QUEENS BENCH DIVISION DIVISION
LEEDS DISTRICT REGISTRY
TECHNOLOGY AND CONSTRUCTION COURT
Oxford Row Leeds LS1 3BG |
||
B e f o r e :
____________________
MR SYDNEY BELL MRS ANGELA BELL |
Claimants |
|
- and - |
||
(1) NORTHUMBRIAN WATER LIMITED |
Defendant |
____________________
Mr James Medd (instructed by DAC Beachcroft Claims)) for the Defendant
Hearing dates: 19, 20, 21 and 22 January 2016
Date draft circulated to the Parties: 15 February 2016
Date handed down: 5 April 2016
____________________
Crown Copyright ©
Introduction
Limitation
“"I do not think that in the case of a continuing nuisance … the Statutes of Limitations have any application except as to the amount of damages to be recovered”"
Does the Defendant have a relevant duty?
“"The existence of a parallel common law right, whereby individual householders who suffer sewer flooding may themselves bring court proceedings when no enforcement order has been made would set at nought the statutory scheme. It would effectively supplant the regulatory role the director was intended to discharge when questions of sewer flooding arise""
“"Thames Water does not have any programme to check for tree roots or other problems with sewers in its area, not even a gradual or targeted one. Instead it waits until defects have been reported by others, including the public, and then it acts.
This approach makes inevitable the type of experience Ms Nicholson had. Only if a defect has been encountered early and reported by the public or the highway authority might an experience of the type she had be avoided.
Views will differ on the question of whether that reactive system is good enough. However in light of the scheme of the 1991 Act, as explained in Marcic that is not a question for this Court to judge in litigation such as the present.”"
“" Whilst the principle in Marcic’'s case precludes the claimants from bringing claims which require a court to embark on a process which is inconsistent and conflicts with the statutory process under the 1991 Act, it does not preclude the claimant from bringing a claim in nuisance involving allegations of negligence where, as a matter of fact and degree, the exercise of adjudicating on that course of action is not inconsistent and does not involve conflicts with the statutory process under the 1991 Act""
“"Policy matters were likely to lead to such inconsistency and conflicts and operational matters were less likely to do so. It must be a question of fact and degree. Where an allegation is tantamount to requiring major plant renewal that will fall on one side of the line whilst an allegation that a filter should be cleaned will lie on the other side of the line”"
Is there strict liability for the nuisance or does it have to be fault based?
Independent Contractors
""it matters not whether the defendants themselves by their actions cause subsidence or whether they employ contractors … their duty was to prevent their sewage plants becoming a nuisance. How they accomplish that was immaterial""
“"Whether a person can be said to be a wrongdoer if the nuisance is created by an independent contractor depends on whether he could reasonably have foreseen that the work he had instructed the independent contractor to do was likely to result in a nuisance”"
“"the Defendant clearly continued the nuisance for they came clearly within the terms that they knew the danger, they were able to prevent it and they omitted to prevent it”"
Does a claim lie in nuisance for withdrawal of support where the land immediately affected is not owned by the Claimants?
“"The duty of the owner of a sewer at common law will be to see that the sewage in his sewer does not escape to the injury of others and mere neglect of this duty would give the person so injured a good cause of action.”"
