QUEEN''S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
(1) EDWARD GOLDSWAIN (2) JACQUELINE HALE |
Claimant |
|
- and - |
||
(1) BELTEC LIMITED (t/a BCS CONSULTING) (2) AIMS PLUMBING AND BUILDING SERVICES LIMITED |
First Defendants Second Defendant |
____________________
Steven Walker QC (instructed by Bond Dickinson LLP) for the First Defendants
The Second Defendant did not appear and was not represented
Hearing dates: 17-20 and 24 February 2015
____________________
Crown Copyright ©
Mr Justice Akenhead:
The History
“"I was pleased to meet you at the above property to discuss your requirements, with a view to providing a quotation for the structural elements of the above scheme.
We estimate to prepare details and justifying calculations, based on our conversation which I understood to be carrying out a survey of the existing basement/ground floor, designs for excavating the basement, underpinning the perimeter walls, providing support to the internal walls and structure as necessary, providing details for damp proofing and drainage, in sufficient detail to satisfy the building regulations, our fee would be £1,350 + VAT and disbursements.
The above fee allows for a single initial visit.
We trust the above information is sufficient for your immediate needs and look forward to your further instructions.
If you wish for us to proceed, could you please sign and return the attached letter of instruction and sign the agreement to our Terms and Conditions. We are unable to proceed without this being returned. At present we are able to prepare calculations within approximately 2 weeks of any instruction, obviously this can vary depending upon workload from week to week…”"
“"This letter instructs [Beltec] to carry out structural designs in accordance with their estimate letter…
This cost being £1,350 + VAT and disbursements.
Any subsequent site visits will be charged at £200.00 + VAT per visit…”"
“"UNDERPINNING METHOD STATEMENT
1. Divide overall length of wall into 1m length as shown on drawing, work sequence to be such that the wall is adequately supported at all times.
2. Excavate pins in order shown.
3. Construct basement slab section + kicker.
4. Construct wall section. Leave 24 hours (600 mm reinforcement to be driven to the next section).
5. At mid-height prop pin horizontally against internal ‘'dumpling’' or opposite face.
6. Dry pack between wall & foundations leave for minimum of 48 hours before excavation of any adjacent pins.
7. Excavate next pin (in order shown).
8. Repeat 2.
9. Repeat 3.
UNDERPINNING GENERAL NOTES
…3. A soil investigation is to be carried out including trial pits and boreholes prior to confirmation of engineer’'s details…
6. Concrete pins to be constructed in the order as shown on the drawing…
12. The contractor is responsible for the stability of all excavation and the building during the course of the works and therefore shall have planking and strutting on site at all times to comply with current health and safety regulations…
15. New high level underpinning to be horizontally propped at mid height. Corners to be propped with diagonals across adjacent pins. All propping and temporary works to contractor’'s design and method statement…”"
“"After discussions with Jaquie Hale we understand that you produced the drawings and specifications for the above project.
We are going to be undertaking the 1st fix works inclusive of the underpinning. Could you confirm at this stage if you are going tohave any further input into this project. At present we are producing a method statement for the underpinning works and will require the input from a structural engineer to confirm the following:
1. Inspect the initial bays and advise of new foundation depth
2. Concrete specification and any reinforcement requirements
3. Temporary structural propping
If you have not allowed for these works please could you provide us with a quotation.
Please contact me to discuss further.""
It is likely that there was no response from Beltec to this letter. That is evidenced from an e-mail dated 3 September 2012 from Mr James of AIMS to Ms Hale. Another e-mail from her to Mr James on 10 September 2012 suggests that she spoke to someone at Beltec who said to her that it would not ""normally work with the builder as this duplicates what the local authority does""; she asked them to try again.
“"Regarding the underpinning method statement I have attached the drawing 12065-TW001 which contains the suggested method statement along with the horizontal props position.
For any question don''t hesitate to contact me.""
