the consideration mentioned in clause 2A.5 the Contractor will collaborate with the Consultant Team and shall commence the Pre-Construction Period and carry out and complete the Pre-Construction Services in accordance with clause 2A.4.1.”"
“"During the Pre-Construction Period:
1…
2…
3…The Contractor will remain wholly responsible for the carrying out and completing of the Pre-Construction Services.”"
“"The Contractor in submitting the Contractor’'s Proposals for the Contractor’'s Designed Portion and the Contract Sum Analysis in accordance with the terms and conditions of this Contract thereby confirms that it is satisfied that:
….
.4 any of the Works designed by the Contractor will fully comply with the Statutory Requirements and in accordance with the Employer’'s Requirements and this Contract”".
“"The Contractor shall assume responsibility for the Employer’'s Requirements in all respects pursuant to the terms and Conditions of this Contract”".
“"The Contractor shall carry out and complete the Works in a proper and workmanlike manner and in compliance with the Contract Documents, the Construction Phase Plan and other Statutory Requirements, and shall give all notices required by the Statutory Requirements and the Contractor shall forthwith supply to the Architect/Contract Administrator copies of all such notices and of all documentation relating thereto.”"
“"The Contractor warrants that the Works when completed shall comply with the Requisite Consents and Statutory Requirements.”"
“"Where there is a Contractor’'s Designed Portion:
2.19.1 insofar as the design of the Contractor’'s Design Portion is comprised in the Contractor’'s Proposals and in the Employer’'s Requirements and in what the Contractor is to complete under clause 2 and in accordance with this Contract (including any design which the Contractor is to carry out as a result of a Variation in the Employer’'s Requirements), the Contractor warrants and undertakes to the Employer that:
.1 . . .
.2 The Works will, when completed, comply with the Statutory Requirements and with any performance specifications or requirements included or referred to in the Employer’'s Requirements and will be adequate for the purposes of the Development, for the avoidance of doubt this excludes any fitness for purpose obligation;”"
“"The following are the Relevant Events referred to in clauses 2.27 and 2.28:
.1 Variations and any other matters or instructions which under these Conditions are to be treated as, or as requiring, a Variation;
. . .
.6 Any impediment, prevention or default, whether by act or omission, by the Employer, the Architect/Contractor Administrator, the Quantity Surveyor or any of the Employer’'s Persons, except to the extent caused or contributed to by any default, whether by act or omission of the Contractor or of any of the Contractor’'s Persons.
. . .
.13 force majeure.”"
“"The following are the Relevant Matters:
. . .
.6 any impediment, prevention or default, whether by act or omission, by the Employer, the Architect/Contractor Administrator, the Quantity Surveyor or any of the Employer’'s Persons, except to the extent caused or contributed to by any default, whether by act or omission of the Contractor or of any of the Contractor’'s Persons.”"
“"The term Variation means:
.1 the alteration or modification of the design, quality or quantity of the Works including:
.1 the addition, omission or substitution of any work:
.2 the alteration of the kind or standard of any of the materials or goods to be used in the Works;
.3 the removal from the site of any work executed or Site Materials other than work, materials or goods which are not in accordance with this Contract;
.2 the imposition by the Employer of any obligations or restrictions in regard to the maters set out in this clause 5.1.2 or the addition or alteration or omission of any such obligations or restrictions so imposed or imposed by the Employer in the Contract Bills or in the Employer’'s Requirements in regard to:
.1 access to the site or use of any specific parts of the site;
.2 limitations of working space;
.3 limitations of working hours; or
.4 the execution or completion of the work in any specific order”"
“"This is the list of items of services that are intended to be dealt with during the pre-commencement period.
1. Obtain consent relating to the planning condition in respect to highway and construction management.
2. Obtain consent relating to other relevant planning conditions that require discharging prior to commencement of works in respect to SUDS, Rainwater Harvesting and pool backwash system.
. . .
10. Identify if any other outstanding or missing or unknown or such issues that require clarification or further input so as to mitigate any delays.”"
“"the carrying out by the Statutory Undertaker of work in pursuance of its statutory obligations in relation to the Works, or the failure to carry out such work.”"
Mr Moran submitted that had this provision not been excluded from the contract it would “"have covered the key eventuality in the present case, namely the intervention of RBKC - whether lawful or not”".
“"the exercise after the Base Date by the United Kingdom Government of any statutory power which directly affects the execution of the Works.”"
“"the exercise after the Base Date by the United Kingdom Government, Olympic Delivery Authority and Transport for London of any statutory power relating to the London 2012 Olympics which directly affects the execution of the Works where such effects were not reasonably foreseeable.”"
Mr Moran submitted that this change to the normal printed form supports his case that the risk of foreseeable actions (including unjustified interventions) by statutory authorities that it including RBKC) was assumed by Walter Lilly.
