QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
NATS (SERVICES) LIMITED |
Claimant |
|
- and - |
||
GATWICK AIRPORT LIMITED |
Defendant |
____________________
Michael Bowsher QC, Rob Williams and Daisy Mackersie (instructed by Freshfield Bruckhaus Deringer) for the Defendant
Philip Moser QC (instructed by Simmons & Simmons LLP) for an Interested Party (DFS Deutsche Flugsicherung GMBH)
Hearing dates: 24 October and 3 November 2014
____________________
Crown Copyright ©
Mr Justice Akenhead:
Introduction
"GAL published its intention to carry out the Procurement in the Official Journal of the European Union ("OJEU") on 2 October 2013. The tender was divided into two lots. Lot 1 related to air navigation services, including provision of staff for those services and Lot 2 related to maintenance and repair of equipment. The Procurement proceeded by way of Invitation to Tender ("ITT"), a negotiation phase and then the submission of best and final offers ("BAFO").
6. NATS submitted its BAFO for Lots 1 and 2 on 2 June 2014. By letter dated 18 July 2014 GAL notified NATS that its tender had been unsuccessful and that DFS had been successful. In the correspondence that followed NATS sought further information and GAL contended that it did not come within the Regulations.
7. On 18 August 2014 GAL wrote to NATS to give them 7 days' notice that GAL intended to enter into the contract with DFS. NATS therefore issued proceedings and an application for a declaration that there was an automatic suspension under Regulation 45G of the Regulations, alternatively an interim injunction. Particulars of Claim were served on 28 August 2014. On 3 September 2014 NATS issued an application for disclosure. Also on 3 September 2014 GAL issued an Application seeking to lift any automatic suspension, alternatively if the suspension remained in place, an undertaking in damages by NATS.
8. After a hearing relating to disclosure on 5 September 2014 the application for disclosure was adjourned until early October 2014. The other applications were then heard on 10 and 12 September 2014."
Strike-out and Re-amendment
"(f) Further, the Claimant avers that the quality scores awarded to it were manifestly wrong. The Defendant has admitted by letter dated 30 July 2014 that the Claimant's score should have been increased by a maximum of 0.9%. The Claimant avers that, even taking this into account, its score remains too low in manifest error, as more fully particularised in Schedule 1 hereto. Further, the Defendant has failed to provide any adequate justification for the scores awarded to DFS and the Claimant avers (on the basis of the limited information available to it at this stage) that the scores awarded to DFS the for quality are also likely to have been manifestly wrong. Without prejudice to the generality of the foregoing, on the basis of the evidence served by the Defendant for a hearing on 10 September 2014, the Claimant avers that DFS was over-scored for its Transition Plan (for which it obtain full marks the both Lots 1 and 2) in circumstances in which (i) it was apparently unable to transition in the required 12 month period; (iii) it needed 12-15 months to transition; (iii) it could not offer a seamless transition whilst maintaining capacity;and/or(iv) it envisaged (as a conservative estimate) a likely capacity reduction of 5% over a 2-4 week period after the end of the transition period and/or, as is apparent from the documents and/or information disclosed by the Defendant on 15 and/or 20 October 2014, (v) DFS' transition plan(s) and/or proposals were considered by the Defendant to be insufficiently robust and/or required to be "de-risked" and/or "deferred" and/or otherwise modified and/or revised in the period after "normalisation" of the technical scores and after submission of BAFOs in order to be acceptable to the Defendant. The Claimant reserves its right further to particularise this allegation on disclosure of relevant documentation.
(h) Further, it is apparent from the documents and/or information disclosed by the Defendant on 15 and/or 20 October 2014 that the decision to award the contract to DFS was not made and/or was not made solely on the basis of the award criteria in the tender documents, but rather took into consideration other unlawful factors, thereby breaching the principles of equal treatment, transparency and/or non-discrimination (as is apparent from papers prepared for the board meetings on 19 June 2014 and 25 June 2014 and 16 July 2014 and the BAFO tender assessment report). The best particulars the Claimant can give are the factors identified in those documents, namely:
(i) undisclosed criteria and/or sub-criteria including capability, working relationship, business, international business, M port operations, unspecified material available in the public domain, creation of a competitive market for the future, transparency, asset management, total airfields operations, experience of the Defendant and/or overall impression is not directly linked to the scoring matrix (see page 3 of 19 June 2014 paper, pages 5, 6, 8, 11, 13-19 of 25 June 2014 paper, pages 2, 3, 5, 7, 14-20 of 16 July 2014 paper, pages 6, 7 of the BAFO tender assessment report).
