QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Rolls Building |
||
B e f o r e :
____________________
CO-OPERATIVE GROUP LIMITED | Claimant | |
- and - | ||
BIRSE DEVELOPMENT LIMITED | Defendant | |
- and - | ||
STUARTS INDUSTRIAL FLOORING LIMITED | Third Party | |
- and - | ||
JUBB & PARTNERS | Fourth Party |
____________________
MR. S. HUGHES QC and MR. T. LAZUR (instructed by DAC Beachcroft LLP) appeared on behalf of the Claimant.
MS. F. SINCLAIR QC and MR. R. LIDDELL (instructed by Clyde & Co LLP) appeared on behalf of the Defendant.
MR. M. CANNON QC and MS. K. POWELL (instructed by Reynolds Porter Chamberlain LLP) appeared on behalf of the Third Party.
MR. B. PILLING (instructed by Beale & Co LLP) appeared on behalf of the Fourth Party.
____________________
Crown Copyright ©
MR. JUSTICE AKENHEAD:
"So far as costs are concerned, I anticipate that the defending parties will seek their costs but they may feel that it would be difficult for the court to do a summary assessment and that an interim payment on account of costs may be more appropriate."
Then I said:
"At the handing down of the judgement, I will deal with any issues on further directions and costs."
"In addition, all of the defending parties would have incurred substantial costs in connection with the claimant's attempts to secure permission to amend and costs have been wasted on serial draft re-amendments in the Part 20 claims. Birse alone has incurred in excess of £753,523 in fees and disbursements since directions were provided for the Co-op's application to amend in June 2012. Since little else has happened procedurally since June 2012, the majority of these costs relate to the amendment question."
I took that into account at face value to infer that a substantial, indeed very substantial, part of that amount of costs had been incurred since the first application to re-amend was issued in mid-2012, initially dealt with by His Honour Judge Davis and which then made its way to the Court of Appeal for judgment in May 2013.
MR. PILLING: My Lord, would you like a figure?
MR. JUSTICE AKENHEAD: I have probably got a figure, actually, £25,630.50, not challenged by the claimant. So there will be an order on the summary costs assessment in that figure. Those should all be payable within 14 days.