(Formerly HT-14-372) |
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Rolls Building, 7 Rolls Buildings London EC4A 1NL |
||
B e f o r e :
____________________
Imtech Inviron Limited |
Claimant |
|
- and - |
||
Loppingdale Plant Limited |
Defendant |
____________________
Richard Bradley Esq (instructed by CE Law) for the Defendant
Hearing dates: 19th November 2014
____________________
Crown Copyright ©
Mr. Justice Edwards-Stuart:
Introduction
The issues
i) by the terms of the contract the adjudicator was to be one of three named persons, which did not include this adjudicator, Mr. Ben Sareen, and in default of any of the named persons being willing and able to act, the adjudicator was to be nominated by the Institution of Civil Engineers; orii) the adjudicator purported to adjudicate different disputes arising under different contracts without the consent of all the parties contrary to paragraph 8(2) of the Scheme for Construction Contracts.
The contractual structure
The Framework Agreement
"... This Agreement and all Task Orders awarded under it shall be deemed to have been made in England in accordance with English Law and shall be construed and interpreted in accordance with English Law and subject to the exclusive jurisdiction of the English Courts."
"100.1 (1) A dispute arising under or in connection with this contract is referred to and decided by the Adjudicator. A Party may refer the dispute to the Adjudicator at any time.
100.2 (1) The Parties appoint the Adjudicator under the NEC Adjudicator's Contract current at the starting date.
…
100.4 (1) A Party does not refer any dispute under or in connection with this contract to the tribunal unless it has first been decided by the Adjudicator in accordance with this contract."
The Terms and Conditions of the Subcontract (September 2012 version)
"1.1 These Terms and Conditions together with the Framework Agreement attached to these Terms and Conditions ('the Framework Agreement') together with the Purchase Order to be issued by LPL to the contractor for each sub-contract and the Task Order to be issued to LPL and a copy provided to the Subcontractor for each subcontract ('the Task Order') set out all the rights and obligations of the parties each to the other and no other terms or conditions shall be implied save to the extent that such terms and conditions are implied by statute save as may be agreed by the parties in writing.
…
1.3 The subcontract Works are executed as part of work to be carried out by LPL for its Customer under the Principal Contract as set out in the Framework Agreement and the Task Order (together 'the Principal Contract'). The Subcontractor shall be deemed to have read the Principal Contract and to be fully aware of the obligations, risks and liabilities assumed by LPL under them. The Subcontractor shall perform and assume, as part of its obligations under this contract, LPL's obligations, liabilities and risks contained within the Principal Contract that relate to the carrying out of the Task Order and/or Purchase Order as if they were expressly referred to in the subcontract as obligations, liabilities and risks of the subcontractor, all things being equal …. Schedule 1 is a list of the relevant clauses under the Principal Contract as a summary but this is provided entirely without prejudice to the Subcontractor's liability under this clause.
1.4 In the event of conflict between the terms and conditions of the Principal Contract and these Terms and Conditions the former shall take precedence save in relation to payment provisions set out in clause 1.16 of these Terms and Conditions which will always prevail. The order of priority without prejudice to this stated exception is
1.4.1 The Task Order
1.4.2 The Framework Agreement
(together "the Principal Contract")
1.4.3 These Terms and Conditions
1.4.4 The Purchase Order"
"1.23 The provisions of the Principal Contract in respect of liability, insurance and Indemnification in respect of death or injury to persons and loss or damage to property shall apply between LPL and the Subcontractor under this contract as though they were respectively the Customer and LPL.
…
1.25 The contract shall be governed by English Law and the Subcontractor consents to the exclusive jurisdiction of the English Courts in matters regarding the Subcontract except to the extent that LPL invokes the jurisdiction of the Courts of any other country."
i) In clause 1.3 Inviron's obligations were to comply with LPL's obligations and liabilities that related"… to the carrying out of the Task Order and/or Purchase Order as if they were expressly referred to in the sub-contract as obligations, liabilities and risks of the Subcontractor, all other things being equal".This, submitted Mr. Winser, concerned what he described as primary obligations relating to the work to be carried out and how it was to be done rather than secondary obligations, such as those relating to insurance and indemnities.ii) By contrast, clause 1.23 made specific provision for compliance by Inviron with certain secondary obligations, namely liability, insurance and indemnification in respect of death or injury to persons and loss or damage to property. Mr. Winser's point here was that this clause would not have been necessary if these obligations were covered by clause 1.3.