(ii) selection criteria (which cannot lawfully be used at award stage), including unspecified "material supplied by both parties as part of the Pre-Qualification Questionnaire (PQQ)" (see page 13 of 25 June 2014 paper, page 14 of 16 July 2014 paper)."
17. If, which is not accepted, the Defendant is correct that DFS would have won Lot 1 individually assessed at the BAFO stage, on the basis of information disclosed by the Defendant on 15 and 20 October 2014 in relation to DFS' price for its non-compliant bid, it is averred that DFS' tender for Lot 1 and, in consequence its final combined price for both Lots wasthe Claimant is concerned that the price submitted by DFS for Lot 1 may have beenabnormally low. In particular, it is averred that (a) the Claimant's price was *; (b) the Claimant, as incumbent, was very well aware of the cost of carrying out the services; (c) *(d) however, it appears that DFS' Lot 1 price was some X%* below the Claimant's price and consequently that its finally adjusted overall price was some Y%* below the Claimant's price; (e) this was notwithstanding that (1) DFS' rights, but not the Claimant's, needed to include the transition and (2) DFS apparently agreed the Defendant's terms and conditions including unlimited liability. The Defendant has denied in its Defence that DFS' price was abnormally low but does not explain whether it carried out any assessment pursuant to Regulation 30(6). In the circumstances, the Claimant avers that the Defendant failed (in breach of the Regulations, including the principles of equal treatment, transparency and non-discrimination and/or in manifest error) to carry out an investigation adequately or at all into whether the bid was abnormally low and/or to reject it having carried out such an investigation. It is averred that the result of such an investigation should have been a determination that the price was abnormally low and that the bid should have been rejected.The Claimant is not currently aware of the breakdown that DFS' price as this information has not been disclosed by the Defendant. The Claimant is therefore unable at this stage to plead any particulars of breach by the Defendant, but preserves its right to do so once proper disclosure of all relevant documentation has been provided.
"The Defendant awarded a score of 5 on the basis that copies of report audits were not provided. That complaint is misconceived. The full audit reports sought by the Defendant were in the data room during the procurement. Further, the Defendant could and should have asked for these documents."
"36. The parties would have known that DWF were pressing for an explanation of the "Scottish anomaly" and had not received it. The pleading repeatedly makes it clear that until they have that explanation DWF is working in the dark, see for instance paragraphs 23, 25, 28 and 34. The only "hard" facts which DWF have and refer to are the anomaly itself. That was called a "manifest error."
37. In those circumstances I think the reader would take it that the real complaint was about whatever caused that error. It was in effect saying "here is the error. Something has gone wrong. My complaint is that that something is a breach of the duties owed to me." In the course of argument I suggested an analogy with the principles of res ipsa loquitur, an analogy which I think holds good. If, for instance, you get your car serviced and on the way back from the garage the steering fails, the inference is that the garage was negligent somehow. You only have to plead the fact of servicing and the accident – you do not have to explain how and in what way the steering failed.
38. The "right to reserve" in para. 32 would be understood by the reasonable reader in the sense that DWF were saying that if or when the reasons for the anomaly were disclosed, they would be relied upon too. They were not saying that they were not relying on those reasons now as part of the thrust of their case.
39. I am confirmed in my way of reading the pleading by the fact that it is exactly how the IS understood it. The Defence shows that the IS fully understood that the complaint was that something had gone wrong in the tender process as evidenced by the anomaly. It positively set out to rebut such a complaint, to explain and justify it.
40. Thus paragraph 14 of the Defence (I do not quote it here for it is quite long) specifically seeks to explain the alleged anomaly and denies that it is "inexplicable as alleged or at all." Moreover the Defence specifically pleads to the "reserve the right" paragraph 32 saying:
"26. As to paragraph 32: (i) it is admitted that the claimant's scores in relation to its tender for a Framework Agreement covering England and Wales were moderated downwards following the claimant's presentation on 10 December 2013…. It is denied that the claimant's scores were moderated downwards at any other stage;
(ii) it is denied that such downward moderation was made by reference to matters and/or criteria not apparent from the ITT and/or other tender information. In particular it is denied that the claimant's scores were moderated downwards because certain of the claimant's partners are the subject of investigation by the Insolvency Service."