S180 1991 Act and Schedule 12 paragraph 4
Remaining Issues
Causation
June 1980 | Construction of Dene Lodge begins |
March 1995 | Construction of the extension to the north of the existing property commences begins |
3 May 2001, | Mrs Bell telephoned Sandra Hutton, an operative at the Defendant customer call centre. There is a computer note of that conversation. It states as follows “"Urgent – at back of the garden area sunken-thought due to rain but now found raw sewage leaking and running into burn at the rear |
4 May 2001 | A repair was undertaken by Graydons, a firm of contractors on the Defendant’'s list of approved contractors. The repair consisted of the installation of 5 metres of plastic pipe into the existing sections of the sewer pipe. |
3 March 2003 |
Mrs Bell telephoned the Defendant again. This time she spoke to Valerie Thompson another operative employed at the call centre. Mrs Thompson records that “"mrs (Bell) rang to confirm sewage running into the burn again see prev notes. Last time there was a sewage collapse due to landslide please can we ask the rep to check this out”" |
27 September 2007 | The sewer pipe fails in that there is no flow detected to the sewage treatment works. The sewer is found to be in poor condition |
28 September 2007 | CCTV survey and temporary repair undertaken by Graydons |
1 October 2007 | Further CCTV survey |
5 October 2007 | Graydons carry out further repairs |
15 October 2007 | Further repairs following further leaks |
18 October 2007 | The Defendant record that the Claimants’' garden is falling away |
25 October 2007 | Graydons install plastic piping from rear of Dene Lodge to the sewage works |
7 February 2008 | Entec (a further contractor) visits the site |
13 February 2008 | Entec reports to the Defendant |
11 February 2008 | Mrs Bell calls the Defendant to report that drain is backing up |
22 February 2008 | The Defendant install a temporary fix to the backing up drain |
27 February 2008 | Entec recommend diversion of the sewer |
May 2008 | Temporary pipe installed |
1 December 2008 | Further leak from temporary pipe |
26 April 2010 | Further leak reported. The Defendant’'s employee who attends on site reports further ground movement |
27 April 2008 | Graydons carry out repair |
20 September 2010 | Permanent remedial work involving diversion of part of the sewer under the roadway commences |
Jan/Feb 2011 | Grouting work to abandoned pipe carried out |
The Claimant’'s Lay Evidence
Mr Sydney Bell
Mrs Angela Bell
Mr Kenneth Johnson
The Defendant’'s Lay Evidence
Mr Neil Howliston
“"All land in this area where it slopes down to watercourse is falling away but leakage from the sewer will be causing further instability in the ground conditions. Edge of garden to Dene House (sic) is already falling away and the occupiers do link this to the ongoing problems with the sewer”"
“"sewage continues to leak, currently in 2 places from hole in bank side and from plastic pipe, causing further instability in ground conditions…”"
Mrs Aileen Deeble
“"it is very obvious that there has been a lot more ground movement since I last attended this site and Dene Lodge has lost more of its garden area”"
Mr Paul Kelly
Mrs Kathryn Waugh
Mr Amitkumar Patel
Mr Mark Johnson
Mrs Beatrice Brindley
“"The failure of the existing combined sewer was likely to be due to progressive slope movement on the bank of Ogle Letch. It is considered most likely that original pipe failure was due to slope movement, however subsequent episodes of leaking sewage from broken pipes or open joints may have exacerbated the existing instability”"
Mr Richard Woodhouse
Mr Paul Scorer
Mrs Sandra Hutton
The Experts
Dr George Reeves
a. The slope angles of the bank of the burn below Dene Lodge are only about 15 to 20 degrees. Glacial till such as this is usually stable until the slope is about 28 degrees.
b. The slope is eroding from the top to the bottom. There is, he says, a down slope movement of material from the top of the slope which is in stark contrast to the small slope failure due to toe [9] erosion by the flow of water in the stream.
c. Evidence of rotational shears can be seen in the top of the slope because the shear strength of the clay has been weakened by continuous saturation of the upper part of the slope by fluids emanating from the pipe or its trench.
d. There is no other slope movement occurring at other parts of the bank at different locations that have a similar incline.
e. A chemical reaction between the clay and alkaline in effluent will also undermine the integrity of the slope
a. TPB reveals that the pipe is only incompletely grouted in that there is grout in only the bottom of the pipe.
b. Water emerged under pressure from the pipe in TPA into the excavated hole and seepage from the pipe joint was noted..[10]
c. Seepage was noted from the pipe at TPC and TPD.
a. The abandoned sewer remains in the ground notwithstanding that the original plan shows that in the area to the east of Dene Lodge it should be removed.
b. There has been grouting which is ineffective in preventing lateral flow of fluid along the pipe.
c. Repairs to joints were ineffective in sealing leaks.
d. There is a trench providing a preferential pathway for subsurface fluids.
e. The defective pipe and the trench are introducing moisture into the area which is slipping and is the cause of the slippage because it has made the area too saturated to remain stable.