Mr Pistilli accepted in evidence that the ""TW"" reference meant ""Temporary Works"". This was essentially the same as Drawing S002A with the following (material) amendments:
(a) Notes to the ""Underpinning Method Statement”" became:
“"8. Repeat 2-6 until last pin is constructed.
9. Excavate and Cast Base Slab"".
` (b) Added to the Basement Underpinning Plan at two locations, there were shown two horizontal props from the flank wall back to the party wall described as:
“"”"Mabey”" S3/10 Mk3 soldiers (or equivalent ""Mabey”" tubular) horizontal props installed to manufacturer’'s specifications"".
These were located on the plan about 2m away from the rear side light well and from the front or road side wall. These types of prop are heavy duty props from a well-known manufacturer.
The Proceedings
(a) Whether in the original design documentation produced in March 2012 Beltec should have spelt out or explained any unusual risks not likely to be obvious to a competent contractor.
(b) Whether Beltec should have checked whether the contractor to be appointed had secured or had internally the appropriate expertise to carry out the job.
(c) Whether Beltec should have appreciated and provided for any particular weakness created towards the rear of the flank wall by the introduction of the rear light well and the doorway to be created in that area.
(d) Whether the contract between the Claimants and Beltec was such that Beltec had a continuing obligation after providing the design for the underpinning and floor slab to visit the site and give appropriate advice.
(e) Whether Beltec was negligent in failing to warn both AIMS and the Claimants about the shortcomings in AIMS’' activities.
(f) Whether AIMS would have done any better than it did do even if the risks had been spelt out more precisely than they were or if an appropriate warning had been given in late September 2012 to it by Beltec.
(g) What was the mechanism of failure: bearing pressure (that is primarily downward movement), not associated with an absence of propping or horizontal or lateral failure of the basement walls caused by an absence of propping.
The Witnesses
The Law
“"I do not think that the consulting engineer has any duty to tell the contractors how to do their work. He can and no doubt will offer advice to contractors as the various aspects of the work, but the ultimate responsibility for achieving the consulting engineer’'s design remains with the contractors…”" (Page 123)
“"…What is said, however, is that when the consulting engineer knows or ought to know that the contractors are heading into danger whereby damage to property is likely to result, then he owes the contractors a duty of care to prevent such damage occurring. If he sees the contractor is not taking special precautions without which a risk of damage to property is likely to arise, then he the consulting engineer cannot sit back and do nothing. I am not sure that the consulting engineer’'s duty extends quite that far but, even if it does, I do not believe that he is under a duty to do more than warn the contractors to take the precautions necessary, and in so far as those precautions consisted here of shoring and providing temporary support and immediate blinding in excavations in the vicinity of the party wall, I am satisfied that [he] gave [the contractor] ample warning"". (Page 124)
This case did not unequivocally therefore establish that there was a duty to warn because the judge said at Page 124 that he was not sure that the duty extended that far. In any event, it is predicated on the basis that the engineer knows or ought to know that the contractors are heading into danger.
“"The present appeal concerns (a) temporary works which were (b) designed and specifically instructed by the employer, so that (c) they became part of [the sub-contract] works, which (d) were obviously dangerous, and which (e) [the sub-contractor] knew to be dangerous….[The main contractor] had the services of the consulting civil engineer. [The main contractor and the sub-contractor] are each to be taken as experienced in their respective roles. In my judgment, of the elements which I have referred to, all are relevant but (d) and (e) are crucial. These temporary works were, to the knowledge of [the sub-contractor], obviously dangerous to the extent that the risk of serious personal injury or death was apparent. [The sub-contractor] were not mere bystanders and, in my judgment, there is an overwhelming case on the particular facts that their obligation to perform their contract with the skill and care of an ordinarily competent contractor carried with it an obligation to warn of the danger which they perceived…The question is, not whether [the sub-contractor] owed a duty of care to someone who was injured, but what was the scope of the implied contractual term in their subcontract with [the main contractor…[The sub-contractor], with others, had a duty to guard against the risk of personal injury to a potentially large number of people. That duty extended to giving proper warnings about the risk. It was not itself a contractual duty owed to the [main contractor], but it is a relevant circumstance in determining the extent of performance which [the sub-contractor’'s] implied duty of skill and care required…”"
May LJ (with whom the two other members of the Court agreed) at page 148 left over for “"future consideration circumstances where (a) the contractor did not know, but arguably ought to have known, that the design was dangerous, and (b) where there was a design defect, of which the contractor knew or ought to have known, which was not dangerous"".