41. This shows that the IS read paragraph 32 as containing a present averment; it was not just a pointless reference to a possible future amendment.
43. In the result I think the Judge was in error to conclude that a new cause of action was being alleged. What was being done was to move from a case based on inference from the anomaly to one based on explanation for it. It remained the same case."
"The allegation that the DFS' price may have been abnormally low is unparticularised and embarrassing and is in any event denied. GAL cannot plead further."
This is not acknowledging that there was an identifiable or identified cause of action which needed to be responded to. In my view, the current pleading bears no relationship to that which was under review in the DWF case.
(a) There is no properly pleaded basis for this claim.
(b) The case is suggested to be wholly inconsistent with facts which have been set out in a Confidential Annex.
(c) The claim is bad in law.
(d) The claim is brought late and out of time.
(e) The introduction of this claim now risks the introduction of requests for substantial fresh disclosure which would be particularly onerous in nature and would imperil the trial date or the prospects of a fair trial.
"(6) If an offer for a contract is abnormally low the utility may reject that offer but only if it has—
(a) requested in writing an explanation of the offer or of those parts which it considers contribute to the offer being abnormally low;
(b) taken account of the evidence provided in response to a request in writing; and
(c) subsequently verified the offer or parts of the offer being abnormally low with the economic operator."
(7) Where a utility requests an explanation in accordance with paragraph (6), the information requested may, in particular, include—
(a) the economics of the method of construction, the manufacturing process or the services provided;
(b) the technical solutions suggested by the economic operator or the exceptionally favourable conditions available to the economic operator for the execution of the work or works, for the supply of goods or for the provision of the services;
(c) the originality of the work, works, goods or services proposed by the economic operator;
(d) compliance with the provisions relating to employment protection and working conditions in force at the place where the contract is to be performed; or
(e) the possibility of the economic operator obtaining State aid.
(8) Where a utility establishes that a tender is abnormally low because the economic operator has obtained State aid, the offer may be rejected on that ground alone only after—
(a) consultation with the economic operator; and
(b) the economic operator is unable to prove within a reasonable time limit fixed by the utility, that the aid has been granted in a way which is compatible with the EC Treaty.
(9) Where a utility rejects an abnormally low offer in accordance with paragraph (8), it shall send a report justifying the rejection to the Minister for onward transmission to the Commission."
"If for a given contract, tenders are obviously abnormally low in relation to the transaction, the authorities awarding contracts shall examine the details of the tenders before deciding to whom it will award a contract. The result of this examination shall be taken into account.
For this purpose it shall request the tenderer to furnish the necessary explanations and, where appropriate, it shall indicate which parts it finds unacceptable.
If the documents relating to the contract provide for its award at the lowest price tendered, the authority awarding contracts must justify to the Advisory Committee set up by the Council Decision of 26 July 1971 the rejection of tenders which it considers to be too low."
The judgement of the European Court goes on:
"20…it should be observed that it was in order to enable tenderers submitting exceptionally low tenders to demonstrate that those tenders are genuine ones that the Council, in Article 29(5) of Directive 71/305, laid down a precise, detailed procedure for the examination of tenders which appear to be abnormally low.
26 The examination procedure must be applied whenever the awarding authority is contemplating the elimination of tenders because they are abnormally low in relation to the transaction. Consequently, whatever the threshold for the commencement of that procedure may be, tenderers can be sure that they will not be disqualified from the award of the contract without first having the opportunity of furnishing explanations regarding the genuine nature of their tenders".
This points very strongly towards the underlying Directive relating to the contracting authority's right to eliminate abnormally low tenderers and, as importantly, to the allegedly abnormally low tenderer being given the opportunity to explain why its tender is as low as it is. This latter aspect is simply, on analysis, a manifestation of the fairness obligation required of the whole procurement process.
"30. 4. If, for a given contract, tenders appear to be abnormally low in relation to the works, the contracting authority shall, before it may reject those tenders, request, in writing, details of the constituent elements of the tender which it considers relevant and shall verify those constituent elements taking into account the explanations received.