f. As regards Syd’'s Wood Garage, made ground and the outfall of water from the highway drain, these are all minor features in only one of the areas of landslip and make little, if any, contribution to the slope failure. Indeed it can be seen in the trial pits that the made ground is insignificant. [11]
“" I can’'t say whether this slippage would have occurred even if the pipe had not been there and was never there. I don’'t think anybody can but the rest of Ogle Letch has not failed and the only difference is this pipe. There must be highway drainage in place in other areas but there has been no problem there”"
Dr David Barrie Jones
a. The bank in its natural state is probably only marginally stable but the bank to the east of Dene Lodge has had significant made ground tipped onto it and at the lip of the slope. In paragraph 5.1.2 of his report he specifically singles out the made ground adjacent to Syd’'s Wood Garage because not only is its weight a factor but it serves to block or partially block the highway drain. However he points out that there is also made ground further to the north, on an area of landslip.
b. Ground movement has clearly occurred before 2007. This is clear because the foundations of the telegraph pole to the north of Dene Lodge (and well away from the area of land slip near Syd’'s Wood Garage) were affected by saturation even before 2001. I refer to this in paragraph 76 above.
c. The drainage channel to the north of the property is draining into an area affected by land slip. If, as is common ground, the landslip is caused by saturation then it is argued that that channel (both before and after it was enlarged in 2014) has been introducing into an already naturally wet area copious volumes of water from the pavement of Beacon Road and the hills below the pavement but above Dene Lodge.
d. The highway drain flows onto the bank adjacent to the property adding to saturation caused by a high water table. Not only that but, as I have said, the outfall is obscured by made ground.
e. Surface water from the rear of Dene Lodge is running onto the slope from areas other than the drainage channel because Dene Lodge is higher up than the slope and slopes towards it.
f. Erosion caused by the fact that this area is on the outside of a bend in the burn. [12].
g. Rainfall and a natural rise in the water table.
Conclusion as to causation
Material Contribution
“"the essence of the Claimants’' case is that a reduction of the water levels in the ponds causes their alleged loss and damage. Thus, in my judgment, the Claimants must prove on the balance of probabilities that, but for the excavation of the lakes, their loss and damage would not have occurred.
Fault based nuisance
Final Remarks
HH Judge Saffman
Note 1 See witness statement of Beatrice Brindley paragraph 12 [Back] Note 2 It is described by Dr Reeves, the Claimants’ expert as a “higher permeability drainage pathway” [Back] Note 3 Clerk and Lindsell Ed 21 para 20-142 [Back] Note 4 It is not disputed that there has been leakage from the pipe because of defects in it [Back] Note 5 I do not overlook that there is another water course commencing at a junction in the road leading to the Beacon Road row of houses that will capture some of the water falling in that area and prevent it flowing onto the Claimants’ land or the slope to the burn abutting it [Back] Note 6 The evidence of Mr Woodhouse (which was not challenged) was, at paragraph 20 of his Witness Statement, that a grade 5 defect is “where the pipe moves, deforms, or collapses.”
OR Category 5 defect means that sections of the sewer have collapsed. [Back] Note 7 Which had been installed as a temporary measure some years before [Back] Note 8 It should be noted that since 2007 this section of the pipe was not operative in any event and sewage was transported via 150 metres of plastic pipe installed in 2007 as part of the temporary repairs. [Back] Note 9 That part of the slope contiguous to the running water [Back] Note 10 In fact Dr Reeves did not see water emerge under pressure. He was simply told that by Mr Bell who had dug the pit. [Back] Note 11 I should add that at E10 he says that no builders’ rubble etc is evident below Dene Lodge. As Dr Reeves accepted, from the evidence of photographs attached to Dr Jones report, there is made ground here but insufficient to be a factor contributing to land slip. [Back] Note 12 Demonstrated by the plan at E219 [Back] Note 13 See paragraph 146 above [Back] Note 14 Although I accept Mr Collins contention in paragraph 21 of his final submissions that there are defects along the whole length of the sewer, not just in the area abutting Dene Lodge [Back]