“"16. I do not accept Mr Brown''s submission that it is sufficient to establish the duty to warn that it was possible that Avonforce would carry out the excavation in the way that it did. It seems to me that it is unreasonable to impose a duty to warn in such circumstances. It is common ground that Avonforce was negligent in excavating in the way that it chose to do. Why should Advanced assume that Avonforce would carry out the excavation negligently when it could have chosen a safe alternative way of doing it? The case for a duty to warn becomes even more difficult when there is added to the other elements of the case the fact that Avonforce was being advised by apparently competent engineers. It is true that Advanced did not know the scope of KHP''s retainer, but Mr Roberts was aware that KHP were involved, because they had written annotations on the drawing. It is true that on the facts of Plant, the fact that the instructions had been given by the clients'' engineer did not negative the duty to warn. But in that case, JMH was aware that what it was instructed to do was dangerous. Where, as here, the contractor is not aware of what is proposed, and at its highest, the case is that it ought to have known that what occurred might have been proposed, it seems to me that the position is quite different. In such a case, I consider that it is relevant to the question of whether there is a duty to warn that the client is being advised by an independent professional person. Why should the contractor assume that the client will act negligently, particularly when he is being independently advised by an engineer?
17. As I have said, in my view it is unreasonable to impose a duty to warn on Advanced in the circumstances of this case. The duty to warn is no more than an aspect of the duty of a contractor to act with the skill and care of a reasonably competent contractor. Reasonableness lies at the heart of the common law. As Lord Reid said in Lord Reid said in Young & Marten Ltd v McManus Childs Ltd [1969] 1 AC 454, 465 ""no warranty ought to be implied in a contact unless it is in all the circumstances reasonable"". Advanced was not asked to advise Avonforce what excavation techniques should be adopted, nor did Avonforce tell Advanced how it proposed to go about carrying out the excavation. It chose to employ a method that was negligent when suitable alternatives were available.”"
“"22. In my judgment if an engineer employed by an owner in respect of permanent works observes a state of temporary works which is dangerous and causing immediate peril to the permanent works in respect of which he is employed, he is obliged to take such steps as are open to him to obviate that danger. It seems to me that that follows, partly as a matter of common sense, but also because the engineer is, after all, instructed in relation to the permanent works as a whole. It would appear strange if he is under a duty to take such steps as he can to see that they survive for say, the next 25 years, or whatever the design life for the building is, but is not obliged to take any steps to warn of an immediate danger to those works caused by an imperilling act by the contractor.”"
He went on to find that an obviously dangerous state of affairs had arisen which was apparent when the engineer attended site (see Paragraph 54) and that Mr Fidler was in breach of duty for not warning the contractor of the risks of the site collapsing and in not taking immediate steps to prevent the danger (see Paragraph 56).
“"78. In my view, there can be little doubt that a failure to warn in the case of potential danger to human beings may give rise to a breach of any duty of care owed to a third party by a party who knows of the danger. I use the word ""may"" because it is necessary always to review all the circumstances and there might be circumstances which justify not warning. Where the parties are in contract, the duty to warn may extend to dangers of which the party in question should have been aware by reason of its involvement. Thus, a surveyor contractually appointed may owe his client a duty of care and will often be under an obligation carefully to ascertain whether there is a danger in the structure being surveyed; failure to advise or warn of the danger may well still give rise to liability even if the surveyor is in fact unaware of the danger. In purely tortious circumstances, any duty to warn may not in fact extend to warning the class of persons who might be affected by the danger; it may be limited to warning the party with whom the person required to warn is in contract or to warning the local authority.