The contracting authority may take into consideration explanations which are justified on objective grounds including the economy of the construction method, or the technical solution chosen, or of the exceptionally favourable conditions available to the tenderer for the execution of the work, or the originality of the work proposed by the tenderer.
If the documents relating to the contract provides for its award at the lowest price tendered, the contracting authority must communicate to the Commission the rejection of tenders which it considers to be too low."
In the actual procurement in that case, the invitation to tender laid down "abnormally low" thresholds which Lombardini and Mantovani (these being two separate cases) exceeded. Important observations of court were as follows:
"34. The Directive nevertheless aims…to abolish restrictions on freedom of establishment and on the freedom to provide services in respect of public works contracts in order to whether that such contracts to genuine competition between entrepreneurs in the Member States…
35. The primary aim of the Directive is to open up public works contracts to competition. It is exposure to Community competition in accordance with the procedures provided for by the Directive which avoids the risk of the public authorities indulging in favouritism…
36. The coordination at Community level of procedures for the award of public works contracts is that essentially aimed at protecting the interests of traders established in a Member State who wish to offer goods or services to contracting authorities established in Member State and, to that end, to avoid both the risk of preference being given to national tenderer for applicants whenever a contract is awarded by the contracting authorities and the possibility that the body governed by public law may choose to be guided by considerations other than economic ones…
44. In paragraph 17 of that judgement [Case 76/81 Transporoute [1982] ECR 417], The Court held that the contracting authority may not in any circumstances reject an abnormally low tender without even seeking an explanation from the tenderer, since the aim of Article 29 (5) of Directive 71/305, which is to protect tenderers against arbitrariness on the part of the authority awarding contracts, could not be achieved if it were left to that authority to judge whether or not it was appropriate to seek explanations.
45. Similarly, the Court has consistently held that Article 29 (5)… prohibits Member States from introducing provisions which require the automatic exclusion from procedures for the award of public works contracts of certain tenders determined according to a mathematical criterion, instead of obliging the awarding authority to apply the examination procedure laid down in the Directive [Fratelli referred to]…
47 According to the Court, a mathematical criterion in accordance with which tenders which exceeded the basic value for the price of the work by a percentage more than 10 points below the average percentage by which the tenders admitted exceeded that amount would be considered anomalous and consequently eliminated, deprived tenderers who have submitted particularly low tenders of the opportunity to demonstrate that those tenders are genuine ones, so that application of such a criterion is contrary to the aim of Directives 71/35, namely to promote the development of effective competition in the field of public contracts is [Fratelli referred to]…
50. Since the requirements laid down by both the initial and the amended version of Article 29 (5) of Directive 71/305 are in substance is identical to those imposed by Article 30 (4) of the Directive, the foregoing considerations apply equally in relation to the interpretation of the latter provision.
51. In consequence, Article 30 (4) of the Directive necessarily presupposes the application of an inter partes procedure of for examining tenders regarded by the contracting authority as abnormally low, placing the latter under an obligation, after it has inspected all the tenders and before awarding the contract, first asked in writing the details of the elements in the tender suspected of anomaly which gave rise to doubts on its path in the particular case and then to assess their tender in the light of the explanations provided by the tenderer concerned in response to that request…
53. It is essential that each tenderer suspected of submitting an abnormally low tender should have the opportunity effectively to state his point of view in that respect, giving him the opportunity to supply all explanations as to the various elements of his tender at a time - necessarily after the opening of all the envelopes - when he is aware not only of the anomaly threshold applicable to the contract in question and of the fact that his tender has appeared abnormally low, but also of the precise points which have raised questions on the part of the contracting authority…
55. It is apparent from the very wording of that provision, drafted in imperative terms, that the contracting authority is under a duty, first, to identify suspect tenders, secondly to allow the undertakings concerned to demonstrate their genuineness by asking them to provide the details which it considers appropriate, thirdly to assess the merits of the explanations provided by the persons concerned, and, fourthly to take a decision is whether to admit or reject those tenders. It is therefore not possible to regard the requirements inherent in the inter partes nature of the procedure for examining abnormally low tenders, within the meaning of Article 30 (4) of the directive, as having been complied with unless all the steps thus described have been successfully accomplished…
67…it is undisputed that the Directive does not define the concept of an abnormally low and, a fortiori, does not determine the method of calculating an anomaly threshold. That is therefore a task for the individual Member States…"
"47. As a preliminary point, it should be recalled that the Commission enjoys a broad margin of assessment with regard to the factors to be taken into account for the purpose of deciding to award a contract following an invitation to tender, and that review by the Court is limited to checking compliance with the procedural rules and a duty to give reasons, the correctness of the facts found and that there is no manifest error of assessment or misuse of powers…
49…the contracting authority is obliged to allow the tenderer to clarify, or even explain, the characteristics of its tender before rejecting it, if it considers that a tender is abnormally low. The obligation to check the seriousness of a tender also arises where there are doubts beforehand as to its reliability, also bearing in mind that the main purpose of that article is to enable a tenderer not to be excluded from the procedure without having had an opportunity to explain the terms of its tender which appears abnormally low.