iii) Although Schedule 1 was said not to be an exhaustive list, Mr. Winser noted that all the obligations identified were what he described as primary obligations, and that this was therefore consistent with his submission in relation to clause 1.3.
iv) Clause 1.25 was different to the provision relating to jurisdiction in the Framework Agreement, and this cannot have been a mistake. This shows, submitted Mr. Winser, that it cannot have been the intention of the parties that the jurisdiction clause in the Framework Agreement was to be carried over into the September Conditions.
"46. Where parties are in dispute as to what they have agreed the task of the Court is to determine from the communications that passed between them in the context in which those communications were made what reasonable persons in their position would regard them as having intended to agree. Where those parties agree the essential terms of a contract and also that their contract shall include the terms of a previous contract or contracts between them the Court may have to determine which provisions of which contract(s) they meant to incorporate. If the Court is able to decide what those provisions were, it should not, in my judgment, be astute to impose any special rules which limit the ability of the parties validly to agree what, on ordinary principles of construction, they would be taken to have agreed.
47. If terms which are said to have been agreed are particularly onerous or restrictive of rights that would otherwise arise, it may be necessary, if they are to be enforceable, for the party seeking to rely upon them to show that notice of their existence appropriate to their content was given to the party potentially affected by them. Where the term in question ('the offending term') was included in a previous contract, but without such notice being given, it may be that general words incorporating terms of the previous contract (including the offending term) in a later contract are insufficient to incorporate the offending term. But an arbitration clause such as the present is not usually some form of onerous term to which special attention must be drawn: see: Streford v Football Association [2007] EWCA Civ 238. The fact that such an arbitration clause ousts the jurisdiction of the court does not, in a single contract case, mean that it requires some extraordinary method of incorporation.
48. I accept that, if the terms of an earlier contract or contracts between the parties are said to have been incorporated it is necessary for it to be clear which terms those were. But, like Langley J, I do not regard this to be the position only if the terms said to be incorporated include an arbitration or jurisdiction clause. Whenever some terms other than those set out in the incorporating document are said to be incorporated it is necessary to be clear what those terms are. Since arbitration clauses are not terms which regulate the parties' substantive rights and obligations under the contract but are terms dealing with the resolution of disputes relating to those rights and obligations it is also necessary to be clear that the parties did intend to incorporate such a clause. But, if a contract between A and B incorporates all the terms of a previous contract between them other than the terms newly agreed in the later contract, there should be no lack of clarity in respect of what is to be incorporated.
49. There is a particular need to be clear that the parties intended to incorporate the arbitration clause when the incorporation relied on is the incorporation of the terms of a contract made between different parties, even if one of them is a party to the contract in suit. In such a case it may not be evident that the parties intended not only to incorporate the substantive provisions of the other contract but also provisions as to the resolution of disputes between different parties, particularly if a degree of verbal manipulation is needed for the incorporated arbitration clause to work. These considerations do not, however, apply to a single contract case."
(Mr. Winser's emphasis)
"4. … The factual matrix is key to understanding what the parties must have intended by the words they used. But it far from follows that the need to know what that matrix was requires a full trial with discovery, evidence and cross-examination of witnesses. If there is no actual conflict of evidence on a relevant point of background matrix, it is only when there really are reasonable grounds for supposing that a fuller investigation of the facts as to the background might make a difference to construction that the court should decline to construe the contract on a summary judgment (including strike out) application.
5. The court should not be over-astute to decline to deal with the construction of a contract summarily merely on the basis that something relevant to the matrix might turn up if there were a full trial. Most disputes as to 'pure' construction of a contract will be suitable for summary determination because the factual matrix necessary for its construction will itself be determinable on that application."
Did the adjudicator decide more than one dispute?
"The dispute that has arisen between the Parties, and which this Notice relates and is confined to, is the failure of LPL to pay the 'notified sum' due to Inviron in respect of Inviron's Application Number 6."
Conclusion