79. In conclusion on this topic, I consider that an obligation to warn may arise in the context of a tortious duty of care, certainly in the case of a danger to people, known to exist by the person who it is said should be giving a warning. This will depend on all the facts and the circumstances including what function and role the person said to be required to warn is fulfilling. All other aspects of the law relating to whether duties of care exist at all and the scope of such duties apply to the issue of whether warnings should be given. It is at least possible that where someone is charged, contractually, with an obligation to ascertain or check whether designs or works are safe for human beings, his or her tortious duty of care may extend to warning or advising about inherent dangers of which he or she should have been aware.
80. In my judgement overall, Bembridge has simply failed to establish that Mr Bennett, AFL or Mr Martin were in breach of the duty of care which they owed to Mr Cleightonhills. In the case of Mr Bennett, there was nothing careless in his provision, location and fixing of the steel clips; he can not properly be criticised for failing to warn Bembridge of the inadequacy of the location and fixing of the platform gratings because there was nothing in itself wrong with such location and fixing because the gratings were put in exactly the position specified and the fixings of the relevant Panel 3 were in terms of numbers and locations consistent with the requirements of good practice and BS 4592. The installation and fixing of the grating complied with BS 4592; the problem was not with the installation and fixing but it was with the design for which Mr Bennett had no responsibility and which he neither knew nor could reasonably be expected to have known was deficient. He properly sub-contracted the supply and fabrication of the steel work, including the gratings, to AFL. He did not know the specific and precise purposes of the Platform (heavy loads, small wheeled trolleys, aggressive use of forklift truck, routine presence of people on the Platform). He was entitled to assume, and was certainly not careless in assuming, that Mr Ely and RMA between them would have spelt out precisely what they wanted and what was required in the drawings upon which they asked him to quote. He can not be criticised for failing to be aware of the need for an edging strip because neither was it clear or discernible from all the information provided to him and indeed to Mr Martin that there would be material horizontal loads which could or would foreseeably cause the gratings to move nor was it in practice or under his contract incumbent on him to question the design to which he was being required to work.”"
“"100. However, it does not seem to me that such a duty arises on the facts of this case. First, the ''duty to warn'' cases all arise in the context of a contractual relationship: there are no reported cases in which this kind of duty to warn is said to arise in tort, owed to a third party. There is no reason, either on the facts or as a matter of policy, to extend the duty in this case, particularly as Mr Steel was a contractor, not a professional. That conclusion may be another way of expressing the conclusion I have reached above about the absence of sufficient proximity.
101. But even assuming that such a duty was capable of being owed to a third party, all of the cases stress that a duty to warn is only triggered by a clear defect or something that is ''obviously dangerous'' (the expression used in Plant and Aurum). When applied to the facts of this case, it means that if (which I do not accept) Mr Steel was capable of owing a duty to warn to the claimant, that duty would only have been triggered by his discovery of something that was obviously dangerous. But there was no such thing. As set out in paragraphs 17-18 above, the Tree was apparently healthy. It was also covered in ivy. There was nothing which would have identified to Mr Steel that the Tree was ''obviously dangerous''. He would not have seen the fork because it was covered in ivy. And the mere fact of the fork would not have put even a trained arboriculturalist on notice that there was a problem, at least not without further investigation. He would only have noticed the decay behind the ivy if he had looked carefully for it and there was nothing in his contract workscope that required him to do any such thing.