50….only when any tender is considered abnormally low…is the evaluation committee required to request details of the constituent elements of the tender which it considers relevant before, where appropriate, rejecting it… consequently, given that the evaluation committee had no intention, in this case, of rejecting WT's tender, since their tender did not appear to be abnormally low, Article 139 of the detailed implementing rules proved to be irrelevant."
"24. In those circumstances, the Court must understand the questions referred to it, taken as a whole, as seeking to ascertain to what extent contracting authorities, when they take the view, in a restricted public procurement procedure, that the tender submitted by a tenderer is abnormally low or imprecise or does not meet the technical requirements of the tender specifications, may or must seek clarification from the tenderer concerned, having regard to Articles 2 and 55 of Directive 2004/18…
26. It is in the light of those considerations that the questions referred to the Court must be answered, by examining in turn the situation in which the contracting authority considers the tender to be abnormally low and that in which it takes the view that tender is imprecise or does not meet the technical requirements of the tender specifications.
27. It must be borne in mind that, under art. 55 of Directive 2004/18, if, for a given contract, tenders appear to be abnormally low in relation to the goods, works or services, the contracting authority must, before it may reject those tenders, "request in writing details of the constituent elements of the tender which it considers relevant".
28. It follows from these provisions, which are stated in a mandatory manner, that the EU legislature intended to require the awarding authority to examine the details of tenders which are abnormally low, and for that purpose obliges it to request the tenderer to furnish the necessary explanations to prove that those tenders are genuine (see, to that effect, [Lombardini]…
29. Accordingly, the existence of a proper exchange of views, at an appropriate time in the procedure for examining tenders, between the contracting authority and the tenderer, to enable the latter to demonstrate that it tenderer is genuine, constitutes a fundamental requirement of Directive 2004/18, in order to prevent the contracting authority from acting in an arbitrary manner and to ensure healthy competition between undertakings [see, to that effect, [Lombardini]…
"153. Thus, the wording of the Directive is somewhat different from that of Regulation 30(6) in the sense that it states that the contracting authority "shall" do certain things before rejecting a tender which appears to be abnormally low, whereas Regulation 30(6) states that the authority may reject a tender which is abnormally low but only if it has done certain things. This difference of wording was one of the matters which led Arnold J in the recent case of Morrison Facilities Services Limited v Norwich City Council [2010] EWHC 487 (Ch), to conclude that it was seriously arguable (for the purposes of granting an interim injunction under Regulation 47) that the relevant authority owed a duty, when it suspected that there has been an abnormally low tender, to investigate that tender.
154. In reaching that conclusion, Arnold J also relied upon the decision of the European Court of First Instance (now the General Court) in Renco SpA v Council of the European Union [2003] ECR II-171, where at paragraphs 75 and 76 the Court stated:
"75 The Court finds that the applicant cannot criticise the Council for checking many of the prices quoted in its tender. It is apparent from the wording of Article 30(4) of Directive 93/37 [the predecessor of the current Directive] that the Council is under a duty, first, to identify suspect tenders, secondly to allow the undertakings concerned to demonstrate their genuineness by asking them to provide the details which it considers appropriate, thirdly to assess the merits of the explanations provided by the persons concerned, and, fourthly, to take a decision as to whether to admit or reject those tenders (Joined Cases C-285/99 and C-286/99 Lombardini and Mantovani [2001] ECR I-9233, paragraph 55). The Court notes, for example, that the Council, in its defence, stated that it had questioned the applicant about very many of the abnormally low prices, namely the price of 319 items in the summary out of a total of 1 020. It also asked the applicant for clarification regarding a series of very blatant anomalies and particularly about the price of the doors, which are the same for single doors, double doors or glass doors. The applicant has not provided adequate explanations for those anomalies either in its reply or at the hearing.
