QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Rolls Building, 7 Rolls Buildings London EC4A 1NL |
||
B e f o r e :
____________________
Lovell Partnerships Limited Connaught Partnerships Ltd (in liquidation) |
Claimants |
|
- and - |
||
Merton Priory Homes |
Defendant |
____________________
(instructed by Pinsent Masons LLP) for the Claimants
Jonathan Acton Davis Esq, QC (instructed by Trowers & Hamlins LLP) for the Defendant
Hearing dates: 8th May 2014
____________________
Crown Copyright ©
Mr. Justice Edwards-Stuart:
The facts
The relevant terms of the contract
"13.5 If any Partnering Team Member …
(b) being a body corporate ... has an administrator appointed (whether by the Court or otherwise) ...
then, in any such case, the appointment of that Partnering Team Member under the Partnering Contract shall automatically terminate that Contract or, if that Partnering Team Member is the Client, then the appointment of all other Partnering Team Members shall automatically terminate with immediate effect.
13.6 In the event that any Partnering Team Member shall breach the Partnering Contract so as to have a demonstrable adverse effect on the implementation of the Term Programme or any Task and shall not remedy such breach within ten (10) Working Days from the date of notice from another Partnering Team Member specifying the breach then, after notifying the Core Group and allowing a period of ten (10) Working Days from the date of such notification to receive and consider their recommendations, the notifying Partnering Team Member (if it not the Client) may terminate its own appointment under the Partnering Contract or, (if it is the Client) may terminate the appointment of the Partnering Team Member in breach, in each case by notice with immediate effect.
13.7 If stated in the Term Partnering Agreement that this Clause 13.7 applies, the Client shall be entitled to terminate the appointment of any other Partnering Team Member by notice with immediate effect if that Partnering Team Member gives any payment or other reward the receipt of which is an offence under Section 117(2) of the Local Government Act.
13.8 In the event of termination in accordance with Clauses 13.2, 13.3 or 13.4 or by reason of Client bankruptcy or insolvency under Clause 13.5 or by any Partnering Team Member of its own appointment in accordance with Clause 13.6 the relevant Partnering Team Member(s) shall be entitled to payment in accordance with Clause 7 of the total amount(s) properly due up to the date of termination.
13.9 In the event of termination of any other Partnering Team Member's appointment by reason of its bankruptcy or insolvency under Clause 13.5 or by the Client in accordance with Clauses 13.6 or 13.7 the Client shall not be bound to make any further payment to that Partnering Team Member and may complete all Tasks using others in place of that Partnering Team Member.
13.10 Termination of the appointment of any Partnering Team Member shall not affect the mutual rights and obligations of the Partnering Team Members accrued at the date of termination."
The interpretation of the contract - the submissions of the parties
"… the ultimate aim of interpreting a provision in a contract, especially a commercial contract, is to determine what the parties meant by the language used, which involves ascertaining what a reasonable person would have understood the parties to have meant."
"... undertake and complete the Task in accordance with each Order and the other Partnering Documents, in consideration for which the client shall pay to the Service Provider the relevant Task Price ... ."
My conclusions and reasons
i) Mr. Acton Davis's interpretation of clause 13.10 involves reading into the clause words that are not there.ii) Clause 13.10 is a freestanding clause. It is not made subject to clause 13.9 by the introduction of words such as "Subject to clause 13.9 ...".
iii) I consider that clauses 13.8 and 13.9 have to be read together. They are addressing different insolvency situations, and it makes commercial sense that clause 13.8 should confer a right to swift payment under clause 7 where it is the Client, and not the Service Provider, who is insolvent. Clause 13.9, by contrast, concerns the situation where the Service Provider is the party who is insolvent and it is quite logical that it should provide that it should not have the benefit of the swift payment machinery under clause 7 which gives the Client no further right of set-off following the prior issue of its valuation. It does not seem to me to be stretching the language to treat the words "any further payment" in clause 13.9 as a reference to a payment under the contractual machinery, being one that can arise as of right once certain conditions are fulfilled.
iv) There is no saving provision in clause 13.9 to permit payment of money that has already fallen due for payment but which has not been paid, or where there has been a course of previous undervaluation. As Lord Hoffmann said in Melville Dundas (supra), at [13]:
"A provision such as clause 27.6.5.1, which gives the employer a limited right to retain funds by way of security for his cross-claims, seems to me a reasonable compromise between discouraging employers from retaining interim payments against the possibility that a contractor who is performing the contract might become insolvent at some future date (which may well be self-fulfilling) and allowing the interim payment system to be used for the purpose for which it was never intended, namely to improve the position of an insolvent contractor's secured or unsecured creditors against the employer."In that case clause 27.6.5.1 gave the contractor the right to recover sums which the employer had unreasonably not paid and which had been outstanding for 28 days before the date of termination. Conversely, there was no provision in that contract that was the equivalent of clause 13.10.v) The effect of depriving clause 13.10 of any application to an accrued entitlement to the payment of money under clause 7 would have the effect of preferring other creditors of the Service Provider over the Client, thereby undermining the general principles of insolvency. Instead of the Client being able to retain the amount of the valuation against any loss it may have suffered by reason of defective work carried out by the Service Provider, it would have to pay it straight out so that it would become part of the assets available for general distribution to the Service Provider's creditors. This was a factor that influenced the majority of the members of the House of Lords in Melville Dundas, and I can see no reason why the same approach should not apply here.
vi) While I can see that in some situations there may be no commercial objection to devising a scheme that leaves a loss to lie where it falls in the event of one party's insolvency, it is not all obvious that this would reflect the intention of the parties if it extended to accrued rights to sums which had fallen due for payment but which had remained unpaid. Mr. Acton Davis said that this objection could be met by the application of the well-known principle in Alghussein Establishment v Eton College [1998] 1 WLR 587, that a party cannot be allowed to take advantage from his own breach of contract. Whilst this principle can be invoked to prevent this, there is very good authority for the proposition that it can also be deployed as a rule of construction: see Alghussein, per Lord Jauncey at 593G-H; Lewison on The Interpretation of Contracts, Fifth Edition, at paragraph 7.10. It seems to me that this is a further reason for not construing clause 13.9 in a manner such that, in a situation where the Client's Representative had made persistent undervaluations of a Service Provider's applications, the Client would (assuming that its representative had acted in good faith) escape any liability to pay a proper amount in respect of those applications following the appointment of an administrator over the Service Provider.
Disposal
"On its true construction the reference to 'any further payment' in clause 13.9 refers to any further payment to which the Service Provider would or might otherwise be entitled pursuant to the contractual provisions relating to payment under clause 7 of the contract. The clause does not prevent the Service Provider from pursuing separately, by way of adjudication, arbitration or litigation, any rights or obligations that had accrued by the date of termination."
Note 1 At paragraph 19 of its skeleton argument Merton said this: “... The Employer is at liberty to complete the work using others. The balancing fact is that the Contract does not contain a clause permissive of recovery of the inevitable consequential costs to the Employer arising out of the termination under Clause 13.5. Thus, absent a claim for breach of contract, no right of set-off arises out of such costs.” [Back]