102. The duty to warn cases are all designed to ensure that a defendant cannot escape liability by referring to and relying upon the narrow constraints of his contractual obligations, in circumstances where he knew (or perhaps ought to have known, although that is itself controversial) that there was a significant danger or problem which no one else had spotted. But it is wrong in principle, as Mr Meredith Hardy seeks to do, to say that there was an obligation to carry out a detailed inspection of the Tree, pursuant to which Mr Steel would have found out its condition, so he could then comply with a duty to warn of obvious defects. That is the wrong way round. A duty to warn starts with the existence of obvious problems which are either known (or perhaps which should have been known) to the professional man or contractor. It does not impose an obligation to carry out wide-ranging inspections and investigations so as to discover whether there is an obvious defect, which might then trigger a duty to warn.”"
(a) Where the professionals (engineers in this case) are contractually retained, the Court must initially determine what the scope of the contractual duties and services were. It is in the context of what the professional person is contractually engaged to do that the scope of the duty to warn and the circumstances in which it may in practice arise should be determined.
(b) It will, almost invariably, be incumbent upon the professional to exercise reasonable care and skill. That duty must be looked at in the context of what the professional person is engaged to do. The duty to warn is no more than an aspect of the duty of a professional to act with the skill and care of a reasonably competent person in that profession.
(c) Whether, when and to what extent the duty will arise will depend on all the circumstances.
(d) The duty to warn will often arise when there is an obvious and significant danger either to life and limb or to property. It can arise however when a careful professional ought to have known of such danger, having regard to all the facts and circumstances.
(e) In considering a case where it is alleged that the careful professional ought to have known of danger, the Court will be unlikely to find liability merely because at the time that the professional sees what is happening there was only a possibility in future of some danger (see Aurum); any duty to warn may well not be engaged if all there is is a possibility that the contractor in question may in future not do the works properly.
Liability (Beltec) - Discussion
“"This letter instructs [Beltec] to carry out structural designs in accordance with their estimate letter…”"
This points strongly also to the scope of the services not covering any supervision or inspection of the contractor. The fact that there is nothing in either letter referring to any involvement with the contractor underlines this as well. The reference to ""subsequent site visits"" to be charged at £200 plus VAT is comprehensible as advising the clients that if they require such visits this is what it would cost.
“"Constructing a basement underneath a domestic property is specialised high risk work that can catastrophically affect the stability of existing buildings.
The project architect and engineer must provide detailed plans of the finished basement.
The builder must use these plans, together with knowledge of the ground conditions on site, to make sure the construction work is planned and undertaken safely. This includes identifying any temporary works such as trench supports or propping arrangements that are required to ensure the stability of any excavation or existing buildings.
Temporary works are the responsibility of the builder and should be planned by a competent person, normally known as the temporary works engineer
Before work starts
- Appoint a competent temporary works engineer to design the propping, shuttering and other support needed to prevent collapse of any excavation or building.
- Devise a construction sequence that includes when and how you will install any temporary works required…
When work starts
- Install the required temporary works and maintain them according to the temporary works engineer’'s instructions
- Support all sides of every excavation to prevent ground or building movement and collapse…”"
“" 1.7.1 Experience tells us that many projects have suffered from either a dearth of information - from client and designer (with the inevitable consequences) - or a surfeit of information transfer, with insufficient attention paid to considering what others really need. It is essential that the important messages do not get buried beneath irrelevances.
1.7.2 A designer is required to take all reasonable steps to provide information about the design to assist other duty holders in complying with their duties under CDM 2007, that is to identify and manage the remaining risks. There are several ways in which information may be transferred…
Is the project information you provide appropriate and targeted?
[There then follow examples of three categories of risk entitled ""Not likely to be obvious to a competent contractor or designer"" which talks about for instance ""less obvious risks such as interim stability"", ""Unusual"" risks and ""Difficult to manage"" risks; this concludes with a statement which says that: ""ultimately, the decision about what information to pass on is a matter of competent professional judgement. Designers are unlikely to be criticised if they have given considered thought to the matter, as outlined in this guidance.""]
1.12 What designers do not have to do
1.12.1 This is self explanatory. Of particular note is that designers do not have to: ‘'specify construction methods, except where the design assumes or requires a particular construction or erection sequence, or where a competent contractor might need such information’'..