The scope of the existing conservation area consent
The authorities
“"17. The question of implication arises when the instrument does not expressly provide for what is to happen when some event occurs. The most usual inference in such a case is that nothing is to happen. If the parties had intended something to happen, the instrument would have said so. Otherwise, the express provisions of the instrument are to continue to operate undisturbed. If the event has caused loss to one or other of the parties, the loss lies where it falls.
18. In some cases, however, the reasonable addressee would understand the instrument to mean something else. He would consider that the only meaning consistent with the other provisions of the instrument, read against the relevant background, is that something is to happen. The event in question is to affect the rights of the parties. The instrument may not have expressly said so, but this is what it must mean. In such a case, it is said that the court implies a term as to what will happen if the event in question occurs. But the implication of the term is not an addition to the instrument. It only spells out what the instrument means.
19. The proposition that the implication of a term is an exercise in the construction of the instrument as a whole is not only a matter of logic (since a court has no power to alter what the instrument means) but also well supported by authority. In Trollope & Colls Ltd v North West Metropolitan Regional Hospital Board [1973] 1 WLR 601, 609 Lord Pearson, with whom Lord Guest and Lord Diplock agreed, said:
""[T]he court does not make a contract for the parties. The court will not even improve the contract which the parties have made for themselves, however desirable the improvement might be. The court''s function is to interpret and apply the contract which the parties have made for themselves. If the express terms are perfectly clear and free from ambiguity, there is no choice to be made between different possible meanings: the clear terms must be applied even if the court thinks some other terms would have been more suitable. An unexpressed term can be implied if and only if the court finds that the parties must have intended that term to form part of their contract: it is not enough for the court to find that such a term would have been adopted by the parties as reasonable men if it had been suggested to them: it must have been a term that went without saying, a term necessary to give business efficacy to the contract, a term which, though tacit, formed part of the contract which the parties made for themselves.""
20. More recently, in Equitable Life Assurance Society v Hyman [2002] 1 AC 408, 459, Lord Steyn said:
""If a term is to be implied, it could only be a term implied from the language of [the instrument] read in its commercial setting.""
21. It follows that in every case in which it is said that some provision ought to be implied in an instrument, the question for the court is whether such a provision would spell out in express words what the instrument, read against the relevant background, would reasonably be understood to mean. It will be noticed from Lord Pearson''s speech that this question can be reformulated in various ways which a court may find helpful in providing an answer – the implied term must ""go without saying"", it must be ""necessary to give business efficacy to the contract"" and so on – but these are not in the Board''s opinion to be treated as different or additional tests. There is only one question: is that what the instrument, read as a whole against the relevant background, would reasonably be understood to mean?
“"26. I accept that both (i) construing the words which the parties have used in their contract and (ii) implying terms into the contract, involve determining the scope and meaning of the contract. However, Lord Hoffmann''s analysis in Belize Telecom could obscure the fact that construing the words used and implying additional words are different processes governed by different rules.
27. Of course, it is fair to say that the factors to be taken into account on an issue of construction, namely the words used in the contract, the surrounding circumstances known to both parties at the time of the contract, commercial common sense, and the reasonable reader or reasonable parties, are also taken into account on an issue of implication. However, that does not mean that the exercise of implication should be properly classified as part of the exercise of interpretation, let alone that it should be carried out at the same time as interpretation. When one is implying a term or a phrase, one is not construing words, as the words to be implied are ex hypothesi not there to be construed; and to speak of construing the contract as a whole, including the implied terms, is not helpful, not least because it begs the question as to what construction actually means in this context.
28. In most, possibly all, disputes about whether a term should be implied into a contract, it is only after the process of construing the express words is complete that the issue of an implied term falls to be considered. Until one has decided what the parties have expressly agreed, it is difficult to see how one can set about deciding whether a term should be implied and if so what term. This appeal is just such a case. Further, given that it is a cardinal rule that no term can be implied into a contract if it contradicts an express term, it would seem logically to follow that, until the express terms of a contract have been construed, it is, at least normally, not sensibly possible to decide whether a further term should be implied. Having said that, I accept Lord Carnwath''s point in para 71 to the extent that in some cases it could conceivably be appropriate to reconsider the interpretation of the express terms of a contract once one has decided whether to imply a term, but, even if that is right, it does not alter the fact that the express terms of a contract must be interpreted before one can consider any question of implication.
29. In any event, the process of implication involves a rather different exercise from that of construction. As Sir Thomas Bingham trenchantly explained in Philips at p 481:
""The courts'' usual role in contractual interpretation is, by resolving ambiguities or reconciling apparent inconsistencies, to attribute the true meaning to the language in which the parties themselves have expressed their contract. The implication of contract terms involves a different and altogether more ambitious undertaking: the interpolation of terms to deal with matters for which, ex hypothesi, the parties themselves have made no provision. It is because the implication of terms is so potentially intrusive that the law imposes strict constraints on the exercise of this extraordinary power.""
