QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
Pioneer Cladding Limited |
Claimant |
|
- and - |
||
John Graham Construction Limited |
Defendant |
____________________
Ms Anna Laney (instructed by Barton Legal Limited) for the Defendant
Hearing date: 26 September 2013
____________________
Crown Copyright ©
The Honourable Mr Justice Coulson:
"(i) Should any dispute arise under this Sub-Contract, the same may referred to an Adjudicator (to be agreed between the parties) or in default of agreement, in the manner hereinafter set out...
(ii) The Adjudication should be carried out in accordance with the Housing Grants, Construction and Regeneration Act 1996 and the Model Adjudication Procedure ('MAP') published by the Construction Industry Council subject to the amendments set out in schedule 5 hereto.
(iii) Notwithstanding clause 29 of MAP the Adjudicator's fees are to be borne by the Party which refers the dispute to adjudication…
(v) In the event that the decision of the Adjudicator is the making of a monetary award ("Adjudicator's Award") in favour of the Sub-Contractor, the following provision shall apply:-
(a) Graham shall place on deposit the amount of the Adjudicator's award with Northern Bank Limited in the joint names of the solicitors acting for Graham and solicitors acting for the Sub-Contractor within seven days from the date of receipt by Graham of the Adjudicator's decision."
"a) Adjudication (whether pursuant to the 1996 Act or the consequential amendments to the standard forms of building and engineering contracts) is designed to be a quick and inexpensive method of arriving at a temporary result in a construction dispute.
b) In consequence, adjudicators' decisions are intended to be enforced summarily and the claimant (being the successful party in the adjudication) should not generally be kept out of its money.
c) In an application to stay the execution of summary judgment arising out of an Adjudicator's decision, the Court must exercise its discretion under Order 47 with considerations a) and b) firmly in mind (see AWG).
d) The probable inability of the claimant to repay the judgment sum (awarded by the Adjudicator and enforced by way of summary judgment) at the end of the substantive trial, or arbitration hearing, may constitute special circumstances within the meaning of Order 47 rule 1(1)(a) rendering it appropriate to grant a stay (see Herschell).
e) If the claimant is in insolvent liquidation, or there is no dispute on the evidence that the claimant is insolvent, then a stay of execution will usually be granted (see Bouygues and Rainford House).
f) Even if the evidence of the claimant's present financial position suggested that it is probable that it would be unable to repay the judgment sum when it fell due, that would not usually justify the grant of a stay if:
(i) the claimant's financial position is the same or similar to its financial position at the time that the relevant contract was made (see Herschell); or
(ii) The claimant's financial position is due, either wholly, or in significant part, to the defendant's failure to pay those sums which were awarded by the adjudicator (see Absolute Rentals)."
(i) Is it probable that Pioneer would be unable to repay the £188,665.49 if that was the outcome of the ongoing arbitration?(ii) Is Pioneer's financial position the same or similar to the financial position of which Graham was aware at the time that the contract was made?
(iii) Is Pioneer's financial position due either wholly or in significant part to Graham's failure to pay the sums awarded by the Adjudicator?
(a) The original accounts for the year ending November 2012 show losses of £212,950.(b) Even the amended accounts show net assets of just £1,382. I deal with the fact that there are two different figures in further detail below.
(c) There are five County Court Judgments outstanding against Pioneer which have been entered since the 16th May 2013, totalling £61,440. Indeed all but £6,601 of that sum relates to County Court Judgments entered in the last five weeks. The biggest single Judgment of all, namely £38,859, has not been specifically addressed by Mr Lloyd, the relevant director of Pioneer, anywhere in his evidence.
(d) Generally in relation to these debts, Mr Lloyd has said in his first statement that Pioneer 'simply does not have the money to settle the judgments at this stage'. In my view, that is a clear and unqualified admission that Pioneer are technically insolvent.