1.12.2 Most designs assume a construction sequence; some require a specific sequence. It is important in all cases that this is clear to the contractor, and that the assumptions behind the erection phase are known, for example use of standard connection details, and means of attaining temporary stability…”"
Section 3
TEMPORARY WORKS
3.1 Introduction
3.1.1 This element of guidance has been provided for two reasons: firstly because temporary works are within the ambit of CDM 2007 as structures within their own right; and secondly because they are inextricably linked to, but distinctly different from, the permanent works.
3.1.2 Although the contractor is responsible for a safe system of work relating to temporary works, permanent works designers often have a major contributory role.
3.2 Permanent works design
3.2.1 The permanent works designer will need to be satisfied that the permanent works design allows for a reasonable safe system of work in respect of temporary works (having regard to hazard elimination and risk reduction to be implemented by the temporary works designer and subsequently the contractor).
3.2.2 Where the likely solution is an industry standard, that is based on codes of practice and established temporary systems, then there may be no need to take any further action. However, if the solution is not standard, or will result in risks which may not be obvious to the contractor, then this should be highlighted. Information should include details of the interaction with the permanent works, paying specific attention to interim instability issues…
3.3 Temporary works designer
3.3.1 The temporary works designer may be employed by the permanent works design organisation, principal contractor, contractor, supplier, manufacture, or be self-employed. Contractually, the temporary works designer may be remote from both the principal contractor and the permanent works designer. However, for the purposes of CDM 2007, the role is classified as a ‘'designer’' and this ‘'Guidance for designers’' is therefore relevant.
3.3.2 Typical shortfalls in temporary works design include:
- not providing lateral stability requirements and vertical load limitations amongst outputs…”"
“"125 Designers are required to avoid foreseeable risks ‘'so far as is reasonably practicable, taking due account of other relevant design considerations’'. The greater the risk, the greater the weight that must be given to eliminating or reducing it. Designers are not expected to consider or address risks which cannot be foreseen…However, designers must not produce designs that cannot be constructed, maintained, used or demolished in reasonable safety…
131 Designers must provide information that other project team members are likely to need to identify and manage the remaining risks. This should be project specific, and concentrate on significant risks which may not be obvious to those who use the design. For example, providing generic risk information about the prevention of falls is pointless, because competent contractors will already know what needs to be done, but if the design gives rise to a specific and unusual fall risk which may not be obvious to contractors, designers should provide information about this risk.
132 Designers also need to provide information about aspects of the design that could create significant risks during future construction work or maintenance. If in doubt about the level of information needed, the best way to find out is to ask those who will use it…""
Liability (AIMS) - Discussion
Causation
Quantum
Item
Amount claimed
Amount allowed and findings
1. Barnet Council Fees
£265
£265 - amount admitted
2. Planning Application Fee
£385
£385 - amount accepted
3. Demolish existing two-storey extension
£0
£0 - it was accepted that this was not required as it was sufficiently stable to remain.