30. It is of some interest to see how implication was dealt with in the recent case in this court of Aberdeen City Council v Stewart Milne Group Ltd 2012 SLT 205. At para 20, Lord Hope described the implication of a term into the contract in that case as ""the product of the way I would interpret this contract"". And at para 33, Lord Clarke said that the point at issue should be resolved ""by holding that such a term should be implied rather than by a process of interpretation"". He added that ""[t]he result is of course the same"".”"
The course of the hearing
“"1. You will provide us with three drawings:
- Drawing 1 will show us the rear elevations of buildings before any of your files works commence i.e. The buildings in their “"existing”" state.
- Drawing 2 was show us the rear elevations of both building (sic) before any of your clients works commenced but with all parts of both buildings which have been demolished and which are to be demolished clearly shaded or coloured so there can be no misunderstanding about what parts of the buildings are removed as part of your clients proposals.
- Drawing 3 was shows the rear elevations of both buildings in their proposed final state following completion of all your clients works . . .”"
The issues about obtaining planning permission or conservation area consent
Issue 4
Issues 1-3: RBKC’'s letter of 17 July 2013
“"I write further to my officer’'s visit to the above-mentioned properties on 3rd July 2013 regarding demolition work undertaken. Whilst the extent of demolition at this time was not substantial demolition and a breach of the above Act had not occurred, my officer was shown plans from the on site engineer that indicated the following demolition works:-
- rear elevation of both 48 and 50 to be demolished below the cill of the first floor windows,
- the whole of the internal envelope of both buildings from third to lower ground level to be demolished
- the removal of the roof from each property
- the removal of the ground and lower ground front bay of 48 Palace Gardens Terrace
You are advised that the extent of demolition proposed above is considered substantial demolition requiring Conservation Area Consent from the Council. I confirm that such an application has not been sought or obtained.
I must also advise you that carrying out unauthorised substantial demolition works to a building in a conservation area is an offence under Section 9 of the Planning (Listed Buildings & Conservation Areas) Act 1990. Any person found guilty of such an offence is liable to a fine of up to £20,000 upon conviction in the Magistrates Court [and an unlimited fine if convicted by the Crown Court]. Continued non-compliance can result in further prosecutions for a similar offence, incurring similar fines. The Council may also issue a conservation area consent enforcement notice, which is served on all parties having a material interest in the property. It is entered on the Local Land Charges records which could make the future sale of financing of the property more difficult.
If it is your intention to proceed with the above demolition works, I would wish to receive an appropriate application within 28 days of the date on this letter. You will need to demonstrate why the above demolition works are structurally necessary and what temporary works you are proposing to secure the stability of the buildings. I would also wish to receive written confirmation of your intentions, within 21 days of the date on this letter.
If you fail to do so, and the works proceed without the necessary consent, I will consider initiating formal prosecution proceedings in this matter.
. . .”"
(1) It was not an instruction to stop either the Works generally or the demolition work specifically.(2) The letter contained an unequivocal expression of RBKC’'s view that the extent of the demolition work shown on the plans seen on site went beyond the scope of the existing conservation area consent.
(3) If that view was correct, or at least not wrong on its face, no reasonable contractor could be expected to continue with the demolition work for so long as RBKC maintained that position (save to the extent that he was confident that further demolition was permitted by the existing consent).
(4) In those circumstances if the want of appropriate conservation area consent was caused by a breach of the implied term by Mr Clin, then in the light of (3) above and/or clause 2.1.1 of the Contract (by which Walter Lilly was required to comply with Statutory Requirements), such breach would amount to an act of prevention by the employer.
(5) If the extent of the demolition work shown on the plans was more extensive than that for which conservation area consent had been obtained, and if that state of affairs was the result of a failure by Walter Lilly to provide relevant information to the architect in time (or within any time reasonably requested), then the effective cause of the want of the appropriate conservation area consent would be Walter Lilly’'s failure to provide that information.
(1) Issue 1.1: this issue does not affect the contents of paragraph 25.1 of the Particulars of Claim (which refers to the demolition work, not to the Works), but otherwise see above.(2) Issue 1.2: No.
(3) Issue 2: this depends on whether or not the relevant conservation area consent had been obtained. If it had, the answer is No. If it had not been obtained, the answer is Yes. (I note from the way in which this issue has been formulated that it seems to imply that the relevant consent had not been obtained.)
(4) Issue 3.1: upon the information available I am not in a position to answer this question. In any event, it may be largely a question of fact.
(5) Issue 3.2: I am not prepared to answer this issue upon the material available (because the answer would be either speculative or hypothetical); but if the want of relevant conservation area consent was the result of a breach of the implied term by Mr Clin, then I consider that such breach would have been amounted to an act of prevention.
Issues 6.2- 6.3: matters following RBKC’'s letter of 17 July 2013
The former paragraph 3.3 of Walter Lilly’'s proposed preliminary issues
After note
Note 1 It seems to me that the wording of clause 2A.6.2 is wide enough to include the situation where the contractor submits proposals that he knows are not covered by the existing consent(s) but is confident that the necessary consent can be obtained (“will fully comply . . . will fully comply . . . ). [Back]