QUEEN'S BENCH DIVISION
MANCHESTER DISTRICT REGISTRY
TECHNOLOGY AND CONSTRUCTION COURT
1 Bridge Street West, Manchester M60 9DJ |
||
B e f o r e :
SITTING AS A JUDGE OF THE HIGH COURT
____________________
AMEY LG LIMITED |
Claimant |
|
- and - |
||
CUMBRIA COUNTY COUNCIL |
Defendant |
____________________
Martin Bowdery QC & Frances Pigott (instructed by REN Legal, Solicitors, London EC2) for the Defendant
Hearing date: 10 November 2016
____________________
Crown Copyright ©
His Honour Judge Stephen Davies
A. Introduction
2.1 The appropriate order as to costs.2.2 The amount of the payment on account of costs.
2.3 The rate of interest on costs.
4.1 After taking into account all claims and counterclaims Amey was the victor, achieving a judgment of around £5.365 million, comprising around £3.698 million principal plus contractual interest of around £1.697 million.4.2 Amey was successful as to around £4.616 million in relation to its part 1 claim, claimed at around £7.915 million, being its valuation of its annual account claims for work done in the 3 final years of the contract, where it said that Cumbria had wrongfully undervalued its claims and wrongfully made deductions from them.
4.3 Amey was only successful as to around £296,000 in relation to its part 2 claim, claimed at around £19.774 million, being its valuation of what were pleaded as being 16 separate final account claims for additional sums claimed under the contract and/or as damages.
4.4 Cumbria was successful as to around £1.214 million in relation to its counterclaims, claimed at around £15.646 million.
4.5 Adding together Amey's part 1 and part 2 claims, and deducting Cumbria's counterclaims, pleaded as a defence and set off as well as an independent counterclaim, produced the net balance of £3.698 million principal. The interest of around £1.697 million represents contractual interest on that sum at 8% over base from June 2012.
B. The respective cases
(1) Whilst it accepted that Amey was the successful party, because of Amey's relative lack of success, its conduct and relevant admissible offers its costs entitlement should be reduced to 50% of its recoverable costs.(2) There should be separate costs orders in Cumbria's favour in relation to three discrete items, the first being the costs attributable to what I have found were Amey's delays and defaults as regards its failure to produce documents from its SAP IT system, the second being the costs attributable to what are said to have been Amey's unreasonable allegations of fraud and dishonesty made in closing submissions, and the third being the costs of obtaining legal advice as regards Amey's threat of contempt proceedings.
C. Costs incurred
C. The relevant principles as regards the award of costs
"(i) In commercial litigation where each party has claims and asserts that a balance is owing in its own favour, the party which ends up receiving payment should generally be characterised as the overall winner of the entire action.(ii) In considering how to exercise its discretion the court should take as its starting point the general rule that the successful party is entitled to an order for costs.
(iii) The judge must then consider what departures are required from that starting point, having regard to all the circumstances of the case.
(iv) Where the circumstances of the case require an issue-based costs order, that is what the judge should make. However, the judge should hesitate before doing so, because of the practical difficulties which this causes and because of the steer given by rule [44.2(7)].
(v) In many cases the judge can and should reflect the relative success of the parties on different issues by making a proportionate costs order.
(vi) In considering the circumstances of the case the judge will have regard not only to any part 36 offers made but also to each party's approach to negotiations (insofar as admissible) and general conduct of the litigation.
(vii)
(viii) In assessing a proportionate costs order the judge should consider what costs are referable to each issue and what costs are common to several issues. It will often be reasonable for the overall winner to recover not only the costs specific to the issues which he has won but also the common costs."
D. Proportionality
E. Success
(1) Amey succeeded on items (j), 3, 4, 5, 6, 8 and 19. Whilst it did not succeed in full on these claims they were not knowingly exaggerated. Mr Bowdery QC referred to item 6, landfill, where he submitted that the claim as advanced by Amey was rejected and it only succeeded on the basis of the court being prepared to find in part for Amey on the basis of the case advanced by Cumbria. Whilst that is true so far as it goes, it should also be borne in mind that I found Amey's case to be misconceived because it proceeded on a number of unverified assumptions, rather than because it was being put forwards on a basis which was always known to be exaggerated or hopeless.(2) I did find that items 1 and 2 were put forwards on an artificial exaggerated basis, see my substantive judgment at [9.14], although I did not find (and do not find) that they were knowingly put forward on that basis.
