QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
Seele Middle East FZE |
Claimant |
|
- and - |
||
Drake & Scull International SA CO |
Defendant |
____________________
Richard Harding QC (instructed by Lawrence Graham LLP) for the Defendant
Hearing date: 23 January 2014
____________________
Crown Copyright ©
Mr Justice Ramsey :
Introduction
Background
"Your 'excuses' for not leaving and subsequently refusing to return to work have no foundation whatsoever and should you fail to return and recommence works in earnest forthwith it will be taken that you have abandoned the contract. DSI secured your offices and storage facilities after abandonment of site as protective measures until further notice."
"Further to our letter ref '1297' dated 27th November 2013 giving Notice pursuant to clause 32.3 of the subcontract conditions requiring you to provide a fully detailed schedule within 14 days of that letter clearly showing how you will remedy the substantial and material breach of contract and following your abandonment of the site herewith suspend all your performance under your subcontract until such time as you have complied with the foregoing request, all in strict accordance with the aforementioned clause.
Be advised you will not be allowed to return to the worksite until you have properly fulfilled your obligations as required above."
These proceedings
"Production Drawings subsequent to achieving suitable status approval, including but not limited to: cutting, machining and assembly drawings, schedules for glass and bought-in materials, laydown drawings for site materials."
"SAUDI ARAMCO shall own any new and unique designs initially and specifically created or invented by VENDOR or its Subcontractors or Suppliers for the FAÇADE and paid for under this Order. As Owner, SAUDI ARAMCO shall have exclusive and unrestricted right to possess, use and dispose of such drawings."
"The Claimant's internal proprietary installation plan, the Claimants bespoke installation 3D model, cutting, machining and assembly drawings and layout drawings or site materials."
"The Defendant whether by itself its servants or agents otherwise be restrained from making any use of the documents in the Claimants site office, from removing and documents from the Claimant's site office and from disposing of or parting with in any way documents in the Claimant's site office."