76 In that regard, the Court observes that, although Article 30(4) of Directive 93/37 does not require the Council to check each price quoted in each tender, it must examine the reliability and seriousness of the tenders which it considers to be generally suspect, which necessarily means that it must ask, if appropriate, for details of the individual prices which seem suspect to it, a fortiori when there are many of them. Furthermore, the fact that the applicant's tender was considered to conform to the contract documents did not relieve the Council of its obligation, under the same article, to check the prices of a tender if doubts arose as to their reliability during the examination of the tenders and after the initial assessment of their conformity."
155. In relation to Renco, Mr Howell submitted that it was not a case where the European Court was saying that there was a duty to investigate all tenders which appeared abnormally low irrespective of whether they were going to be rejected. In my judgment that submission is correct. Neither Renco nor the earlier case in the European Court of Justice of Impresa Lombardini v ANAS [2001] ECR I-9233, to which Arnold J refers, were cases where the issue arose directly for decision whether the relevant authority owed a duty to investigate "abnormally low" tenders generally, as opposed to where the authority was considering rejecting the tender. In both those cases, the authority was proposing to reject the tenders in question. Furthermore, although the point did not arise directly in the later decision of the General Court in TQ3 Travel Solutions Belgium SA v The Commission [2005], in my judgment it is implicit in the reasoning of the Court at paragraphs 49 and 50 that the relevant authority is not under a duty to investigate a tender which appears abnormally low unless it intends to reject it.
156. Mr Howell submitted that Arnold J had misread the Directive as imposing an obligation to investigate "suspect" tenders generally, when it did not, save in cases where the authority was proposing to reject the tender in question. I agree with that submission. In my judgment, despite the difference of wording, there is no difference in substance between the provisions of the Directive and those of the Regulations. The thrust of both provisions is that an authority cannot reject a tender which is abnormally low unless it does certain things in terms of investigating that tender. For present purposes, there is no difference between saying that you shall do certain things before an entitlement to reject arises and saying that you may reject the tender provided you have done certain things.
157. Either way, there is nothing in either provision to support the contention that there is a general duty owed by the authority to investigate so-called "suspect" tenders which appear abnormally low. Nothing in the European Court decisions to which Arnold J refers dictates a different conclusion. In any event, Morrison is only a decision as to what was arguable on an interlocutory basis. Having heard full argument on the point at trial I am quite satisfied that neither the Directive nor the Regulation imposes a duty to investigate so-called suspect tenders generally.
158. It follows that, on the correct interpretation of both the Directive and the Regulation (save in the case of Fourways where the Council did consider the tender abnormally low and was contemplating rejecting the tender at least in part if not totally), the Council was not under a duty generally to investigate so-called "suspect" tenders in circumstances where the Council had no intention of rejecting those tenders. In my judgment, this aspect of Varney's complaint that the Council was in breach of duty in failing to investigate the tenders other than Fourways fails at the first hurdle.
159. Furthermore, I consider that there is another fundamental obstacle to Varney's case that the Council was in breach of duty in failing to investigate the other tenders. Although Regulation 30(6) talks in the abstract of an offer which is abnormally low, the Directive refers to tenders which "appear to be abnormally low" which only makes sense as a reference to what "appears" to the relevant authority. In the circumstances, it seems to me that the duty for which Varney contends could only arise where the Council either knows or suspects that the tender in question is abnormally low. Leaving Fourways out of account, it is quite clear on the evidence of Mr Shaw and Mr King (which I accept) that neither of them actually knew or suspected that the other tenders were abnormally low.