(3) Amey lost on item 12, the very substantial Better Highways re-rating claim, because whilst I found for Amey on the number of gang days worked I was not satisfied that it was contractually entitled to a re-rate (see paragraph 5 above) - there was no question of exaggeration, knowing or otherwise, by Amey.
(4) I did not and do not find exaggeration by Amey, whether intentional or otherwise, in relation to item 13; it was simply a claim which failed on my interpretation of the contract and my factual findings. The same is true of item 14.
(5) I found against Amey on item 17 on the basis of my finding as to what was contractually required of Cumbria and on the basis that it was a global claim. I was also critical of Amey's approach to extrapolation, which I did describe as an "egregious failure" [18.29]. However I also recorded [18.17] Amey's ready acceptance that this claim was really only ever advanced as a counter to Cumbria's equivalent patching thickness claims. Thus I would consider this as an opportunistic and over-optimistic claim, as opposed to a deliberately dishonest or exaggerated claim.
(6) I found against Amey on item 20 on the basis of my findings as to the proper interpretation of the contract and on the basis that it was a global claim, but I did not nor do I find that it was pursued as a deliberately dishonest or exaggerated claim.
(7) Amey did not completely lose on item 23, and there is no question of this being an exaggerated claim.
(8) Amey lost on item 24 and I did accept that it was a "speculative" claim [22.10], but it was really no more than a book-end claim anyway.
F. Conduct
SAP
Other conduct / Contempt
G. Admissible Offers
(a) Its approach was both commercial and reasonable, in contrast it says to Amey's uncommercial and unreasonable approach. Thus it says that the only relevant admissible global offer made by Amey was one made in August 2014 to accept only £19.95 million plus costs. It complains of Amey's failure to make any admissible global counter-offer in response to Cumbria's drop hands offer, and submits that this illustrates that Amey continued to take a wholly unrealistic approach to its part 2 claims. In oral submissions Mr Bowdery contended that had Amey made a sensible counter-proposal in response to Cumbria's offer it is likely that a reasonable settlement would have been achieved.(b) As at July 2015 the true value of Amey's claim (adjusting for interest) would have been around £4.87 million. It submits that given the likely costs recovery which Amey will obtain on detailed assessment it is likely that Amey spent more than that in costs from that date onwards in obtaining the judgment which it did.
H. My Decision
(1) A substantial amount of the time and cost of this case was taken up by the consideration of the details of the contract and how it operated in the 7 years of its lifetime, because all of this was relevant to a good deal of the individual claims and counterclaims. This time and these costs may properly be regarded as "common" as opposed to "issue specific" costs.(2) A substantial, broadly equivalent, amount of time and cost was taken up by the consideration of the substantial value defects counterclaims, on which Cumbria very substantially failed, and in respect of which I have made considerable criticisms of Cumbria. It was this substantial failure which really explained why Amey established a net balance due in its favour.
(3) A substantial, but lesser, amount of time and cost was taken up by the consideration of the substantial value Better Highways payment claim, on which Amey very substantially failed, but where I have no criticism whatsoever of Amey in pursuing this claim, and indeed where Cumbria also failed on one of the two substantial issues (number of gang days, as opposed to rate, where Amey failed).
(4) A substantial, but also lesser, amount of time and cost was taken up by the consideration of the individual items of claim and counterclaim, where there were varying degrees of success and failure on both sides. Whilst Amey undoubtedly failed on a substantial proportion of its claims, and whilst I have made some criticisms of some of its claims, it is not a case where I concluded that all, or even the greater majority, of Amey's part 2 claims were either hopelessly weak or deliberately exaggerated.
(5) Standing back, the most significant consideration here in my judgment is that both parties were advancing substantial claims against the other, where they both knew that the critical question was who owed who money and how much. Amey has convincingly won overall, because although it has won significantly less than it claimed it has still recovered a substantial amount, and it has also succeeded in defeating very substantial counterclaims. Cumbria made no Part 36 offer, and came nowhere near to making any sensible admissible alternative settlement proposal involving a substantial payment both of principal, interest and costs. Whilst with hindsight Amey ought to have considered making a counter-proposal or Part 36 offer in response to Cumbria's drop hands proposal, there is no basis for considering that this would have resulted in a settlement and no proper basis for any serious criticism of Amey's overall approach to seeking to settle this case.
(6) Whilst there are some limited criticisms which can be made of Amey's conduct, the same is true of Cumbria.
I. Payment on account of costs
J. Interest on costs incurred pre-judgment
Note 1 The figures are taken from the version of the agreed quantum experts schedule dated 9 November 29016 produced by Ameys quantum expert Mr Taft and attached to the substantive judgment. [Back]