4. Remove concrete and shoring left by Council
£18,230.88
£ 15,192 - This claim was broken down into four elements, breaking out of concrete (£2,240.40, disposal (£2,952), removal of shoring and earth work support (£10,000) and contingency (20%). I accept Mr Ellis
Item | Amount claimed | Amount allowed and findings |
1. Barnet Council Fees | £265 | £265 - amount admitted |
2. Planning Application Fee | £385 | £385 - amount accepted |
3. Demolish existing two-storey extension | £0 | £0 - it was accepted that this was not required as it was sufficiently stable to remain. |
4. Remove concrete and shoring left by Council | £18,230.88 | £ 15,192 - This claim was broken down into four elements, breaking out of concrete (£2,240.40, disposal (£2,952), removal of shoring and earth work support (£10,000) and contingency (20%). I accept Mr Ellis’' evidence on the first item, based as it was on a rate which he had obtained locally; the work would be complicated and difficult. Similar considerations apply to the second element. I accept Mr Ellis’' evidence on the £10,000 item; the photographs show that the removal of the shoring and support works will be complex and fraught with difficulty given that, particularly the party wall will need support maintained for it and there will therefore need to be a number of return trips. However, I disallow the contingency because the other amounts are sufficient and there is to be an overall contingency. |
5. Rebuilding costs | £105,000 | £105,000 - amount now accepted by both experts |
6. Works to extension of | £45,500 | £9,211.55 - This was broken down in Mr Ellis’' first report; in evidence there was substantial agreement on many items: roof, brickwork windows and M&E repairs, plastering, decorations, new flooring finishes work, work to single-storey extension, tying of external crack and reform missing section of floor plates (totalling £6,211.55). Counsel were agreed that works to the first-floor kitchen and bathroom should sensibly be left to be dealt with by indemnity declarations. The two remaining matters relating to the ground floor kitchen and bathroom were, on any account substantially to be reduced. I accept Mr Ellis’' evidence allowing £1,500 for the kitchen and £1,500 for the bathroom which will require repair and reinstatement not only for damage caused but to allow for deterioration. |
7. Reinstate landscaping and decking | £5,250 | £0 - experts agreed in their second joint statement on this. |
8. Provisional sums | £21,800 | £14,885- These were the sums included within the rebuilding costs, excluded from the agreed figure above. The experts agreed on figures for work to party walls and tie in works (£2,500 and £2,000). I accept Mr Ellis’' evidence that £3,000 will probably need to be spent on work to the existing foundations, which from the photographs are clearly seriously disrupted. I accept his evidence that work to the division wall costing £2,500 will be required. There are likely to be charges for service connections (gas, water and electricity) but consider that an allowance of £2,000 is reasonable. Due to the congestion on the site, it is likely that the pavement and the road outside will be damaged during the remedial work and a reasonable allowance for repairs would be £1,000. There should be no additional allowance for preliminaries which are covered within the rebuilding costs. Professional fees on these should be allowed at the rate of 14.5%. |
9. Contingency | 10% | £14,429 - I accept that it is reasonable to allow 10%; the works have not been designed in any real detail and there are known difficulties such as stability problems on the party wall. The contingency should be allowed on items 3 to 8 above (amount allowed £144,288.55). |
10. Professional fees |
14.5% | £23,014 - I preferred the evidence of Mr Ellis. There will have to be input from architect, engineer and quantity surveyor and there is bound to be extensive professional involvement in view not only due to what has happened but because there will need to be a close involvement particularly from the architect and engineer. |
House contents | £21,284 | £18,831 - Only 2 items are challenged. I accept Ms Hale’'s evidence that at least £12,000 of her clothing was lost and destroyed. No loss has been established in relation to the shed and contents (£2,453 claimed |
11. Alternative accommodation and additional expenses | £59,750 + £18,136 | £71,667 - Beltec’'s Counsel accepted that that this should be assessed on the cost of comparable alternative accommodation from November 2012 to November 2015 assessed at £1,800 pcm. In addition, there is acceptance of Items 26, 29 and 30 in the Additional Expenses. I agree that this is a reasonable approach. The Claimants’' assessment (totalling £77,916) seeks to claim all the costs related to the purchase of the Yarlington property without giving credit for the profit on its sale. |
12. General damages | £2,750 | £14,875 -- Counsel for Beltec has suggested a total of £12,500, based on 3 years at £2,000 p.a. for Ms Hale, £1,500 for Mr Goldswain and £500 each for the children during their lives to date. There is no claim as such for the children but the allowance should be based on 3.5 years allowing for the time realistically required before they can move back in to No. 4. The yearly rates should be £2,250 and £2,000 respectively for the Claimants. There very clearly has been very substantial distress and inconvenience in the past and there will be substantial inconvenience in the period leading up to the completion of the remedial works. |
Total | £287,754.55 |
’ evidence on the first item, based as it was on a rate which he had obtained locally; the work would be complicated and difficult. Similar considerations apply to the second element. I accept Mr Ellis’ evidence on the £10,000 item; the photographs show that the removal of the shoring and support works will be complex and fraught with difficulty given that, particularly the party wall will need support maintained for it and there will therefore need to be a number of return trips. However, I disallow the contingency because the other amounts are sufficient and there is to be an overall contingency.