160. Mr Coppel contended in his cross-examination of Mr Shaw and Mr King and in his submissions that the Council ought to have known or suspected that the other tenders were abnormally low. He submitted that it was a manifest error to have accepted tenders which the Council should have recognised as unsustainable. Alternatively, he submitted that there was a duty to reject such tenders. In terms of what is the correct test in law, I am firmly of the view that the duty for which Varney contends (even if, contrary to the decision I have already indicated, such a duty could arise) cannot arise save in the case where the relevant authority actually knows or suspects that a tender is abnormally low. What it is contended an authority ought to have known or suspected, but did not know or suspect, is not sufficient to impose the duty for which Varney contends. Were it otherwise, an authority would have to investigate all tenders in detail to satisfy itself of the economic viability of each tender, an unrealistic and onerous burden"
(a) It is important, legitimate and proper to interpret statutory instruments in this country which deal with public procurement in the light of EC Directives and legislation. The implementation of such directives and legislation is left to the British legislature. Provided however that the statutory instrument in question is, properly construed, drafted in such a way as not to offend against the contents of EC Directives and legislation, it can be enforced.
(b) The relevant Directives do not require the contracting authority (or GAL assuming it is a utility in this case) to determine whether or not a tender is abnormally low. What they do address is what is to happen if the authority does determine or consider that a given tender is "abnormally low". The authority in those circumstances must, but only if it is considering an option to reject that abnormally low tender, give the relevant tenderer the opportunity to explain itself. The Utilities Contract Regulations 2006 are, in this context, not inconsistent with the relevant Directives.
(c) There is no definition either in the Directives or in the 2006 Regulations as to what "abnormally low" means. Various expressions are used in the European decisions, but often not by way of definition: "genuine" (Lombardini and Fratelli), "genuine and viable" or "sound and viable" (SECAP Case C- 147/06 [2008] 2 CMLR 56), "reliable and serious" (Renco and TQ3 Travel Solutions Belgium) or "serious" (PC-Ware Information Technologies BV T-121/08 [2010] ECRII-1541). I would not wish to add to any confusion but the words "abnormally low" must encompass a bid which is low (and almost invariably lower than the other tenderers) and the bid must be beyond and below the range of anything which might legitimately (in the context of a particular procurement) be considered to be normal. Obviously, a bid which is ridiculously low and which could not be justified on any intelligible commercial basis might well not be considered as genuine and therefore could well be abnormally low. A very low bid which is effectively illegal, such as what is sometimes referred to as "predatory pricing" by a tenderer in effect to eliminate competition, can be rejected because it undermines competition and comprehensiveness and itself runs counter to general Treaty and other European requirements.
(d) There is no obligation on the part of utilities or contracting authorities to determine or consider that bids are "abnormally low". There is no obligation to reject "abnormally low" bids. There is no such express statutory requirement or any expressed requirement in the Directives or European legislation, all of which are primarily directed to giving rights to a tenderer, which has submitted what is considered by the utility or contracting authority to be an abnormally low tender, to be given by the utility or contracting authority the chance to explain itself before its tender is rejected. The Court should be very slow to interpret the 2006 Regulations as imposing some obligation on the contracting authoritu or utility to determine that either there is or might be an abnormally low tender. It is not usual to imply obligations into a statute or statutory instrument in the same way as in this country one implies terms into contracts; that is not to say that a purposive interpretation of statutes is not permissible (it often is).
(e) If that is right, it would not be necessary to consider whether there was independently some "manifest error" on the part of the given contracting authority or utility in failing to appreciate that there was or might have been an abnormally low tender. However, at best, even if the "manifest error" approach could in these circumstances sensibly be adopted, one would have to be able to determine that it was an error which no reasonable contracting authority or utility could realistically have made.
"69. The appeal in Worldwide Corporation v GPT Ltd was by the Claimants against the refusal of Moore-Bick J in the Commercial Court to permit amendments to the claim in the first week or so of the trial, amendments prompted not by discovery of some unsuspected evidence or fact but by a re-appraisal by newly instructed Counsel of the merits of the case. It was said that he felt that the case previously pleaded would fail and that only by way of the amendment could the case be put on an arguable basis. Waller LJ gave the judgment of the court, setting out the reasons why the appeal had been dismissed. Mr Stanley Brodie Q.C. for the Claimants relied on observations as to the generous approach of the court to amendments required to enable the true issues between the parties to be resolved, so long as any injustice can be avoided, mainly by terms as to costs: Bowen LJ in Cropper v Smith (1884) 26 Ch D 700 at 710-711 is one of the classic statements of this attitude. Another is that of Brett MR in Clarapede & Co v Commercial Union Association (1883) 32 WR 262 at 263. More recent statements include that of Millett LJ in Gale v Superdrug Stores plc [1996] 1 WLR 1089 at 1098 and following. The court in Worldwide Corporation v GPT said this about this attitude:
"We are doubtful whether even applying the principle stated by Bowen LJ, the matter is so straightforward as Mr Brodie would seek to persuade us. But, in addition, in previous eras it was more readily assumed that if the amending party paid his opponent the costs of an adjournment that was sufficient compensation to that opponent. In the modern era it is more readily recognised that in truth the payment of the costs of an adjournment may well not adequately compensate someone who is desirous of being rid of a piece of litigation which has been hanging over his head for some time, and may not adequately compensate him for being totally (and we are afraid there are no better words for it) "mucked about" at the last moment. Furthermore the courts are now much more conscious that in assessing the justice of a particular case the disruption caused to other litigants by last minute adjournments and last minute applications have also to be brought into the scales."
