QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Rolls Building, Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
____________________
VAN OORD UK LIMITED SICIM ROADBRIDGE LIMITED |
First Claimant Second Claimant |
|
- and - |
||
ALLSEAS UK LIMITED |
Defendant |
____________________
(instructed by K&L Gates) for the Claimants
Mr Simon Lofthouse QC and Mr Robert Clay
(instructed by Curtis Davis Garrard LLP) for the Defendant
Hearing date: 12 November 2015
____________________
Crown Copyright ©
The Honourable Mr Justice Coulson:
1. INTRODUCTION
(a) That AUK's offer of 13 January 2014 was a valid Part 36 offer, but it was a defendant's offer (which had the consequences set out in CPR r.36.17(3)), and was not a claimant's offer (which would have had the consequences set out in r.36.17(4));(b) That the appropriate rate for interest, in relation to both the judgment sum and costs, was 2.5% (in other words, 2% over base, a common, but not inevitable rate awarded in cases like this: see Fitzroy Robinson Ltd v Mentmore Towers Ltd [2009] EWHC 3365);
(c) That OSR was liable to pay AUK's costs;
(d) That AUK was entitled to have those costs assessed on an indemnity basis, save for the £1.3 million paid by AUK to Knowles Ltd, in respect of which I concluded that OSR should be permitted to argue recoverability, proportionality and reasonableness at the detailed assessment;
(e) That OSR must make an interim payment on account of costs to AUK in the sum of £1.3 million.
2. THE PART 36 OFFER
Subject to paragraph (7), where paragraph (1)(b) applies, the court must, unless it considers it unjust to do so, order that the claimant is entitled to—
(a) interest on the whole or part of any sum of money (excluding interest) awarded, at a rate not exceeding 10% above base rate for some or all of the period starting with the date on which the relevant period expired;
(b) costs (including any recoverable pre-action costs) on the indemnity basis from the date on which the relevant period expired;
(c) interest on those costs at a rate not exceeding 10% above base rate; and
(d) provided that the case has been decided and there has not been a previous order under this sub-paragraph, an additional amount, which shall not exceed £75,000, calculated by applying the prescribed percentage set out below to an amount which is—
(i) the sum awarded to the claimant by the court; or
(ii) where there is no monetary award, the sum awarded to the claimant by the court in respect of costs—
Amount awarded by the court | Prescribed percentage |
Up to £500,000 | 10% of the amount awarded |
Above £500,000 | 10% of the first £500,000 and (subject to the limit of £75,000) 5% of any amount above that figure. |
"(3) Subject to paragraphs (7) and (8), where paragraph (1)(a) applies, the court must, unless it considers it unjust to do so, order that the defendant is entitled to—
(a) costs (including any recoverable pre-action costs) from the date on which the relevant period expired;
(b) and interest on those costs."
"This letter is intended to have the consequences of a claimant's offer to settle in accordance with Part 36 of the Civil Procedure Rules…
We should point out that you will face potentially adverse costs consequences in the event that you choose not to accept the proposal set out in this letter and any judgment subsequently awarded is at least as advantageous to our client as the offer set out in this letter. In these circumstances our client will seek:
(1) his costs on the indemnity basis with interest at 10% above base rate on those costs; and
(2) interest on his damages at 10% above base rate,
from the date on which the Relevant Period expired."
"Without prejudice save as to costs
THE MEMBERS OF A JOINT VENTURE BETWEEN VAN OORD UK LTD. AND SICIM ROADBRIDGE LTD. (OSR) V ALLSEAS UK LTD. (AUK) Offer to settle under part 36
We refer to Contract no. 400970/AUK/LFL/001 for the Laggan Tormore Development and the Claims relating to WP10 Onshore Works East made under the LETTER OF CLAIM reference OSR/LPU/248 dated 29th August 2013.
Although OSR's claim has serious deficiencies, AUK is mindful that under the Civil Procedure Rules (CPR(s)) litigants are expected to try to resolve their disputes whenever possible. AUK therefore makes the following offer to settle under Part 36 (the "Offer").
This Offer is intended to have the consequences set out in Part 36 of the CPRs. In particular, if the Offer is accepted, AUK will be liable for OSR's costs up to the date of notice of acceptance in accordance with CPR 36.10 for a maximum period of 21 days ("the relevant period").