5. Rebuilding costs
£105,000
£105,000 - amount now accepted by both experts
6. Works to extension of
£45,500
£9,211.55 - This was broken down in Mr Ellis’ first report; in evidence there was substantial agreement on many items: roof, brickwork windows and M&E repairs, plastering, decorations, new flooring finishes work, work to single-storey extension, tying of external crack and reform missing section of floor plates (totalling £6,211.55). Counsel were agreed that works to the first-floor kitchen and bathroom should sensibly be left to be dealt with by indemnity declarations. The two remaining matters relating to the ground floor kitchen and bathroom were, on any account substantially to be reduced. I accept Mr Ellis’ evidence allowing £1,500 for the kitchen and £1,500 for the bathroom which will require repair and reinstatement not only for damage caused but to allow for deterioration.
7. Reinstate landscaping and decking
£5,250
£0 - experts agreed in their second joint statement on this.
8. Provisional sums
£21,800
£14,885- These were the sums included within the rebuilding costs, excluded from the agreed figure above. The experts agreed on figures for work to party walls and tie in works (£2,500 and £2,000). I accept Mr Ellis’ evidence that £3,000 will probably need to be spent on work to the existing foundations, which from the photographs are clearly seriously disrupted. I accept his evidence that work to the division wall costing £2,500 will be required. There are likely to be charges for service connections (gas, water and electricity) but consider that an allowance of £2,000 is reasonable. Due to the congestion on the site, it is likely that the pavement and the road outside will be damaged during the remedial work and a reasonable allowance for repairs would be £1,000. There should be no additional allowance for preliminaries which are covered within the rebuilding costs. Professional fees on these should be allowed at the rate of 14.5%.
9. Contingency
10%
£14,429 - I accept that it is reasonable to allow 10%; the works have not been designed in any real detail and there are known difficulties such as stability problems on the party wall. The contingency should be allowed on items 3 to 8 above (amount allowed £144,288.55).
10. Professional fees
14.5%
£23,014 - I preferred the evidence of Mr Ellis. There will have to be input from architect, engineer and quantity surveyor and there is bound to be extensive professional involvement in view not only due to what has happened but because there will need to be a close involvement particularly from the architect and engineer.
House contents
£21,284
£18,831 - Only 2 items are challenged. I accept Ms Hale’s evidence that at least £12,000 of her clothing was lost and destroyed. No loss has been established in relation to the shed and contents (£2,453 claimed
11. Alternative accommodation and additional expenses
£59,750 + £18,136
£71,667 - Beltec’s Counsel accepted that that this should be assessed on the cost of comparable alternative accommodation from November 2012 to November 2015 assessed at £1,800 pcm. In addition, there is acceptance of Items 26, 29 and 30 in the Additional Expenses. I agree that this is a reasonable approach. The Claimants’ assessment (totalling £77,916) seeks to claim all the costs related to the purchase of the Yarlington property without giving credit for the profit on its sale.
12. General damages
£2,750
£14,875 -- Counsel for Beltec has suggested a total of £12,500, based on 3 years at £2,000 p.a. for Ms Hale, £1,500 for Mr Goldswain and £500 each for the children during their lives to date. There is no claim as such for the children but the allowance should be based on 3.5 years allowing for the time realistically required before they can move back in to No. 4. The yearly rates should be £2,250 and £2,000 respectively for the Claimants. There very clearly has been very substantial distress and inconvenience in the past and there will be substantial inconvenience in the period leading up to the completion of the remedial works.
Total
£287,754.55
Decision