70. Later in the judgment the court said this under the heading "Approach to last minute amendments":
"Where a party has had many months to consider how he wants to put his case and where it is not by virtue of some new factor appearing from some disclosure only recently made, why, one asks rhetorically, should he be entitled to cause the trial to be delayed so far as his opponent is concerned and why should he be entitled to cause inconvenience to other litigants? The only answer which can be given and which, Mr Brodie has suggested, applies in the instant case is that without the amendment a serious injustice may be done because the new case is the only way the case can be argued, and it raises the true issue between the parties which justice requires should be decided.
We accept that at the end of the day a balance has to be struck. The court is concerned with doing justice, but justice to all litigants, and thus where a last minute amendment is sought with the consequences indicated, the onus will be a heavy one on the amending party to show the strength of the new case and why justice both to him, his opponent and other litigants requires him to be able to pursue it."
71. The court also recognised, as I do, the reluctance with which an appellate court will interfere with discretionary case management decisions, perhaps especially those of a trial judge.
72. As the court said, it is always a question of striking a balance. I would not accept that the court in that case sought to lay down an inflexible rule that a very late amendment to plead a new case, not resulting from some late disclosure or new evidence, can only be justified on the basis that the existing case cannot succeed and the new case is the only arguable way of putting forward the claim. That would be too dogmatic an approach to a question which is always one of balancing the relevant factors. However, I do accept that the court is and should be less ready to allow a very late amendment than it used to be in former times, and that a heavy onus lies on a party seeking to make a very late amendment to justify it, as regards his own position, that of the other parties to the litigation, and that of other litigants in other cases before the court.
73. A point which also seems to me to be highly pertinent is that, if a very late amendment is to be made, it is a matter of obligation on the party amending to put forward an amended text which itself satisfies to the full the requirements of proper pleading. It should not be acceptable for the party to say that deficiencies in the pleading can be made good from the evidence to be adduced in due course, or by way of further information if requested, or as volunteered without any request. The opponent must know from the moment that the amendment is made what is the amended case that he has to meet, with as much clarity and detail as he is entitled to under the rules.
74. The Worldwide Corporation decision was made under the RSC, not the CPR, which only came into force some five months later, but it seems to me that it reflects the tenor of the CPR, which was no doubt in the minds of the judges, who will have been very familiar with the terms of Lord Woolf's reports that led to the reform of the rules. As appears from the passage quoted above from Savings & Investment Bank v Fincken, it has been endorsed as appropriate under the CPR."
"This is a bad claim as is apparent from the documents themselves. Commentary upon the award decision at board level does not amount to a retaking of the decision on the basis of new criteria. This claim is bad and the key documents are before the Court to demonstrate that. This is dealt with by Elizabeth Townsend from paragraphs 16 to 19 of her witness statement."
Essentially, it is argued, largely on the facts, that the relevant decision making board made its decision in effect only on the basis that DFS had "won" and had the best tender score and not on the basis of any of the supposedly extraneous factors which arguably may have been referred to in papers prepared for the purpose of seeking the decision. I consider that this is primarily a question of fact and, although the argument and indeed the evidence of Ms Townsend as presented may turn out to be right, it will all be a question of evidence as to the basis on which, factually, the decision was taken. It is not suggested that there will be any logistic difficulty in GAL dealing with this allegation or in requisite members of the Board or Board sub-group answering questions as to whether they did take into account any (arguably unacceptable) factors in reaching their decision. I will therefore allow this amendment.
Specific Disclosure