Terms of the Offer
AUK is willing to settle the whole of the Claims referred to above, which for the avoidance of doubt is all matters described in OSR's Letter of Claim reference OSR/LPU/248 dated 29 August 2013 including OSR's Consolidated Claim dated 5 December 2012 and including all subsequent Addenda numbered 1 to 4 issued in January 2013 and February 2013 and all other submissions relating to OSR Change Order Requests referenced 058 (Parts 1 and 2), 066 (withdrawn by OSR), 068, 103 and 104 on the following terms:
AUK to pay OSR within 14 days of acceptance of the Offer, the sum of £3,800,000.00 gross including interest ("the settlement sum") less amounts already paid on account for these Claims. The settlement sum will be in full and final settlement of all claims which OSR has or may have against AUK in this matter. For the avoidance of any doubt the amounts that have already been paid on account are:-
Gross Amount Certified and Paid (in GBP) | |
COR 058 Part 1 (was original COR 058) | 2,850,000.00 |
COR 058 Part 2 (was original COR 066) | 558,839.00 |
COR 068 | 132,000.00 |
TOTAL | 3,540,839.00 |
The amount that will be paid within 14 days of acceptance of the Offer, which is the balance between the settlement sum and amounts already paid is £259,161.00.
This Offer takes account of any counterclaim AUK may have in relation to matters addressed in the Claims.
The settlement sum does not include costs and, as mentioned above, if the Offer is accepted, AUK will be liable for OSR's costs up to the date of notice of acceptance in accordance with CPR 36.10 for a maximum period of 21 days ("the relevant period").
Failure to accept this offer
If OSR does not accept the Offer, and subsequently commences proceedings in relation to this matter, and fails to do better than the Offer at trial, AUK intends to rely on CPR 36.14. This means for the avoidance of any doubt, that AUK will be seeking an order that OSR pays AUK its costs from the date when the relevant period expires and interest on those costs. In the event that OSR chooses to accept this offer prior to the commencement of proceedings, this offer is made on the basis that costs provisions of Part 36 and Part 44 shall apply.
Although AUK have not been formally notified that Mr Stimpson of Keating Chambers has been instructed for the purpose of proceedings, it was indicated during the meeting that this would occur and therefore this Offer is also copied to Mr Stimpson.
AUK understands that you are in possession of all necessary information and documents to be able to consider this Offer. If that is not correct, or if you think that this Offer is in any way non-compliant with the requirements of Part 36 of the CPRs, please notify us by return."
3. BASIS OF ASSESSMENT
"16…
(a) Indemnity costs are appropriate only where the conduct of a paying party is unreasonable "to a high degree. 'Unreasonable' in this context does not mean merely wrong or misguided in hindsight": see Simon Brown LJ (as he then was) in Kiam v MGN Ltd [2002] 1 WLR 2810.
(b) The court must therefore decide whether there is something in the conduct of the action, or the circumstances of the case in general, which takes it out of the norm in a way which justifies an order for indemnity costs: see Waller LJ in Excelsior Commercial and Industrial Holdings Ltd v Salisbury Hammer Aspden and Johnson [2002] EWCA (Civ) 879.
(c) The pursuit of a weak claim will not usually, on its own, justify an order for indemnity costs, provided that the claim was at least arguable. But the pursuit of a hopeless claim (or a claim which the party pursuing it should have realised was hopeless) may well lead to such an order: see, for example, Wates Construction Ltd v HGP Greentree Alchurch Evans Ltd [2006] BLR 45.
(d) If a claimant casts its claim disproportionately wide, and requires the defendant to meet such a claim, there was no injustice in denying the claimant the benefit of an assessment on a proportionate basis given that, in such circumstances, the claimant had forfeited its rights to the benefit of the doubt on reasonableness: see Digicel (St Lucia) Ltd v Cable and Wireless PLC [2010] EWHC 888 (Ch).
17. These principles have recently been restated in the judgment of Gloster J (as she then was) in Euroption Strategic Fund Ltd v Skandinaviska Enskilda Banken AB [2012] EWHC 749 (Comm)."
4. DISPROPORTIONATE COSTS
(a) The costs attributable to Knowles Ltd, the claims consultants who acted on behalf of AUK;(b) The costs of the court bundling exercise;
(c) The overall proportionality of AUK's costs.
I deal with each of those three points briefly in turn.
(i) The Costs of Knowles Ltd
"I regard it as fairly self-evident that it would be more economical, in terms of both time and money, for NAP's solicitors to take advantage of HCC's already acquired knowledge of the documents and the issues in the adjudication, rather than read themselves into the documents from scratch. HCC will (or should) have had the facts at their fingertips and been familiar with the documentation produced in the adjudication, as well as being broadly aware of what other documents might be in the possession of NAP."
(ii) The Bundling
(iii) Proportionality Generally
5. INTERIM PAYMENT ON ACCOUNT OF COSTS